Northwest Pipeline LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Union Meter Station Upgrade Project and Request for Comments on Environmental Issues, 18394-18396 [2015-07768]

Download as PDF 18394 Federal Register / Vol. 80, No. 65 / Monday, April 6, 2015 / Notices SUPPLEMENTARY INFORMATION: DEPARTMENT OF ENERGY Purpose of the Board: The purpose of the Board is to make recommendations to DOE–EM and site management in the areas of environmental restoration, waste management, and related activities. Tentative Agenda Topics: Wednesday, April 22, 2015 Æ EM Program Update Æ EM SSAB Chairs’ Round Robin: Topics, Achievements, and Accomplishments Æ EM Budget Update Æ Roundtable Discussion: DOE Communication Strategies Æ Public Comment Period tkelley on DSK4VPTVN1PROD with NOTICES Thursday, April 23, 2015 Æ DOE Headquarters News and Views Æ EM Headquarters Waste Disposition Update Æ EM Safety Culture Presentation Æ Public Comment Public Participation: The EM SSAB Chairs welcome the attendance of the public at their advisory committee meetings and will make every effort to accommodate persons with physical disabilities or special needs. If you require special accommodations due to a disability, please contact David Borak at least seven days in advance of the meeting at the phone number listed above. Written statements may be filed either before or after the meeting with the Designated Federal Officer, David Borak, at the address or telephone listed above. Individuals who wish to make oral statements pertaining to agenda items should also contact David Borak. Requests must be received five days prior to the meeting and reasonable provision will be made to include the presentation in the agenda. The Designated Federal Officer is empowered to conduct the meeting in a fashion that will facilitate the orderly conduct of business. Individuals wishing to make public comment will be provided a maximum of five minutes to present their comments. Minutes: Minutes will be available by writing or calling David Borak at the address or phone number listed above. Minutes will also be available at the following Web site: https:// www.em.doe.gov/stakepages/ ssabchairs.aspx. Issued at Washington, DC, on March 30, 2015. LaTanya R. Butler, Deputy Committee Management Officer. [FR Doc. 2015–07804 Filed 4–3–15; 8:45 am] BILLING CODE 6450–01–P VerDate Sep<11>2014 18:14 Apr 03, 2015 Jkt 235001 Federal Energy Regulatory Commission [Docket No. CP15–110–000] Northwest Pipeline LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Union Meter Station Upgrade Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Union Meter Station Upgrade Project involving construction and operation of facilities by Northwest Pipeline LLC (Northwest) in Union County, Oregon. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on April 27, 2015. You may submit comments in written form or verbally. Further details on how to submit written comments are in the Public Participation section of this notice. If you sent comments on this project to the Commission before the opening of this docket on March 6, 2015, you will need to file those comments in Docket No. CP15–110–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 determined in accordance with state law. Northwest provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Summary of the Proposed Project Northwest proposes to modify its existing meter station in Grande Ronde Valley, southeast of La Grande, Union County, Oregon. The Union Meter Station Upgrade Project would increase the existing Union Meter Station’s capacity from approximately 3,120,000 to 5,500,000 standard cubic feet per day of natural gas in accordance with a Facility Agreement between Northwest and Avista Corporation, a local distribution company. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction The project would require approximately 0.2 acre of total surface use occurring on previously disturbed and graveled land. Project construction would occur within the existing 50-footwide by 100-foot-long Union Meter Station property. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\06APN1.SGM 06APN1 Federal Register / Vol. 80, No. 65 / Monday, April 6, 2015 / Notices In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • geology and soils; • land use; • water use and quality; • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; and • public safety. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section beginning on page 4. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act tkelley on DSK4VPTVN1PROD with NOTICES In accordance with the Advisory Council on Historic Preservation’s implementing regulations for Section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 We will define the 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic VerDate Sep<11>2014 18:14 Apr 03, 2015 Jkt 235001 project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under Section 106. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before April 27, 2015. For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP15–110–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 18395 Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) whose property may be used temporarily for project purposes, or who own property within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP15–110). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The E:\FR\FM\06APN1.SGM 06APN1 18396 Federal Register / Vol. 80, No. 65 / Monday, April 6, 2015 / Notices eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ docs-filing/esubscription.asp. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: March 27, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–07768 Filed 4–3–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 803–105] tkelley on DSK4VPTVN1PROD with NOTICES Pacific Gas and Electric Company; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Application for Temporary Variance of Minimum Flow Requirement b. Project No.: 803–105 c. Date Filed: March 25, 2015 d. Applicant: Pacific Gas and Electric Company (licensee) e. Name of Project: DeSabla Centerville f. Location: Butte Creek and West Branch Feather River in Butte County, California g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Rich Doble, Senior License Coordinator, Pacific Gas and Electric Company, Mail Code: N11C, P.O. Box 770000, San Francisco, CA 94177. Phone (415) 973–4480 i. FERC Contact: Mr. John Aedo, (415) 369–3335, or john.aedo@ferc.gov j. Deadline for filing comments, motions to intervene, protests, and recommendations is 15 days from the issuance date of this notice by the Commission (April 14, 2015). The VerDate Sep<11>2014 18:14 Apr 03, 2015 Jkt 235001 Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P– 803–105) on any comments, motions to intervene, protests, or recommendations filed. k. Description of Request: The licensee requests Commission approval for a temporary variance of the minimum flow requirements of Article 39 of the project license. The licensee proposes to reduce flows from Philbrook Reservoir to 0.8 cubic feet per second (cfs) (with an additional 0.2 cfs flow buffer) to ensure the availability of cold water storage for spring-run Chinook salmon during the fish holding period in the summer. The licensee explains that current drought conditions have resulted in depressed storage levels in Philbrook Reservoir and that spring-run Chinook salmon have already entered Butte Creek. The licensee requests the above variance until June 1, 2015, or until conditions improve, as determined by the licensee and resource agencies at monthly meetings. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street, NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. PO 00000 Frm 00045 Fmt 4703 Sfmt 9990 m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the variance. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: March 30, 2015. Kimberly D. Bose, Secretary. [FR Doc. 2015–07763 Filed 4–3–15; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\06APN1.SGM 06APN1

