Pacific Gas and Electric Company, Diablo Canyon Power Plant, Units 1 and 2, and Diablo Canyon Independent Spent Fuel Storage Installation, 8706-8711 [2015-03384]

Download as PDF 8706 Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices Day Event/Activity 0 10 60 20 25 30 40 A A+3 A + 28 A + 53 A + 60 >A + 60 Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests. Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding. Deadline for submitting petition for intervention containing: (i) demonstration of standing; and (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply). U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents). If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staff’s grant of access. Deadline for NRC staff reply to motions to reverse NRC staff determination(s). (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement for SUNSI. If access granted: issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff. Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective order. Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI. (Answer receipt +7) Petitioner/Intervenor reply to answers. Decision on contention admission. BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–275, 50–323, and 72–26; NRC–2015–0022] Pacific Gas and Electric Company, Diablo Canyon Power Plant, Units 1 and 2, and Diablo Canyon Independent Spent Fuel Storage Installation Nuclear Regulatory Commission. AGENCY: License amendment application; opportunity to comment, request a hearing, and petition for leave to intervene; order. ACTION: The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an amendment to Facility Operating License Nos. DPR–80 and DPR–82 and Special Nuclear Materials License No. SNM–2511 issued to Pacific Gas and Electric Company. The NRC proposes to determine that the amendment request involves no significant hazards consideration. In addition, the amendment request contains Sensitive Unclassified NonSafeguards Information (SUNSI). emcdonald on DSK67QTVN1PROD with NOTICES SUMMARY: VerDate Sep<11>2014 19:32 Feb 17, 2015 Jkt 235001 Submit comments by March 20, 2015. A request for a hearing must be filed by April 20, 2015. Any potential party as defined in § 2.4 of Title 10 of the Code of Federal Regulations (10 CFR), who believes access to SUNSI is necessary to respond to this notice must request document access by March 2, 2015. ADDRESSES: You may submit comments by any of the following methods (unless this document describes a different method for submitting comments on a specific subject): • Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC–2015–0022. Address questions about NRC dockets to Carol Gallagher; telephone: 301–287–3422; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • Mail comments to: Cindy Bladey, Office of Administration, Mail Stop: OWFN–12 H08, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001. For additional direction on obtaining information and submitting comments, see ‘‘Obtaining Information and Submitting Comments’’ in the SUPPLEMENTARY INFORMATION section of this document. DATES: [FR Doc. 2015–03379 Filed 2–17–15; 8:45 am] PO 00000 Frm 00118 Fmt 4703 Sfmt 4703 Siva P. Lingam, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555– 0001; telephone: 301–415–1564, email: Siva.Lingam@nrc.gov. SUPPLEMENTARY INFORMATION: FOR FURTHER INFORMATION CONTACT: I. Obtaining Information and Submitting Comments A. Obtaining Information Please refer to Docket ID NRC–2015– 0022 when contacting the NRC about the availability of information for this action. You may obtain publiclyavailable information related to this action by any of the following methods: • Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC–2015–0022. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publiclyavailable documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘ADAMS Public Documents’’ and then select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301–415–4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number for each E:\FR\FM\18FEN1.SGM 18FEN1 Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in the SUPPLEMENTARY INFORMATION section. • NRC’s PDR: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. emcdonald on DSK67QTVN1PROD with NOTICES B. Submitting Comments Please include Docket ID NRC–2015– 0022 in your comment submission. The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC posts all comment submissions at https:// www.regulations.gov as well as entering the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information. If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment submissions into ADAMS. II. Introduction The NRC is considering issuance of an amendment to Facility Operating License Nos. DPR–80 and DPR–82 and Special Nuclear Materials License No. SNM–2511 issued to Pacific Gas and Electric Company (the licensee) for operation of the Diablo Canyon Power Plant (DCPP), Units 1 and 2, located in San Luis Obispo County, California, and the Diablo Canyon Independent Spent Fuel Storage Installation. By letter dated September 24, 2013 (ADAMS Accession No. ML13268A398), as supplemented by letters dated December 18, 2013 (security-related), and May 15, 2014 (ADAMS Accession No. ML14135A379), the licensee submitted an application for a license amendment request. The licensee is requesting that the Commission grant it preemption authority consistent with the Commission’s authority under Section 161A of the Atomic Energy Act of 1954, as amended, (the Act), to authorize the security personnel of designated classes of licensees to possess and use certain firearms, ammunition, and other devices such as large-capacity ammunition feeding VerDate Sep<11>2014 19:32 Feb 17, 2015 Jkt 235001 devices, notwithstanding Federal, State or local laws prohibiting such possession or use. If the amendment request is granted, the licenses would be modified to reflect the Commission’s grant of Section 161A preemption authority. Before issuance of the proposed license amendment, the Commission will have made findings required by the Act, and the Commission’s regulations. The Commission has made a proposed determination that the amendment request involves no significant hazards consideration. Under the Commission’s regulations in § 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below: 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated? The [proposed license amendment] requests the NRC to exercise its preemption authority under Section 161A of the Atomic Energy Act of 1954, as amended (42 U.S.C. 2201a). The proposed amendment does not involve any physical changes to structures, systems or components. Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated. 2. Does the proposed change create the possibility of a new or different accident from any accident previously evaluated? The proposed amendment associated with preemption authority does not create the possibility of a new or different accident from any accident previously evaluated. 3. Does the proposed change involve a significant reduction in a margin of safety? The proposed amendment associated with preemption authority does not impact accident analyses, fission product barriers, or margin of safety. Therefore, the proposed change does not involve a significant reduction in a margin of safety. The NRC staff has reviewed the licensee’s analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are PO 00000 Frm 00119 Fmt 4703 Sfmt 4703 8707 satisfied. Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration. The Commission is seeking public comments on this proposed determination. Any comments received by March 20, 2015, will be considered in making any final determination. You may submit comments using any of the methods discussed under the ADDRESSES section of this document. Normally, the Commission will not issue the amendment until the expiration of 60 days after the date of publication of this notice. The Commission may issue the license amendment before expiration of the 60day period provided that its final determination is that the amendment involves no significant hazards consideration. In addition, the Commission may issue the amendment prior to the expiration of the 30-day comment period should circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility. Should the Commission take action prior to the expiration of either the comment period or the notice period, it will publish in the Federal Register a notice of issuance. Should the Commission make a final No Significant Hazards Consideration Determination, any hearing will take place after issuance. The Commission expects that the need to take this action will occur very infrequently. III. Opportunity To Request a Hearing and Petition for Leave To Intervene Within 60 days after the date of publication of this Federal Register notice, any person whose interest may be affected by this proceeding and who desires to participate as a party in the proceeding must file a written request for hearing or a petition for leave to intervene specifying the contentions which the person seeks to have litigated in the hearing with respect to the license amendment request. Requests for hearing and petitions for leave to intervene shall be filed in accordance with the NRC’s ‘‘Agency Rules of Practice and Procedure’’ in 10 CFR part 2. Interested person(s) should consult a current copy of 10 CFR 2.309, which is available at the NRC’s PDR. The NRC’s regulations are accessible electronically from the NRC Library on the NRC’s Web site at https://www.nrc.gov/reading-rm/ doc-collections/cfr/. As required by 10 CFR 2.309, a request for hearing or petition for leave to intervene must set forth with particularity the interest of the E:\FR\FM\18FEN1.SGM 18FEN1 emcdonald on DSK67QTVN1PROD with NOTICES 8708 Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices petitioner in the proceeding and how that interest may be affected by the results of the proceeding. The hearing request or petition must specifically explain the reasons why intervention should be permitted, with particular reference to the following general requirements: (1) The name, address, and telephone number of the requestor or petitioner; (2) the nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The hearing request or petition must also include the specific contentions that the requestor/petitioner seeks to have litigated at the proceeding. For each contention, the requestor/ petitioner must provide a specific statement of the issue of law or fact to be raised or controverted, as well as a brief explanation of the basis for the contention. Additionally, the requestor/ petitioner must demonstrate that the issue raised by each contention is within the scope of the proceeding and is material to the findings that the NRC must make to support the granting of a license amendment in response to the application. The hearing request or petition must also include a concise statement of the alleged facts or expert opinion that support the contention and on which the requestor/petitioner intends to rely at the hearing, together with references to those specific sources and documents. The hearing request or petition must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact, including references to specific portions of the application for amendment that the petitioner disputes and the supporting reasons for each dispute. If the requestor/petitioner believes that the application for amendment fails to contain information on a relevant matter as required by law, the requestor/ petitioner must identify each failure and the supporting reasons for the requestor’s/petitioner’s belief. Each contention must be one which, if proven, would entitle the requestor/ petitioner to relief. A requestor/ petitioner who does not satisfy these requirements for at least one contention will not be permitted to participate as a party. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to VerDate Sep<11>2014 20:47 Feb 17, 2015 Jkt 235001 participate fully in the conduct of the hearing with respect to resolution of that person’s admitted contentions, including the opportunity to present evidence and to submit a crossexamination plan for cross-examination of witnesses, consistent with NRC’s regulations, policies, and procedures. The Atomic Safety and Licensing Board will set the time and place for any prehearing conferences and evidentiary hearings, and the appropriate notices will be provided. Hearing requests or petitions for leave to intervene must be filed no later than 60 days from the date of publication of this notice. Requests for hearing, petitions for leave to intervene, and motions for leave to file new or amended contentions that are filed after the 60-day deadline will not be entertained absent a determination by the presiding officer that the filing demonstrates good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i)–(iii). If a hearing is requested, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to decide when the hearing is held. If the final determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, then any hearing held would take place before the issuance of any amendment unless the Commission finds an imminent danger to the health or safety of the public, in which case it will issue an appropriate order or rule under 10 CFR part 2. IV. Electronic Submissions (E-Filing) All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC’s E-Filing rule (72 FR 49139; August 28, 2007). The EFiling process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings PO 00000 Frm 00120 Fmt 4703 Sfmt 4703 unless they seek an exemption in accordance with the procedures described below. To comply with the procedural requirements of E-Filing, at least 10 days prior to the filing deadline, the participant should contact the Office of the Secretary by email at hearing.docket@nrc.gov, or by telephone at 301–415–1677, to request (1) a digital identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a request or petition for hearing (even in instances in which the participant, or its counsel or representative, already holds an NRCissued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on the NRC’s public Web site at https:// www.nrc.gov/site-help/e-submittals/ getting-started.html. System requirements for accessing the ESubmittal server are detailed in the NRC’s ‘‘Guidance for Electronic Submission,’’ which is available on the agency’s public Web site at https:// www.nrc.gov/site-help/esubmittals.html. Participants may attempt to use other software not listed on the Web site, but should note that the NRC’s E-Filing system does not support unlisted software, and the NRC Meta System Help Desk will not be able to offer assistance in using unlisted software. If a participant is electronically submitting a document to the NRC in accordance with the E-Filing rule, the participant must file the document using the NRC’s online, Web-based submission form. In order to serve documents through the Electronic Information Exchange System, users will be required to install a Web browser plug-in from the NRC’s Web site. Further information on the Webbased submission form, including the installation