Missiles Generated by Extreme Winds, 18261-18262 [2015-07709]
Download as PDF
Federal Register / Vol. 80, No. 64 / Friday, April 3, 2015 / Notices
Title of Collection: Labor Standards
for the Registration of Apprenticeship
Programs.
OMB Control Number: 1205–0223.
Affected Public: Private Sector—
businesses or other for-profits;
Individuals and Households; State,
Local, and Tribal Governments.
Total Estimated Number of
Respondents: 141,129.
Total Estimated Number of
Responses: 141,779.
Total Estimated Annual Time Burden:
14,775 hours.
Total Estimated Annual Other Costs
Burden: $0.
Dated: March 30, 2015.
Michel Smyth,
Departmental Clearance Officer.
[FR Doc. 2015–07681 Filed 4–2–15; 8:45 am]
BILLING CODE 4510–FR–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2013–0161]
Missiles Generated by Extreme Winds
Nuclear Regulatory
Commission.
ACTION: Standard review plan- section
revision; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing a final
revision to the following section in
Chapter 3 of NUREG–0800, ‘‘Standard
Review Plan (SRP) for the Review of
Safety Analysis Reports for Nuclear
Power Plants: LWR Edition,’’ Section
3.5.1.4, ‘‘Missiles Generated by Extreme
Winds.’’
DATES: The effective date of this
Standard Review Plan revision is May 4,
2015.
ADDRESSES: Please refer to Docket ID
NRC–2013–0161 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0161. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual(s) listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
asabaliauskas on DSK5VPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:49 Apr 02, 2015
Jkt 235001
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it available in
ADAMS) is provided the first time that
a document is referenced. The final
revision for SRP Section 3.5.1.4,
‘‘Missiles Generated by Extreme
Winds,’’ is available in ADAMS under
Accession No. ML14190A180. The
previously issued draft revision for
public comment is available in ADAMS
under Accession No. ML13043A004.
• The NRC posts its issued staff
guidance on the NRC’s external Web
page: https://www.nrc.gov/reading-rm/
doc-collections/nuregs/staff/sr0800/.
FOR FURTHER INFORMATION CONTACT:
Jonathan DeGange, telephone: 301–415–
6992; email: Jonathan.DeGange@
nrc.gov, or Nishka Devaser, telephone:
301–415–5196; email: Nishka.Devaser@
nrc.gov, both are staff of the Office of
New Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
SUPPLEMENTARY INFORMATION:
I. Background
On August 8, 2013 (78 FR 48503), the
NRC staff published for public comment
the proposed revision to SRP Section
3.5.1.4, ‘‘Missiles Generated by Extreme
Winds.’’ The staff received no
comments on the proposed revision.
The staff is issuing the guidance in final
form for use. There have been no
changes made to the guidance since it
was issued in proposed form for public
comment. Details of specific changes
between current SRP guidance and the
revised guidance issued here are
included at the end of each of the
revised sections themselves, under the
‘‘Description of Changes,’’ subsections.
II. Backfitting and Issue Finality
This SRP section revision provides
guidance to the NRC staff for reviewing
applications for a construction permit
and an operating license under part 50
of Title 10 of the Code of Federal
Regulations (10 CFR), with respect to
the impacts of external missiles
generated by tornadoes and extreme
winds. The SRP also provides guidance
for reviewing an application for a
standard design approval; a standard
design certification; a combined license;
and a manufacturing license under 10
PO 00000
Frm 00074
Fmt 4703
Sfmt 4703
18261
CFR part 52 with respect to those same
subject matters.
Issuance of this final SRP section
revision does not constitute backfitting
as defined in 10 CFR 50.109 (the Backfit
Rule) nor is it inconsistent with the
issue finality provisions in 10 CFR part
52. The NRC’s position is based upon
the following considerations.
1. The SRP positions would not
constitute backfitting, inasmuch as the
SRP is internal guidance to the NRC
staff.
The SRP provides internal guidance
to the NRC staff on how to review an
application for NRC regulatory approval
in the form of licensing. Changes in
internal staff guidance are not matters
for which either nuclear power plant
applicants or licensees are protected
under either the Backfit Rule or the
issue finality provisions of 10 CFR part
52.
2. The NRC staff has no intention to
impose the SRP positions on existing
licensees and regulatory approvals
either now or in the future.