Agencies

[Federal Register Volume 80, Number 65 (Monday, April 6, 2015)]
[Notices]
[Pages 18394-18396]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-07768]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-110-000]


Northwest Pipeline LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Union Meter Station Upgrade 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Union Meter Station Upgrade 
Project involving construction and operation of facilities by Northwest 
Pipeline LLC (Northwest) in Union County, Oregon. The Commission will 
use this EA in its decision-making process to determine whether the 
project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on April 27, 2015.
    You may submit comments in written form or verbally. Further 
details on how to submit written comments are in the Public 
Participation section of this notice. If you sent comments on this 
project to the Commission before the opening of this docket on March 6, 
2015, you will need to file those comments in Docket No. CP15-110-000 
to ensure they are considered as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Northwest provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including how to participate in the Commission's 
proceedings. It is also available for viewing on the FERC Web site 
(www.ferc.gov).

Summary of the Proposed Project

    Northwest proposes to modify its existing meter station in Grande 
Ronde Valley, southeast of La Grande, Union County, Oregon. The Union 
Meter Station Upgrade Project would increase the existing Union Meter 
Station's capacity from approximately 3,120,000 to 5,500,000 standard 
cubic feet per day of natural gas in accordance with a Facility 
Agreement between Northwest and Avista Corporation, a local 
distribution company.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    The project would require approximately 0.2 acre of total surface 
use occurring on previously disturbed and graveled land. Project 
construction would occur within the existing 50-foot-wide by 100-foot-
long Union Meter Station property.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.

---------------------------------------------------------------------------

[[Page 18395]]

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     geology and soils;
     land use;
     water use and quality;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species; and
     public safety.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section beginning on page 4.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for Section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under Section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before April 
27, 2015.
    For your convenience, there are three methods which you can use to 
submit your comments to the Commission. In all instances please 
reference the project docket number (CP15-110-000) with your 
submission. The Commission encourages electronic filing of comments and 
has expert staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for interested persons to 
submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) whose property may be used temporarily for project 
purposes, or who own property within certain distances of aboveground 
facilities, and anyone who submits comments on the project. We will 
update the environmental mailing list as the analysis proceeds to 
ensure that we send the information related to this environmental 
review to all individuals, organizations, and government entities 
interested in and/or potentially affected by the proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP15-
110). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The

[[Page 18396]]

eLibrary link also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: March 27, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-07768 Filed 4-3-15; 8:45 am]
BILLING CODE 6717-01-P