of the Web browser plug-in, is available on the NRC’s public Web site at https://www.nrc.gov/site-help/esubmittals.html. Once a participant has obtained a digital ID certificate and a docket has been created, the participant can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance E:\FR\FM\18FEN1.SGM 18FEN1 emcdonald on DSK67QTVN1PROD with NOTICES Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices available on the NRC’s public Web site at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered complete at the time the documents are submitted through the NRC’s E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an email notice confirming receipt of the document. The E-Filing system also distributes an email notice that provides access to the document to the NRC’s Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/ petition to intervene is filed so that they can obtain access to the document via the E-Filing system. A person filing electronically using the NRC’s adjudicatory E-Filing system may seek assistance by contacting the NRC Meta System Help Desk through the ‘‘Contact Us’’ link located on the NRC’s public Web site at https:// www.nrc.gov/site-help/esubmittals.html, by email to MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays. Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) first class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited VerDate Sep<11>2014 19:32 Feb 17, 2015 Jkt 235001 delivery service upon depositing the document with the provider of the service. A presiding officer, having granted an exemption request from using E-Filing, may require a participant or party to use E-Filing if the presiding officer subsequently determines that the reason for granting the exemption from use of E-Filing no longer exists. Documents submitted in adjudicatory proceedings will appear in the NRC’s electronic hearing docket which is available to the public at https:// ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the Commission, or the presiding officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. However, a request to intervene will require including information on local residence in order to demonstrate a proximity assertion of interest in the proceeding. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission. Petitions for leave to intervene must be filed no later than 60 days from the date of publication of this notice. Nontimely filings will not be entertained absent a determination by the presiding officer that the petition or request should be granted or the contentions should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(iii). Attorney for licensee: Jennifer Post, Esq., Pacific Gas and Electric Company, P.O. Box 7442, San Francisco, California 94120. Acting NRC Branch Chief: Eric R. Oesterle. Pacific Gas and Electric Company, Docket Nos. 50–275, 50–323, and 72–26, Diablo Canyon Power Plant, Units 1 and 2, San Luis Obispo County, California, and Diablo Canyon Independent Spent Fuel Storage Installation Order Imposing Procedures for Access to Sensitive Unclassified NonSafeguards Information for Contention Preparation A. This Order contains instructions regarding how potential parties to this proceeding may request access to documents containing SUNSI. B. Within 10 days after publication of this notice of hearing and opportunity to petition for leave to intervene, any PO 00000 Frm 00121 Fmt 4703 Sfmt 4703 8709 potential party who believes access to SUNSI is necessary to respond to this notice may request such access. A ‘‘potential party’’ is any person who intends to participate as a party by demonstrating standing and filing an admissible contention under 10 CFR 2.309. Requests for access to SUNSI submitted later than 10 days after publication of this notice will not be considered absent a showing of good cause for the late filing, addressing why the request could not have been filed earlier. C. The requester shall submit a letter requesting permission to access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, and provide a copy to the Associate General Counsel for Hearings, Enforcement and Administration, Office of the General Counsel, Washington, DC 20555–0001. The expedited delivery or courier mail address for both offices is: U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The email address for the Office of the Secretary and the Office of the General Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov, respectively.1 The request must include the following information: (1) A description of the licensing action with a citation to this Federal Register notice; (2) The name and address of the potential party and a description of the potential party’s particularized interest that could be harmed by the action identified in C.(1); and (3) The identity of the individual or entity requesting access to SUNSI and the requester’s basis for the need for the information in order to meaningfully participate in this adjudicatory proceeding. In particular, the request must explain why publicly-available versions of the information requested would not be sufficient to provide the basis and specificity for a proffered contention. D. Based on an evaluation of the information submitted under paragraph C.(3) the NRC staff will determine within 10 days of receipt of the request whether: (1) There is a reasonable basis to believe the petitioner is likely to establish standing to participate in this NRC proceeding; and 1 While a request for hearing or petition to intervene in this proceeding must comply with the filing requirements of the NRC’s ‘‘E-Filing Rule,’’ the initial request to access SUNSI under these procedures should be submitted as described in this paragraph. E:\FR\FM\18FEN1.SGM 18FEN1 8710 Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices (2) The requestor has established a legitimate need for access to SUNSI. E. If the NRC staff determines that the requestor satisfies both D.(1) and D.(2) above, the NRC staff will notify the requestor in writing that access to SUNSI has been granted. The written notification will contain instructions on how the requestor may obtain copies of the requested documents, and any other conditions that may apply to access to those documents. These conditions may include, but are not limited to, the signing of a Non-Disclosure Agreement or Affidavit, or Protective Order 2 setting forth terms and conditions to prevent the unauthorized or inadvertent disclosure of SUNSI by each individual who will be granted access to SUNSI. F. Filing of Contentions. Any contentions in these proceedings that are based upon the information received as a result of the request made for SUNSI must be filed by the requestor no later than 25 days after the requestor is granted access to that information. However, if more than 25 days remain between the date the petitioner is granted access to the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. This provision does not extend the time for filing a request for a hearing and petition to intervene, which must comply with the requirements of 10 CFR 2.309. G. Review of Denials of Access. (1) If the request for access to SUNSI is denied by the NRC staff after a determination on standing and need for access, the NRC staff shall immediately notify the requestor in writing, briefly stating the reason or reasons for the denial. (2) The requester may challenge the NRC staff’s adverse determination by filing a challenge within 5 days of receipt of that determination with: (a) The presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if he or she is