The NRC staff does not intend to
impose or apply the positions described
in the SRP to existing licenses and
regulatory approvals. Hence, the
issuance of this SRP—even if
considered guidance within the purview
of the issue finality provisions in 10
CFR part 52—does not need to be
evaluated as if it were a backfit or as
being inconsistent with issue finality
provisions. If, in the future, the NRC
staff seeks to impose a position in the
SRP on holders of already-issued
licenses in a manner that does not
provide issue finality as described in the
applicable issue finality provision, then
the staff must make the showing as set
forth in the Backfit Rule or address the
criteria for avoiding issue finality as
described in the applicable issue finality
provision.
3. Backfitting and issue finality do
not—with limited exceptions not
applicable here—protect current or
future applicants.
Applicants and potential applicants
are not, with certain exceptions,
protected by either the Backfit Rule or
any issue finality provisions under 10
CFR part 52. Neither the Backfit Rule
nor the issue finality provisions under
10 CFR part 52—with certain
exclusions—were intended to apply to
every NRC action that substantially
changes the expectations of current and
future applicants.
The exceptions to the general
principle are applicable whenever an
applicant references a 10 CFR part 52
license (e.g., an early site permit) or
NRC regulatory approval (e.g., a design
certification rule) with specified issue
E:\FR\FM\03APN1.SGM
03APN1
18262
Federal Register / Vol. 80, No. 64 / Friday, April 3, 2015 / Notices
finality provisions. The staff does not, at
this time, intend to impose the positions
represented in the SRP in a manner that
is inconsistent with any issue finality
provisions. If, in the future, the staff
seeks to impose a position in the SRP
section in a manner that does not
provide issue finality as described in the
applicable issue finality provision, then
the staff must address the criteria for
avoiding issue finality as described in
the applicable issue finality provision.
III. Congressional Review Act
This action is a rule as defined in the
Congressional Review Act (5 U.S.C.
801–808). However, the Office of
Management and Budget has not found
it to be a major rule as defined in the
Congressional Review Act.
Dated at Rockville, Maryland, this 24th day
of March, 2015. For the Nuclear Regulatory
Commission.
Joseph Colaccino,
Chief, New Reactor Rulemaking and
Guidance Branch, Division of Advanced
Reactors and Rulemaking, Office of New
Reactors.
[FR Doc. 2015–07709 Filed 4–2–15; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2008–0252; Docket Nos. 52–025 & 52–
026; Combined License Nos. NPF–91 &
NPF–92]
In the Matter of Municipal Electric
Authority of Georgia (Vogtle Electric
Generating Plant, Units 3 & 4); Order
Extending the Date by Which the Direct
Transfer of Licenses Is To Be
Completed
asabaliauskas on DSK5VPTVN1PROD with NOTICES
II
The U.S. Nuclear Regulatory
Commission’s (NRC’s) order, dated
April 29, 2014, approved three direct
transfers of portions of MEAG Power’s
22.7 percent undivided ownership
interest in VEGP, Units 3 and 4. Each of
these three transfers may occur
independently of, or in conjunction
with, the others, as follows:
(1) Transfer of a 7.6886571 percent
undivided interest in VEGP, Units 3 and
4, from MEAG Power to MEAG Power
SPVM, LLC (Project M);
(2) transfer of a 9.3466423 percent
undivided interest in VEGP, Units 3 and
4, from MEAG Power to MEAG Power
SPVJ, LLC (Project J); and
(3) transfer of a 5.6647006 percent
undivided interest in VEGP, Units 3 and
4, from MEAG Power to MEAG Power
SPVP, LCC (Project P).
The application for the transfers was
in connection with the finalization of
three loans from the U.S. Federal
Finance Bank (U.S. FFB) or one or more
third-party lenders to be guaranteed by
the U.S. Department of Energy (DOE)
through its loan guarantee program for
the development of advanced nuclear
energy facilities. By its terms, the April
29, 2014, order stated that, ‘‘Should the
transfer of the license not be completed
within one year of this Order’s date of
issue, this Order shall become null and
void, provided, however, that upon
written application and for good cause
shown, such date may be extended by
order.’’
III
I
Georgia Power Company, Oglethorpe
Power Corporation, Municipal Electric
Authority of Georgia (MEAG Power), the
City of Dalton, Georgia, an incorporated
municipality in the State of Georgia
citing by and through its Board of
Water, Light and Sinking Fund
Commissioners (City of Dalton), and
Southern Nuclear Operating Co., Inc.
(SNC) (collectively, the owners) are
holders of combined license (COL) Nos.
