Combined Notice of Filings, 16667-16668 [2015-07164]
Download as PDF
Federal Register / Vol. 80, No. 60 / Monday, March 30, 2015 / Notices
PacifiCorp’s existing Threemile Knoll
Substation to connect the new line to
the regional transmission grid; and (4)
required ancillary facilities such as
access roads.
The new Hooper Springs Substation
will be constructed as a 138/115-kV
substation, meaning that it will include
a transformer capable of converting 138kV electricity to 115-kV electricity. BPA
will acquire 100-foot-wide right-of-way
for the length of the 115-kV line.
Approximately 174 new double-circuit
115-kV steel structures, ranging in
height from 55 to 120 feet with an
average span length between structures
of 730 feet, will be installed in this new
right-of-way. The BPA connection
facility will be located about two miles
southeast of the intersection of
Blackfoot River Road and Diamond
Creek Road and will consist of overhead
line disconnect switches to connect the
new 115-kV line to the existing LVE
line. For the single-circuit 138-kV
transmission line, two wood, H-frame
structures approximately 80 to 85 feet
tall will be installed within a new 125foot-wide right-of-way. A fiber optic
cable also will be installed along the
138-kV transmission line. About 14
miles of new access roads will be
constructed and about 2.4 miles of
existing access roads will be improved
or reconstructed. All mitigation
measures identified in the EIS are
adopted.
Copies of the ROD and EIS
may be obtained by calling BPA’s tollfree document request line, 1–800–622–
4520. The ROD and EIS are also
available on our Web site, https://
efw.bpa.gov/environmental_services/
Document_Library/HooperSprings/.
ADDRESSES:
Tish
Eaton, Bonneville Power
Administration—KEC–4, P.O. Box 3621,
Portland, Oregon 97208–3621; toll-free
telephone number 1–800–622–4519; fax
number 503–230–5699; or email
tkeaton@bpa.gov.
FOR FURTHER INFORMATION CONTACT:
Issued in Portland, Oregon on March 16,
2015.
Elliot E. Mainzer,
Administrator and Chief Executive Officer.
mstockstill on DSK4VPTVN1PROD with NOTICES
[FR Doc. 2015–07199 Filed 3–27–15; 8:45 am]
BILLING CODE 6450–01–P
VerDate Sep<11>2014
19:57 Mar 27, 2015
Jkt 235001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP15–656–000.
Applicants: Transcontinental Gas
Pipe Line Company.
Description: Section 4(d) rate filing
per 154.403: LSS and SS–2 Fuel Tracker
Filing 2015 to be effective 4/1/2015.
Filed Date: 3/18/15.
Accession Number: 20150318–5147.
Comments Due: 5 p.m. ET 3/30/15.
Docket Numbers: RP15–657–000.
Applicants: Equitrans, L.P.
Description: Section 4(d) rate filing
per 154.204: Negotiated Capacity
Release Agreement—3/19/2015 to be
effective 3/19/2015.
Filed Date: 3/19/15.
Accession Number: 20150319–5025.
Comments Due: 5 p.m. ET 3/31/15.
Docket Numbers: RP15–658–000.
Applicants: Enable Gas Transmission,
LLC.
Description: Section 4(d) rate filing
per 154.204: Negotiated Rate Filing—
SND Non-Conforming 0414 (RS FT) to
be effective 2/1/2015.
Filed Date: 3/19/15.
Accession Number: 20150319–5132.
Comments Due: 5 p.m. ET 3/31/15.
Docket Numbers: RP15–659–000.
Applicants: Portland Natural Gas
Transmission System.
Description: Compliance filing per
154.203: Compliance to Order 801—
Docket No. RM14–21–000 to be effective
6/1/2015.
Filed Date: 3/20/15.
Accession Number: 20150320–5022.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15–660–000.
Applicants: Gulf South Pipeline
Company, LP.
Description: Section 4(d) rate filing
per 154.204: Amendments to Neg Rate
Agmts (QEP 37657–137, 36601–40) to be
effective 3/20/2015.
Filed Date: 3/20/15.
Accession Number: 20150320–5023.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15–661–000.