unavailable, another administrative judge, or an administrative law judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) officer if that officer has been designated to rule on information access issues. H. Review of Grants of Access. A party other than the requester may challenge an NRC staff determination granting access to SUNSI whose release would harm that party’s interest independent of the proceeding. Such a challenge must be filed with the Chief Administrative Judge within 5 days of the notification by the NRC staff of its grant of access. If challenges to the NRC staff determinations are filed, these procedures give way to the normal process for litigating disputes concerning access to information. The availability of interlocutory review by the Commission of orders ruling on such NRC staff determinations (whether granting or denying access) is governed by 10 CFR 2.311.3 I. The Commission expects that the NRC staff and presiding officers (and any other reviewing officers) will consider and resolve requests for access to SUNSI, and motions for protective orders, in a timely fashion in order to minimize any unnecessary delays in identifying those petitioners who have standing and who have propounded contentions meeting the specificity and basis requirements in 10 CFR part 2. Attachment 1 to this Order summarizes the general target schedule for processing and resolving requests under these procedures. It is so ordered. Dated at Rockville, Maryland, this 9th day of February, 2015. For the Nuclear Regulatory Commission. Annette L. Vietti-Cook, Secretary of the Commission. ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING Day Event/Activity 0 ........... Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests. Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: Supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding. Deadline for submitting petition for intervention containing: (i) Demonstration of standing; and (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply). U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents). If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staff’s grant of access. Deadline for NRC staff reply to motions to reverse NRC staff determination(s). (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement for SUNSI. If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff. Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective order. 10 ......... 60 ......... 20 ......... 25 ......... emcdonald on DSK67QTVN1PROD with NOTICES 30 ......... 40 ......... A ........... A + 3 .... 2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must be filed with the presiding officer or the Chief Administrative Judge if the presiding officer has not VerDate Sep<11>2014 19:32 Feb 17, 2015 Jkt 235001 yet been designated, within 30 days of the deadline for the receipt of the written access request. 3 Requesters should note that the filing requirements of the NRC’s E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals of NRC PO 00000 Frm 00122 Fmt 4703 Sfmt 4703 staff determinations (because they must be served on a presiding officer or the Commission, as applicable), but not to the initial SUNSI request submitted to the NRC staff under these procedures. E:\FR\FM\18FEN1.SGM 18FEN1 8711 Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued Day Event/Activity A + 28 .. Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI. (Answer receipt +7) Petitioner/Intervenor reply to answers. Decision on contention admission. A + 53 .. A + 60 .. >A + 60 [FR Doc. 2015–03384 Filed 2–17–15; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION Application for a License To Export High-Enriched Uranium Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 110.70 (b) ‘‘Public Notice of Receipt of an Application,’’ please take notice that the U.S. Nuclear Regulatory Commission (NRC) has received the following request for an export license. Copies of the request are available electronically through the Agencywide Documents Access and Management System and can be accessed through the Public Electronic Reading Room link https:// www.nrc.gov/reading-rm.html at the NRC Homepage. A request for a hearing or petition for leave to intervene may be filed within thirty days after publication of this notice in the Federal Register (FR). Any request for hearing or petition for leave to intervene shall be served by the requestor or petitioner upon the applicant, the Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555; the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555; and the Executive Secretary, U.S. Department of State, Washington, DC 20520. A request for a hearing or petition for leave to intervene may be filed with the NRC electronically in accordance with NRC’s E-Filing rule promulgated in August 2007, 72 FR 49139; August 28, 2007. Information about filing electronically is available on the NRC’s public Web site at https://www.nrc.gov/ site-help/e-submittals.html. To ensure timely electronic filing, at least five days prior to the filing deadline, the petitioner/requestor should contact the Office of the Secretary by email at HEARINGDOCKET@NRC.GOV, or by calling (301) 415–1677, to request a digital ID certificate and allow for the creation of an electronic docket. In addition to a request for hearing or petition for leave to intervene, written comments, in accordance with 10 CFR 110.81, should be submitted within thirty days after publication of this notice in the FR to Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555, Attention: Rulemaking and Adjudications. The information concerning this application for an export license follows. NRC EXPORT LICENSE APPLICATION Description of material Name of applicant, date of application, date received, application No., docket No. DOE/NNSA—Y–12 National Security Complex, December 18, 2014, December 23, 2014, XSNM3757, 11006187. Dated this 10th day of February, 2015 at Rockville, Maryland. For the U.S. Nuclear Regulatory Commission. Mugeh Afshar-Tous, Acting Deputy Director, Office of International Programs. [FR Doc. 2015–03376 Filed 2–17–15; 8:45 am] emcdonald on DSK67QTVN1PROD with NOTICES BILLING CODE 7590–01–P VerDate Sep<11>2014 20:47 Feb 17, 2015 Jkt 235001 Destination Material type High-Enriched Uranium (93.20%). Total quantity End use 121.1 kg uranium-235 contained in 130.0 kg uranium. To fabricate fuel at AREVA CERCA in France for ultimate use in reactor fuel reload at the High Flux Reactor in France. NUCLEAR REGULATORY COMMISSION Application for a License To Export High-Enriched Uranium Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 110.70(b) ‘‘Public Notice of Receipt of an Application,’’ please take notice that the U.S. Nuclear Regulatory Commission (NRC) has received the following request for an export license. Copies of the request are available electronically through the Agencywide Documents Access and Management System and can be accessed through the Public Electronic Reading Room link https:// PO 00000 Frm 00123 Fmt 4703 Sfmt 4703 France. www.nrc.gov/reading-rm.html at the NRC Homepage. A request for a hearing or petition for leave to intervene may be filed within thirty days after publication of this notice in the Federal Register (FR). Any request for hearing or petition for leave to intervene shall be served by the requestor or petitioner upon the applicant, the Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555; the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555; and the Executive Secretary, U.S. Department of State, Washington, DC 20520. E:\FR\FM\18FEN1.SGM 18FEN1

