Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
n. Procedural Schedule:
The application will be processed
according to the following revised hydro
licensing schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Filing of recommendations,
terms and conditions, and
prescriptions.
Commission issues Draft EA
Comments on Draft EA Due
Commission Issues Final EA
Target date
May 2015.
December
2015.
January 2016.
May 2016.
o. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
Dated: March 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–06523 Filed 3–20–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
mstockstill on DSK4VPTVN1PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER15–929–002.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment per
35.17(b): Motion for Deferral in OMPA
Revised Stated Rate—ER15–929 to be
effective 12/31/9998.
Filed Date: 3/13/15.
Accession Number: 20150313–5176.
Comments Due: 5 p.m. ET 4/3/15.
Docket Numbers: ER15–1282–000.
Applicants: NorthWestern
Corporation.
VerDate Sep<11>2014
16:51 Mar 20, 2015
Jkt 235001
Description: § 205(d) rate filing per
35.13(a)(2)(iii): SA 28–SD First
Revised—LGIA with Beethoven Wind
LLC to be effective 3/17/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5077.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1283–000.
Applicants: Southwestern Electric
Power Company.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): SWEPCO-Hope PSA
Amendment to be effective 1/1/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5143.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1287–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): First Revised Service
Agreement No. 3669; Queue Nos. Y3–
046, Y3–051, Z1–058 . . . to be effective
2/13/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5159.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1289–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Great River Energy.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): 2015–03–16_GRE RTO
Adder Filing to be effective 1/6/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5163.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1290–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): First Revised Service
Agreement No. 2775; Queue Nos. Y3–
045, Y3–052, Y3–107 to be effective
2/13/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5168.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1291–000.
Applicants: Public Service Company
of Colorado.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): 2015–3–16_PSC–PLND–
A&R ISA 110–0.0.0-Agrmt to be effective
3/17/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5173.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1292–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): First Revised Service
Agreement No. 2181; Queue No. V4–045
to be effective 2/12/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5176.
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
15207
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1293–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) rate filing per
35.13(a)(2)(iii): Revisions to Attachment
AE Sections 4.5.2 and 4.5.3 to be
effective 5/15/2015.
Filed Date: 3/16/15.
Accession Number: 20150316–5187.
Comments Due: 5 p.m. ET 4/6/15.
Docket Numbers: ER15–1294–000.
Applicants: Pacific Gas and Electric
Company.
Description: Pacific Gas and Electric
Company submits Notice of
Termination of Agreement with the City
of Los Angeles Department of Water and
Power, Rate Schedule No. 131.
Filed Date: 3/16/15.
Accession Number: 20150316–5188.
Comments Due: 5 p.m. ET 4/6/15.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 16, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015–06554 Filed 3–20–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. DI15–02–000]
Southern Energy, Inc.; Notice of
Declaration of Intention and Soliciting
Comments, Protests, and Motions To
Intervene
Take notice that the following
application has been filed with the
Commission and is available for public
inspection:
a. Application Type: Declaration of
Intention.
E:\FR\FM\23MRN1.SGM
23MRN1
mstockstill on DSK4VPTVN1PROD with NOTICES
15208
Federal Register / Vol. 80, No. 55 / Monday, March 23, 2015 / Notices
b. Docket No: DI15–02–000.
c. Date Filed: January 16, 2015.
d. Applicant: Southern Energy, Inc.
e. Name of Project: Walker Lake
Hydroelectric Project.
f. Location: The proposed Walker
Lake Hydroelectric Project would be
located on Wilson Lake, near the City of
Haines, in Haines Borough, Alaska.
g. Filed Pursuant to: section 23(b)(1)
of the Federal Power Act, 16 U.S.C.
817(b) (2012).
h. Applicant Contact: John Floreske,
Jr., President, Southern Energy, Inc.,
P.O. Box 489, Mile 1.5 Haines Highway,
Haines, AK 99827; telephone: (909)
766–2899; email: northern@
aptalaska.net.
i. FERC Contact: Any questions on
this notice should be addressed to
Jennifer Polardino, (202) 502–6437, or
email: Jennifer.Polardino@ferc.gov.
j. Deadline for filing comments,
protests, and motions to intervene is: 30
days from the issuance date of this
notice by the Commission.
The Commission strongly encourages
electronic filing. Please file comments,
protests, and motions to intervene using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number DI15–02–000.
k. Description of Project: The
proposed Walker Lake Hydroelectric
Project would consist of: (1) Two
rockfilled 15-foot-wide dams, creating
4,300 acre-feet of usable storage capacity
in Walker Lake at a normal maximum
operating elevation of 1,195 feet mean
sea level (msl); (2) a concrete spillway
and diversion channel for controlled
releases to Walker Creek; (3) a
freestanding concrete intake and
reservoir outlet works at elevation 1,170
feet msl diverting flow from the
southeast dam into the penstock; (4) a
24-inch-diameter, 12,000-foot-long
penstock, of which approximately
10,000 feet would be buried and 2,000
feet would be aboveground; (5) a
powerhouse containing one generating
unit rated at 1 megawatt at 780 feet of
net head; (6) a 50-foot-long tailrace
VerDate Sep<11>2014
16:51 Mar 20, 2015
Jkt 235001
connecting the powerhouse with the
Little Salmon River; (7) an underground,
4-mile-long, 12.5 kilovolt transmission
line extending from the project to a
point of interconnection with Inside
Passage Electric Cooperative’s power
grid; and (8) appurtenant facilities.