Applicants: Natural Gas Pipeline
Company of America.
Description: Section 4(d) rate filing
per 154.204: Negotiated Rate—
Occidental Energy to be effective
4/1/2015.
Filed Date: 3/20/15.
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
16667
Accession Number: 20150320–5117.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15–662–000.
Applicants: Leaf River Energy Center
LLC.
Description: Compliance filing per
154.203: Leaf River Energy Center
LLC—Order No. 801 Compliance Filing
to be effective 4/1/2015.
Filed Date: 3/20/15.
Accession Number: 20150320–5154.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15–663–000.
Applicants: ANR Storage Company.
Description: Compliance filing per
154.203: Compliance to Order 801—
Docket No. RM14–21–000 to be effective
6/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323–5052.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: RP15–664–000.
Applicants: Blue Lake Gas Storage
Company.
Description: Compliance filing per
154.203: Compliance to Order 801—
Docket No. RM14–21–000 to be effective
6/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323–5053.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: RP15–665–000.
Applicants: Bison Pipeline LLC.
Description: Compliance filing per
154.203: Compliance to Order 801—
Docket No. RM14–21–000 to be effective
6/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323–5054.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: RP15–666–000.
Applicants: Horizon Pipeline
Company, L.L.C.
Description: Penalty Revenue
Crediting Report of Horizon Pipeline
Company, L.L.C.
Filed Date: 3/20/15.
Accession Number: 20150320–5266.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15–667–000.
Applicants: Midcontinent Express
Pipeline LLC.
Description: Penalty Revenue
Crediting Report of Midcontinent
Express Pipeline LLC.
Filed Date: 3/20/15.
Accession Number: 20150320–5267.
Comments Due: 5 p.m. ET 4/1/15.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
E:\FR\FM\30MRN1.SGM
30MRN1
16668
Federal Register / Vol. 80, No. 60 / Monday, March 30, 2015 / Notices
Filings in Existing Proceedings
Docket Numbers: RP13–1371–002.
Applicants: Eastern Shore Natural Gas
Company.
Description: Compliance filing per
154.203: Compliance with Order No.
801 to be effective 4/1/2015.
Filed Date: 3/19/15.
Accession Number: 20150319–5042.
Comments Due: 5 p.m. ET 3/31/15.
Docket Numbers: RP15–584–001.
Applicants: Rockies Express Pipeline
LLC.
Description: Tariff Amendment per
154.205(b): Errata to RP15–584 to be
effective 4/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323–5000.
Comments Due: 5 p.m. ET 4/6/15.
Any person desiring to protest in any
of the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5:00 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 23, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–07164 Filed 3–27–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
mstockstill on DSK4VPTVN1PROD with NOTICES
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC15–102–000.
Applicants: Florida Power & Light
Company.
Description: Application of Florida
Power & Light Company for
Authorization Under Section 203 of the
Federal Power Act and Request for
Expedited Action.
Filed Date: 3/23/15.
Accession Number: 20150323–5346.
Comments Due: 5 p.m. ET 4/13/15.
Take notice that the Commission
received the following exempt
wholesale generator filings:
VerDate Sep<11>2014
19:57 Mar 27, 2015
Jkt 235001
Docket Numbers: EG15–70–000.
Applicants: CPV Biomass Holdings,
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of CPV Biomass
Holdings, LLC.
Filed Date: 3/24/15.
Accession Number: 20150324–5086.
Comments Due: 5 p.m. ET 4/14/15.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–3184–004;
ER10–2805–004; ER10–2600–005; ER10–
2564–005; ER10–2289–005; EL15–42–
000.
Applicants: FortisUS Energy
Corporation, Central Hudson Gas &
Electric Corp., Tucson Electric Power
Company, UNS Electric, Inc., UniSource
Energy Development Company.
Description: Response to Order to
Show Cause of the Fortis MBR Sellers.
Filed Date: 3/23/15.
Accession Number: 20150323–5342.
Comments Due: 5 p.m. ET 4/13/15.
Docket Numbers: ER11–4315–005;
ER10–3110–004; ER10–3144–005.
Applicants: Gila River Power LLC,
Union Power Partners, L.P., Entegra
Power Services LLC.