Agencies

[Federal Register Volume 80, Number 32 (Wednesday, February 18, 2015)]
[Notices]
[Pages 8706-8711]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-03384]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-275, 50-323, and 72-26; NRC-2015-0022]


Pacific Gas and Electric Company, Diablo Canyon Power Plant, 
Units 1 and 2, and Diablo Canyon Independent Spent Fuel Storage 
Installation

AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment application; opportunity to comment, request 
a hearing, and petition for leave to intervene; order.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering 
issuance of an amendment to Facility Operating License Nos. DPR-80 and 
DPR-82 and Special Nuclear Materials License No. SNM-2511 issued to 
Pacific Gas and Electric Company. The NRC proposes to determine that 
the amendment request involves no significant hazards consideration. In 
addition, the amendment request contains Sensitive Unclassified Non-
Safeguards Information (SUNSI).

DATES: Submit comments by March 20, 2015. A request for a hearing must 
be filed by April 20, 2015. Any potential party as defined in Sec.  2.4 
of Title 10 of the Code of Federal Regulations (10 CFR), who believes 
access to SUNSI is necessary to respond to this notice must request 
document access by March 2, 2015.

ADDRESSES: You may submit comments by any of the following methods 
(unless this document describes a different method for submitting 
comments on a specific subject):
     Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0022. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: Carol.Gallagher@nrc.gov. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     Mail comments to: Cindy Bladey, Office of Administration, 
Mail Stop: OWFN-12 H08, U.S. Nuclear Regulatory Commission, Washington, 
DC 20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Siva P. Lingam, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 
20555-0001; telephone: 301-415-1564, email: Siva.Lingam@nrc.gov.

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2015-0022 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly-available information related to this action by any of the 
following methods:
     Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2015-0022.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The 
ADAMS accession number for each

[[Page 8707]]

document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in the SUPPLEMENTARY INFORMATION section.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2015-0022 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC posts all comment submissions at https://www.regulations.gov as well as entering the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Introduction