NPF–91 and NPF–92. These COLs
authorize SNC to construct, possess,
use, and operate Vogtle Electric
Generating Plant (VEGP), Units 3 and 4,
and the owners to possess but not
operate VEGP, Units 3 and 4. The
facility, which is currently under
construction, is adjacent to existing
VEGP, Units 1 and 2, on a 3,169-acre
coastal plain bluff on the southwest side
of the Savannah River in eastern Burke
County, GA. The facility is
VerDate Sep<11>2014
approximately 15 miles east-northeast of
Waynesboro, GA, and 26 miles
southeast of Augusta, GA.
17:49 Apr 02, 2015
Jkt 235001
By letter dated February 12, 2015,
SNC on behalf of MEAG Power
requested that the April 29, 2014, order
be extended by 6 months, to October 29,
2015. SNC, in its February 12, 2015,
letter states that:
Diligent efforts have been made to
negotiate the definitive financing agreements
with the DOE. Those negotiations have, for
the most part, concluded. However, certain
provisions in those agreements necessitated
amendments to preexisting long term ‘‘cost
passthrough [sic]’’ contracts between MEAG
Power and the counterparties (offtakers) to
those contracts. While those negotiations
took much longer than MEAG Power
anticipated when the license transfer
application was submitted in December 2013,
those negotiations have concluded, and
amended contracts, dated December 31,
2014, were executed by MEAG Power and
each of the offtakers. In addition, on
December 23, 2014, MEAG Power’s board
approved, in substantially final form, the
definitive financing agreements among
PO 00000
Frm 00075
Fmt 4703
Sfmt 4703
MEAG Power, the Project Companies, and
DOE. All that remains at this juncture is the
receipt of certain promissory notes and other
financing documents from the U.S. FFB. At
that point, MEAG Power will be in a position
to cause judicial proceedings to be instituted
in State court to validate the DOE-guaranteed
loans (including the definitive agreements)
and the new offtake arrangements with the
project companies and to re-validate the
existing arrangements (including the bond
resolutions and the amended offtake
arrangements with the offtakers), all of which
include a validation of the enforceability of
all of these arrangements in connection with
the planned DOE-guaranteed loans. In
addition to the validation proceedings, DOE
must also conclude its internal agency review
of the definitive agreements, which includes
input from the U.S. Office of Management
and Budget (OMB). While MEAG Power is
optimistic that the judicial proceedings will
result in validation of the agreements and
amended bond resolutions, which is a
condition of the financial closing of the DOEguaranteed loans from the U.S. FFB, and that
DOE and OMB will favorably review the
definitive loan agreements, it is difficult to be
certain that the final Federal review will be
concluded and the required State court order
will be issued in time to support a closing
of the transactions by April 29, 2015.
SNC further states that there have
been no changes in the information and
technical and financial qualifications
presented in its December 2, 2013,
request to transfer the licenses.
Moreover, the basis for granting that
request has not changed and remains
valid. The NRC staff notes that its basis
for approving the transfers of MEAG
Power’s licenses for VEGP, Units 3 and
4, is documented in its safety evaluation
supporting the April 29, 2014, order.
Based on the foregoing representations
of SNC, the NRC staff concludes that the
basis for approval has not changed since
the issuance of the April 29, 2014,
order.
The NRC staff has considered the
submittal of February 12, 2015, and has
determined that good cause has been
shown to extend by 6 months, until
October 29, 2015, the date by which the
license transfers must be completed.
IV
Accordingly, under Sections 161b,
161i, and 184 of the Act, 42 U.S.C.
Sections 2201(b), 2201(i), and 2234; and
under Title 10, ‘‘Energy,’’ of the Code of
Federal Regulations Part 50.80,
‘‘Transfers of Licenses—Creditors’
Rights—Surrender of Licenses,’’ It Is
Hereby Ordered that the order granting
the direct license transfer, ‘‘Order
Approving Transfer of License and
Conforming Amendment,’’ dated April
29, 2014, be extended by 6 months, to
October 29, 2015. If the proposed direct
transfer of licenses is not completed by
October 29, 2015, this order and the
E:\FR\FM\03APN1.SGM
03APN1
Agencies
[Federal Register Volume 80, Number 64 (Friday, April 3, 2015)]
[Notices]
[Pages 18261-18262]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-07709]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2013-0161]
Missiles Generated by Extreme Winds
AGENCY: Nuclear Regulatory Commission.
ACTION: Standard review plan- section revision; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing a
final revision to the following section in Chapter 3 of NUREG-0800,
``Standard Review Plan (SRP) for the Review of Safety Analysis Reports
for Nuclear Power Plants: LWR Edition,'' Section 3.5.1.4, ``Missiles
Generated by Extreme Winds.''
DATES: The effective date of this Standard Review Plan revision is May
4, 2015.