Description: Notice of Non-Material
Change in Status of the Entegra Public
Utilities.
Filed Date: 3/24/15.
Accession Number: 20150324–5159.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–1922–001.
Applicants: Duke Energy Florida, Inc.,
Duke Energy Carolinas, LLC.
Description: Compliance filing per 35:
Order No. 1000 Interregional FRCC &
SERTP to be effective 1/1/2015.
Filed Date: 3/24/15.
Accession Number: 20150324–5070.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–1928–002.
Applicants: Duke Energy Progress,
Inc., Duke Energy Carolinas, LLC.
Description: Compliance filing per 35:
Order No. 1000 Interregional—SERTP &
SCRTP & FRCC to be effective 1/1/2015.
Filed Date: 3/24/15.
Accession Number: 20150324–5069.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–1930–002.
Applicants: Louisville Gas and
Electric Company.
Description: Compliance filing per 35:
Order 1000 Interregional FRCC and
SCRTP to be effective 1/1/2015.
Filed Date: 3/24/15.
Accession Number: 20150324–5092.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–1932–001.
Applicants: Tampa Electric Company.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
Description: Compliance filing per 35:
OATT Order No. 1000 Interregional
Compliance Filing 2015 to be effective
1/1/2015.
Filed Date: 3/24/15.
Accession Number: 20150324–5034.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–1935–001.
Applicants: South Carolina Electric &
Gas Company.
Description: Compliance filing per 35:
Order 1000 Interregional Compliance
filing 3–24–15 to be effective 1/1/2015.
Filed Date: 3/24/15.
Accession Number: 20150324–5057.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–1941–002.
Applicants: Alabama Power
Company.
Description: Compliance filing per 35:
Order No. 1000 Second Interregional
Compliance Filing—FRCC & SCRPT
Seams to be effective 1/1/2015.
Filed Date: 3/24/15.
Accession Number: 20150324–5074.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER13–2255–001.
Applicants: Mansfield Power and Gas,
LLC.
Description: Notice of Non-Material
Change in Status of Mansfield Power
and Gas, LLC.
Filed Date: 3/18/15.
Accession Number: 20150318–5204.
Comments Due: 5 p.m. ET 4/8/15.
Docket Numbers: ER13–2318–005;
ER13–2317–005; ER13–2319–005.
Applicants: All Dams Generation,
LLC, Lake Lynn Generation, LLC, PE
Hydro Generation, LLC.
Description: Notification of Change in
Status of the Cube Hydro MBR Sellers.
Filed Date: 3/23/15.
Accession Number: 20150323–5343.
Comments Due: 5 p.m. ET 4/13/15.
Docket Numbers: ER14–2864–003.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment per
35.17(b): Compliance Filing per 2/20/15
Order in Docket No. ER14–2864 to be
effective 11/12/2015.
Filed Date: 3/23/15.
Accession Number: 20150323–5321.
Comments Due: 5 p.m. ET 4/13/15.
Docket Numbers: ER15–551–000.
Applicants: Southwest Power Pool,
Inc.
Description: eTariff filing per
35.19a(b): 2390R2 Westar Energy, Inc.
Refund Report to be effective N/A.
Filed Date: 3/24/15.
Accession Number: 20150324–5077.
Comments Due: 5 p.m. ET 4/14/15.
Docket Numbers: ER15–571–000.
Applicants: Southwest Power Pool,
Inc.
E:\FR\FM\30MRN1.SGM
30MRN1
Agencies
[Federal Register Volume 80, Number 60 (Monday, March 30, 2015)]
[Notices]
[Pages 16667-16668]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-07164]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings
Take notice that the Commission has received the following Natural
Gas Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP15-656-000.
Applicants: Transcontinental Gas Pipe Line Company.
Description: Section 4(d) rate filing per 154.403: LSS and SS-2
Fuel Tracker Filing 2015 to be effective 4/1/2015.
Filed Date: 3/18/15.
Accession Number: 20150318-5147.
Comments Due: 5 p.m. ET 3/30/15.
Docket Numbers: RP15-657-000.