    The NRC is considering issuance of an amendment to Facility 
Operating License Nos. DPR-80 and DPR-82 and Special Nuclear Materials 
License No. SNM-2511 issued to Pacific Gas and Electric Company (the 
licensee) for operation of the Diablo Canyon Power Plant (DCPP), Units 
1 and 2, located in San Luis Obispo County, California, and the Diablo 
Canyon Independent Spent Fuel Storage Installation.
    By letter dated September 24, 2013 (ADAMS Accession No. 
ML13268A398), as supplemented by letters dated December 18, 2013 
(security-related), and May 15, 2014 (ADAMS Accession No. ML14135A379), 
the licensee submitted an application for a license amendment request. 
The licensee is requesting that the Commission grant it preemption 
authority consistent with the Commission's authority under Section 161A 
of the Atomic Energy Act of 1954, as amended, (the Act), to authorize 
the security personnel of designated classes of licensees to possess 
and use certain firearms, ammunition, and other devices such as large-
capacity ammunition feeding devices, notwithstanding Federal, State or 
local laws prohibiting such possession or use. If the amendment request 
is granted, the licenses would be modified to reflect the Commission's 
grant of Section 161A preemption authority.
    Before issuance of the proposed license amendment, the Commission 
will have made findings required by the Act, and the Commission's 
regulations.
    The Commission has made a proposed determination that the amendment 
request involves no significant hazards consideration. Under the 
Commission's regulations in Sec.  50.92, this means that operation of 
the facility in accordance with the proposed amendment would not (1) 
involve a significant increase in the probability or consequences of an 
accident previously evaluated; or (2) create the possibility of a new 
or different kind of accident from any accident previously evaluated; 
or (3) involve a significant reduction in a margin of safety. As 
required by 10 CFR 50.91(a), the licensee has provided its analysis of 
the issue of no significant hazards consideration, which is presented 
below:
    1. Does the proposed change involve a significant increase in the 
probability or consequences of an accident previously evaluated?
    The [proposed license amendment] requests the NRC to exercise its 
preemption authority under Section 161A of the Atomic Energy Act of 
1954, as amended (42 U.S.C. 2201a). The proposed amendment does not 
involve any physical changes to structures, systems or components.
    Therefore, the proposed change does not involve a significant 
increase in the probability or consequences of an accident previously 
evaluated.
    2. Does the proposed change create the possibility of a new or 
different accident from any accident previously evaluated?
    The proposed amendment associated with preemption authority does 
not create the possibility of a new or different accident from any 
accident previously evaluated.
    3. Does the proposed change involve a significant reduction in a 
margin of safety?
    The proposed amendment associated with preemption authority does 
not impact accident analyses, fission product barriers, or margin of 
safety.
    Therefore, the proposed change does not involve a significant 
reduction in a margin of safety.
    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
amendment request involves no significant hazards consideration.
    The Commission is seeking public comments on this proposed 
determination. Any comments received by March 20, 2015, will be 
considered in making any final determination. You may submit comments 
using any of the methods discussed under the ADDRESSES section of this 
document.
    Normally, the Commission will not issue the amendment until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment 
involves no significant hazards consideration. In addition, the 
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day 
comment period such that failure to act in a timely way would result, 
for example, in derating or shutdown of the facility. Should the 
Commission take action prior to the expiration of either the comment 
period or the notice period, it will publish in the Federal Register a 
notice of issuance. Should the Commission make a final No Significant 
Hazards Consideration Determination, any hearing will take place after 
issuance. The Commission expects that the need to take this action will 
occur very infrequently.

III. Opportunity To Request a Hearing and Petition for Leave To 
Intervene

    Within 60 days after the date of publication of this Federal 
Register notice, any person whose interest may be affected by this 
proceeding and who desires to participate as a party in the proceeding 
must file a written request for hearing or a petition for leave to 
intervene specifying the contentions which the person seeks to have 
litigated in the hearing with respect to the license amendment request. 
Requests for hearing and petitions for leave to intervene shall be 
filed in accordance with the NRC's ``Agency Rules of Practice and 
Procedure'' in 10 CFR part 2. Interested person(s) should consult a 
current copy of 10 CFR 2.309, which is available at the NRC's PDR. The 
NRC's regulations are accessible electronically from the NRC Library on 
the NRC's Web site at https://www.nrc.gov/reading-rm/doc-collections/cfr/.
    As required by 10 CFR 2.309, a request for hearing or petition for 
leave to intervene must set forth with particularity the interest of 
the

[[Page 8708]]

petitioner in the proceeding and how that interest may be affected by 
the results of the proceeding. The hearing request or petition must 
specifically explain the reasons why intervention should be permitted, 
with particular reference to the following general requirements: (1) 
The name, address, and telephone number of the requestor or petitioner; 
(2) the nature of the requestor's/petitioner's right under the Act to 
be made a party to the proceeding; (3) the nature and extent of the 
requestor's/petitioner's property, financial, or other interest in the 
proceeding; and (4) the possible effect of any decision or order which 
may be entered in the proceeding on the requestor's/petitioner's 
interest. The hearing request or petition must also include the 
specific contentions that the requestor/petitioner seeks to have 
litigated at the proceeding.
    For each contention, the requestor/petitioner must provide a 
specific statement of the issue of law or fact to be raised or 
controverted, as well as a brief explanation of the basis for the 
contention. Additionally, the requestor/petitioner must demonstrate 
that the issue raised by each contention is within the scope of the 
proceeding and is material to the findings that the NRC must make to 
support the granting of a license amendment in response to the 
application. The hearing request or petition must also include a 
concise statement of the alleged facts or expert opinion that support 
the contention and on which the requestor/petitioner intends to rely at 
the hearing, together with references to those specific sources and 
documents. The hearing request or petition must provide sufficient 
information to show that a genuine dispute exists with the applicant on 
a material issue of law or fact, including references to specific 
portions of the application for amendment that the petitioner disputes 
and the supporting reasons for each dispute. If the requestor/
petitioner believes that the application for amendment fails to contain 
information on a relevant matter as required by law, the requestor/
petitioner must identify each failure and the supporting reasons for 
the requestor's/petitioner's belief. Each contention must be one which, 
if proven, would entitle the requestor/petitioner to relief. A 
requestor/petitioner who does not satisfy these requirements for at 
least one contention will not be permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing with respect to resolution of that person's admitted 
contentions, including the opportunity to present evidence and to 
submit a cross-examination plan for cross-examination of witnesses, 
consistent with NRC's regulations, policies, and procedures. The Atomic 
Safety and Licensing Board will set the time and place for any 
prehearing conferences and evidentiary hearings, and the appropriate 
notices will be provided.
    Hearing requests or petitions for leave to intervene must be filed 
no later than 60 days from the date of publication of this notice. 
Requests for hearing, petitions for leave to intervene, and motions for 
leave to file new or amended contentions that are filed after the 60-
day deadline will not be entertained absent a determination by the 
presiding officer that the filing demonstrates good cause by satisfying 
the three factors in 10 CFR 2.309(c)(1)(i)-(iii).
    If a hearing is requested, the Commission will make a final 
determination on the issue of no significant hazards consideration. The 
final determination will serve to decide when the hearing is held. If 
the final determination is that the amendment request involves no 
significant hazards consideration, the Commission may issue the 
amendment and make it immediately effective, notwithstanding the 
request for a hearing. Any hearing held would take place after issuance 
of the amendment. If the final determination is that the amendment 
request involves a significant hazards consideration, then any hearing 
held would take place before the issuance of any amendment unless the 
Commission finds an imminent danger to the health or safety of the 
public, in which case it will issue an appropriate order or rule under 
10 CFR part 2.