When a Declaration of Intention is
filed with the Federal Energy Regulatory
Commission, the Federal Power Act
requires the Commission to investigate
and determine if the project would
affect the interests of interstate or
foreign commerce. The Commission also
determines whether or not the project:
(1) Would be located on a navigable
waterway; (2) would occupy public
lands or reservations of the United
States; (3) would utilize surplus water
or water power from a government dam;
or (4) would be located on a nonnavigable stream over which Congress
has Commerce Clause jurisdiction and
would be constructed or enlarged after
1935.
l. Locations of the Application: This
filing may be viewed on the
Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above and in the Commission’s Public
Reference Room located at 888 First
Street NE., Room 2A, Washington, DC
20426, or by calling (202) 502–8371.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: All filings must bear in all
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
capital letters the title ‘‘COMMENTS’’,
‘‘PROTESTS’’, and ‘‘MOTIONS TO
INTERVENE’’, as applicable, and the
Docket Number of the particular
application to which the filing refers. A
copy of any Motion to Intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
p. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Dated: March 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–06527 Filed 3–20–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC15–92–000.
Applicants: American Transmission
Company LLC (ATC),Consolidated
Water Power Company.
Description: Joint Application for
Authority to Acquire Transmission
Facilities Under Section 203 of the FPA
of American Transmission Company
LLC, et al.
Filed Date: 3/13/15.
Accession Number: 20150313–5211.
Comments Due: 5 p.m. ET 4/3/15.
Docket Numbers: EC15–93–000.
Applicants: American Transmission
Company LLC (ATC).
Description: Application for
Authority to Acquire Transmission
Facilities Under Section 203 of the FPA
of American Transmission Company
LLC.
Filed Date: 3/13/15.
Accession Number: 20150313–5212.
Comments Due: 5 p.m. ET 4/3/15.
Docket Numbers: EC15–94–000.
Applicants: American Transmission
Company LLC (ATC).
Description: Application for
Authority to Acquire Transmission
Facilities Under Section 203 of the FPA
of American Transmission Company
LLC.
E:\FR\FM\23MRN1.SGM
23MRN1
Agencies
[Federal Register Volume 80, Number 55 (Monday, March 23, 2015)]
[Notices]
[Pages 15207-15208]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-06527]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. DI15-02-000]
Southern Energy, Inc.; Notice of Declaration of Intention and
Soliciting Comments, Protests, and Motions To Intervene
Take notice that the following application has been filed with the
Commission and is available for public inspection:
a. Application Type: Declaration of Intention.
[[Page 15208]]
b. Docket No: DI15-02-000.
c. Date Filed: January 16, 2015.
d. Applicant: Southern Energy, Inc.
e. Name of Project: Walker Lake Hydroelectric Project.
f. Location: The proposed Walker Lake Hydroelectric Project would
be located on Wilson Lake, near the City of Haines, in Haines Borough,
Alaska.
g. Filed Pursuant to: section 23(b)(1) of the Federal Power Act, 16
U.S.C. 817(b) (2012).
h. Applicant Contact: John Floreske, Jr., President, Southern
Energy, Inc., P.O. Box 489, Mile 1.5 Haines Highway, Haines, AK 99827;
telephone: (909) 766-2899; email: northern@aptalaska.net.
i. FERC Contact: Any questions on this notice should be addressed
to Jennifer Polardino, (202) 502-6437, or email:
Jennifer.Polardino@ferc.gov.
j. Deadline for filing comments, protests, and motions to intervene
is: 30 days from the issuance date of this notice by the Commission.
The Commission strongly encourages electronic filing. Please file
comments, protests, and motions to intervene using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC 20426. The first page of any
filing should include docket number DI15-02-000.
k. Description of Project: The proposed Walker Lake Hydroelectric
Project would consist of: (1) Two rockfilled 15-foot-wide dams,
creating 4,300 acre-feet of usable storage capacity in Walker Lake at a
normal maximum operating elevation of 1,195 feet mean sea level (msl);
(2) a concrete spillway and diversion channel for controlled releases
to Walker Creek; (3) a freestanding concrete intake and reservoir
outlet works at elevation 1,170 feet msl diverting flow from the
southeast dam into the penstock; (4) a 24-inch-diameter, 12,000-foot-
long penstock, of which approximately 10,000 feet would be buried and
2,000 feet would be aboveground; (5) a powerhouse containing one
generating unit rated at 1 megawatt at 780 feet of net head; (6) a 50-
foot-long tailrace connecting the powerhouse with the Little Salmon
River; (7) an underground, 4-mile-long, 12.5 kilovolt transmission line
extending from the project to a point of interconnection with Inside
Passage Electric Cooperative's power grid; and (8) appurtenant
facilities.
When a Declaration of Intention is filed with the Federal Energy
Regulatory Commission, the Federal Power Act requires the Commission to
investigate and determine if the project would affect the interests of
interstate or foreign commerce. The Commission also determines whether
or not the project: (1) Would be located on a navigable waterway; (2)
would occupy public lands or reservations of the United States; (3)
would utilize surplus water or water power from a government dam; or
(4) would be located on a non-navigable stream over which Congress has
Commerce Clause jurisdiction and would be constructed or enlarged after
1935.
l. Locations of the Application: This filing may be viewed on the
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number excluding the last three digits in the docket
number field to access the document. You may also register online at
https://www.ferc.gov/docs-filing/esubscription.asp to be notified via
email of new filings and issuances related to this or other pending
projects. For assistance, call 1-866-208-3676 or email
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above and in the Commission's Public Reference Room located at 888
First Street NE., Room 2A, Washington, DC 20426, or by calling (202)
502-8371.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents: All filings must
bear in all capital letters the title ``COMMENTS'', ``PROTESTS'', and
``MOTIONS TO INTERVENE'', as applicable, and the Docket Number of the
particular application to which the filing refers. A copy of any Motion
to Intervene must also be served upon each representative of the
Applicant specified in the particular application.
p. Agency Comments: Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Dated: March 16, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-06527 Filed 3-20-15; 8:45 am]