Applicants: Equitrans, L.P.
Description: Section 4(d) rate filing per 154.204: Negotiated
Capacity Release Agreement--3/19/2015 to be effective 3/19/2015.
Filed Date: 3/19/15.
Accession Number: 20150319-5025.
Comments Due: 5 p.m. ET 3/31/15.
Docket Numbers: RP15-658-000.
Applicants: Enable Gas Transmission, LLC.
Description: Section 4(d) rate filing per 154.204: Negotiated Rate
Filing--SND Non-Conforming 0414 (RS FT) to be effective 2/1/2015.
Filed Date: 3/19/15.
Accession Number: 20150319-5132.
Comments Due: 5 p.m. ET 3/31/15.
Docket Numbers: RP15-659-000.
Applicants: Portland Natural Gas Transmission System.
Description: Compliance filing per 154.203: Compliance to Order
801--Docket No. RM14-21-000 to be effective 6/1/2015.
Filed Date: 3/20/15.
Accession Number: 20150320-5022.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15-660-000.
Applicants: Gulf South Pipeline Company, LP.
Description: Section 4(d) rate filing per 154.204: Amendments to
Neg Rate Agmts (QEP 37657-137, 36601-40) to be effective 3/20/2015.
Filed Date: 3/20/15.
Accession Number: 20150320-5023.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15-661-000.
Applicants: Natural Gas Pipeline Company of America.
Description: Section 4(d) rate filing per 154.204: Negotiated
Rate--Occidental Energy to be effective 4/1/2015.
Filed Date: 3/20/15.
Accession Number: 20150320-5117.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15-662-000.
Applicants: Leaf River Energy Center LLC.
Description: Compliance filing per 154.203: Leaf River Energy
Center LLC--Order No. 801 Compliance Filing to be effective 4/1/2015.
Filed Date: 3/20/15.
Accession Number: 20150320-5154.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15-663-000.
Applicants: ANR Storage Company.
Description: Compliance filing per 154.203: Compliance to Order
801--Docket No. RM14-21-000 to be effective 6/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323-5052.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: RP15-664-000.
Applicants: Blue Lake Gas Storage Company.
Description: Compliance filing per 154.203: Compliance to Order
801--Docket No. RM14-21-000 to be effective 6/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323-5053.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: RP15-665-000.
Applicants: Bison Pipeline LLC.
Description: Compliance filing per 154.203: Compliance to Order
801--Docket No. RM14-21-000 to be effective 6/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323-5054.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: RP15-666-000.
Applicants: Horizon Pipeline Company, L.L.C.
Description: Penalty Revenue Crediting Report of Horizon Pipeline
Company, L.L.C.
Filed Date: 3/20/15.
Accession Number: 20150320-5266.
Comments Due: 5 p.m. ET 4/1/15.
Docket Numbers: RP15-667-000.
Applicants: Midcontinent Express Pipeline LLC.
Description: Penalty Revenue Crediting Report of Midcontinent
Express Pipeline LLC.
Filed Date: 3/20/15.
Accession Number: 20150320-5267.
Comments Due: 5 p.m. ET 4/1/15.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
[[Page 16668]]
Filings in Existing Proceedings
Docket Numbers: RP13-1371-002.
Applicants: Eastern Shore Natural Gas Company.
Description: Compliance filing per 154.203: Compliance with Order
No. 801 to be effective 4/1/2015.
Filed Date: 3/19/15.
Accession Number: 20150319-5042.
Comments Due: 5 p.m. ET 3/31/15.
Docket Numbers: RP15-584-001.
Applicants: Rockies Express Pipeline LLC.
Description: Tariff Amendment per 154.205(b): Errata to RP15-584 to
be effective 4/1/2015.
Filed Date: 3/23/15.
Accession Number: 20150323-5000.
Comments Due: 5 p.m. ET 4/6/15.
Any person desiring to protest in any of the above proceedings must
file in accordance with Rule 211 of the Commission's Regulations (18
CFR 385.211) on or before 5:00 p.m. Eastern time on the specified
comment date.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: March 23, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-07164 Filed 3-27-15; 8:45 am]
BILLING CODE 6717-01-P