IV. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including a 
request for hearing, a petition for leave to intervene, any motion or 
other document filed in the proceeding prior to the submission of a 
request for hearing or petition to intervene, and documents filed by 
interested governmental entities participating under 10 CFR 2.315(c), 
must be filed in accordance with the NRC's E-Filing rule (72 FR 49139; 
August 28, 2007). The E-Filing process requires participants to submit 
and serve all adjudicatory documents over the internet, or in some 
cases to mail copies on electronic storage media. Participants may not 
submit paper copies of their filings unless they seek an exemption in 
accordance with the procedures described below.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at hearing.docket@nrc.gov, or by 
telephone at 301-415-1677, to request (1) a digital identification (ID) 
certificate, which allows the participant (or its counsel or 
representative) to digitally sign documents and access the E-Submittal 
server for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a request or 
petition for hearing (even in instances in which the participant, or 
its counsel or representative, already holds an NRC-issued digital ID 
certificate). Based upon this information, the Secretary will establish 
an electronic docket for the hearing in this proceeding if the 
Secretary has not already established an electronic docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/getting-started.html. System requirements for accessing 
the E-Submittal server are detailed in the NRC's ``Guidance for 
Electronic Submission,'' which is available on the agency's public Web 
site at https://www.nrc.gov/site-help/e-submittals.html. Participants 
may attempt to use other software not listed on the Web site, but 
should note that the NRC's E-Filing system does not support unlisted 
software, and the NRC Meta System Help Desk will not be able to offer 
assistance in using unlisted software.
    If a participant is electronically submitting a document to the NRC 
in accordance with the E-Filing rule, the participant must file the 
document using the NRC's online, Web-based submission form. In order to 
serve documents through the Electronic Information Exchange System, 
users will be required to install a Web browser plug-in from the NRC's 
Web site. Further information on the Web-based submission form, 
including the installation of the Web browser plug-in, is available on 
the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
    Once a participant has obtained a digital ID certificate and a 
docket has been created, the participant can then submit a request for 
hearing or petition for leave to intervene. Submissions should be in 
Portable Document Format (PDF) in accordance with NRC guidance

[[Page 8709]]

available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the 
documents are submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of 
a transmission, the E-Filing system time-stamps the document and sends 
the submitter an email notice confirming receipt of the document. The 
E-Filing system also distributes an email notice that provides access 
to the document to the NRC's Office of the General Counsel and any 
others who have advised the Office of the Secretary that they wish to 
participate in the proceeding, so that the filer need not serve the 
documents on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before a hearing request/petition 
to intervene is filed so that they can obtain access to the document 
via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System 
Help Desk through the ``Contact Us'' link located on the NRC's public 
Web site at https://www.nrc.gov/site-help/e-submittals.html, by email to 
MSHD.Resource@nrc.gov, or by a toll-free call at 1-866-672-7640. The 
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., 
Eastern Time, Monday through Friday, excluding government holidays.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted by: (1) first class mail 
addressed to the Office of the Secretary of the Commission, U.S. 
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemaking and Adjudications Staff; or (2) courier, express mail, or 
expedited delivery service to the Office of the Secretary, Sixteenth 
Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 
20852, Attention: Rulemaking and Adjudications Staff. Participants 
filing a document in this manner are responsible for serving the 
document on all other participants. Filing is considered complete by 
first-class mail as of the time of deposit in the mail, or by courier, 
express mail, or expedited delivery service upon depositing the 
document with the provider of the service. A presiding officer, having 
granted an exemption request from using E-Filing, may require a 
participant or party to use E-Filing if the presiding officer 
subsequently determines that the reason for granting the exemption from 
use of E-Filing no longer exists.
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket which is available to the public at 
https://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the 
Commission, or the presiding officer. Participants are requested not to 
include personal privacy information, such as social security numbers, 
home addresses, or home phone numbers in their filings, unless an NRC 
regulation or other law requires submission of such information. 
However, a request to intervene will require including information on 
local residence in order to demonstrate a proximity assertion of 
interest in the proceeding. With respect to copyrighted works, except 
for limited excerpts that serve the purpose of the adjudicatory filings 
and would constitute a Fair Use application, participants are requested 
not to include copyrighted materials in their submission.
    Petitions for leave to intervene must be filed no later than 60 
days from the date of publication of this notice. Non-timely filings 
will not be entertained absent a determination by the presiding officer 
that the petition or request should be granted or the contentions 
should be admitted, based on a balancing of the factors specified in 10 
CFR 2.309(c)(1)(i)-(iii).
    Attorney for licensee: Jennifer Post, Esq., Pacific Gas and 
Electric Company, P.O. Box 7442, San Francisco, California 94120.
    Acting NRC Branch Chief: Eric R. Oesterle.
Pacific Gas and Electric Company, Docket Nos. 50-275, 50-323, and 72-
26, Diablo Canyon Power Plant, Units 1 and 2, San Luis Obispo County, 
California, and Diablo Canyon Independent Spent Fuel Storage 
Installation
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation
    A. This Order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing SUNSI.
    B. Within 10 days after publication of this notice of hearing and 
opportunity to petition for leave to intervene, any potential party who 
believes access to SUNSI is necessary to respond to this notice may 
request such access. A ``potential party'' is any person who intends to 
participate as a party by demonstrating standing and filing an 
admissible contention under 10 CFR 2.309. Requests for access to SUNSI 
submitted later than 10 days after publication of this notice will not 
be considered absent a showing of good cause for the late filing, 
addressing why the request could not have been filed earlier.
    C. The requester shall submit a letter requesting permission to 
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
Adjudications Staff, and provide a copy to the Associate General 
Counsel for Hearings, Enforcement and Administration, Office of the 
General Counsel, Washington, DC 20555-0001. The expedited delivery or 
courier mail address for both offices is: U.S. Nuclear Regulatory 
Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The email 
address for the Office of the Secretary and the Office of the General 
Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov, 
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------