ADDRESSES: Please refer to Docket ID NRC-2013-0161 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0161. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual(s) listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if it available in
ADAMS) is provided the first time that a document is referenced. The
final revision for SRP Section 3.5.1.4, ``Missiles Generated by Extreme
Winds,'' is available in ADAMS under Accession No. ML14190A180. The
previously issued draft revision for public comment is available in
ADAMS under Accession No. ML13043A004.
The NRC posts its issued staff guidance on the NRC's
external Web page: https://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/.
FOR FURTHER INFORMATION CONTACT: Jonathan DeGange, telephone: 301-415-
6992; email: Jonathan.DeGange@nrc.gov, or Nishka Devaser, telephone:
301-415-5196; email: Nishka.Devaser@nrc.gov, both are staff of the
Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Background
On August 8, 2013 (78 FR 48503), the NRC staff published for public
comment the proposed revision to SRP Section 3.5.1.4, ``Missiles
Generated by Extreme Winds.'' The staff received no comments on the
proposed revision. The staff is issuing the guidance in final form for
use. There have been no changes made to the guidance since it was
issued in proposed form for public comment. Details of specific changes
between current SRP guidance and the revised guidance issued here are
included at the end of each of the revised sections themselves, under
the ``Description of Changes,'' subsections.
II. Backfitting and Issue Finality
This SRP section revision provides guidance to the NRC staff for
reviewing applications for a construction permit and an operating
license under part 50 of Title 10 of the Code of Federal Regulations
(10 CFR), with respect to the impacts of external missiles generated by
tornadoes and extreme winds. The SRP also provides guidance for
reviewing an application for a standard design approval; a standard
design certification; a combined license; and a manufacturing license
under 10 CFR part 52 with respect to those same subject matters.
Issuance of this final SRP section revision does not constitute
backfitting as defined in 10 CFR 50.109 (the Backfit Rule) nor is it
inconsistent with the issue finality provisions in 10 CFR part 52. The
NRC's position is based upon the following considerations.
1. The SRP positions would not constitute backfitting, inasmuch as
the SRP is internal guidance to the NRC staff.
The SRP provides internal guidance to the NRC staff on how to
review an application for NRC regulatory approval in the form of
licensing. Changes in internal staff guidance are not matters for which
either nuclear power plant applicants or licensees are protected under
either the Backfit Rule or the issue finality provisions of 10 CFR part
52.
2. The NRC staff has no intention to impose the SRP positions on
existing licensees and regulatory approvals either now or in the
future.
The NRC staff does not intend to impose or apply the positions
described in the SRP to existing licenses and regulatory approvals.
Hence, the issuance of this SRP--even if considered guidance within the
purview of the issue finality provisions in 10 CFR part 52--does not
need to be evaluated as if it were a backfit or as being inconsistent
with issue finality provisions. If, in the future, the NRC staff seeks
to impose a position in the SRP on holders of already-issued licenses
in a manner that does not provide issue finality as described in the
applicable issue finality provision, then the staff must make the
showing as set forth in the Backfit Rule or address the criteria for
avoiding issue finality as described in the applicable issue finality
provision.
3. Backfitting and issue finality do not--with limited exceptions
not applicable here--protect current or future applicants.
Applicants and potential applicants are not, with certain
exceptions, protected by either the Backfit Rule or any issue finality
provisions under 10 CFR part 52. Neither the Backfit Rule nor the issue
finality provisions under 10 CFR part 52--with certain exclusions--were
intended to apply to every NRC action that substantially changes the
expectations of current and future applicants.
The exceptions to the general principle are applicable whenever an
applicant references a 10 CFR part 52 license (e.g., an early site
permit) or NRC regulatory approval (e.g., a design certification rule)
with specified issue
[[Page 18262]]
finality provisions. The staff does not, at this time, intend to impose
the positions represented in the SRP in a manner that is inconsistent
with any issue finality provisions. If, in the future, the staff seeks
to impose a position in the SRP section in a manner that does not
provide issue finality as described in the applicable issue finality
provision, then the staff must address the criteria for avoiding issue
finality as described in the applicable issue finality provision.
III. Congressional Review Act
This action is a rule as defined in the Congressional Review Act (5
U.S.C. 801-808). However, the Office of Management and Budget has not
found it to be a major rule as defined in the Congressional Review Act.
Dated at Rockville, Maryland, this 24th day of March, 2015. For
the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, New Reactor Rulemaking and Guidance Branch, Division of Advanced
Reactors and Rulemaking, Office of New Reactors.
[FR Doc. 2015-07709 Filed 4-2-15; 8:45 am]
BILLING CODE 7590-01-P