    \1\ While a request for hearing or petition to intervene in this 
proceeding must comply with the filing requirements of the NRC's 
``E-Filing Rule,'' the initial request to access SUNSI under these 
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------

    (1) A description of the licensing action with a citation to this 
Federal Register notice;
    (2) The name and address of the potential party and a description 
of the potential party's particularized interest that could be harmed 
by the action identified in C.(1); and
    (3) The identity of the individual or entity requesting access to 
SUNSI and the requester's basis for the need for the information in 
order to meaningfully participate in this adjudicatory proceeding. In 
particular, the request must explain why publicly-available versions of 
the information requested would not be sufficient to provide the basis 
and specificity for a proffered contention.
    D. Based on an evaluation of the information submitted under 
paragraph C.(3) the NRC staff will determine within 10 days of receipt 
of the request whether:
    (1) There is a reasonable basis to believe the petitioner is likely 
to establish standing to participate in this NRC proceeding; and

[[Page 8710]]

    (2) The requestor has established a legitimate need for access to 
SUNSI.
    E. If the NRC staff determines that the requestor satisfies both 
D.(1) and D.(2) above, the NRC staff will notify the requestor in 
writing that access to SUNSI has been granted. The written notification 
will contain instructions on how the requestor may obtain copies of the 
requested documents, and any other conditions that may apply to access 
to those documents. These conditions may include, but are not limited 
to, the signing of a Non-Disclosure Agreement or Affidavit, or 
Protective Order \2\ setting forth terms and conditions to prevent the 
unauthorized or inadvertent disclosure of SUNSI by each individual who 
will be granted access to SUNSI.
---------------------------------------------------------------------------

    \2\ Any motion for Protective Order or draft Non-Disclosure 
Affidavit or Agreement for SUNSI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 30 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    F. Filing of Contentions. Any contentions in these proceedings that 
are based upon the information received as a result of the request made 
for SUNSI must be filed by the requestor no later than 25 days after 
the requestor is granted access to that information. However, if more 
than 25 days remain between the date the petitioner is granted access 
to the information and the deadline for filing all other contentions 
(as established in the notice of hearing or opportunity for hearing), 
the petitioner may file its SUNSI contentions by that later deadline. 
This provision does not extend the time for filing a request for a 
hearing and petition to intervene, which must comply with the 
requirements of 10 CFR 2.309.
    G. Review of Denials of Access.
    (1) If the request for access to SUNSI is denied by the NRC staff 
after a determination on standing and need for access, the NRC staff 
shall immediately notify the requestor in writing, briefly stating the 
reason or reasons for the denial.
    (2) The requester may challenge the NRC staff's adverse 
determination by filing a challenge within 5 days of receipt of that 
determination with: (a) The presiding officer designated in this 
proceeding; (b) if no presiding officer has been appointed, the Chief 
Administrative Judge, or if he or she is unavailable, another 
administrative judge, or an administrative law judge with jurisdiction 
pursuant to 10 CFR 2.318(a); or (c) officer if that officer has been 
designated to rule on information access issues.
    H. Review of Grants of Access. A party other than the requester may 
challenge an NRC staff determination granting access to SUNSI whose 
release would harm that party's interest independent of the proceeding. 
Such a challenge must be filed with the Chief Administrative Judge 
within 5 days of the notification by the NRC staff of its grant of 
access.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. The availability of interlocutory 
review by the Commission of orders ruling on such NRC staff 
determinations (whether granting or denying access) is governed by 10 
CFR 2.311.\3\
---------------------------------------------------------------------------

    \3\ Requesters should note that the filing requirements of the 
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals 
of NRC staff determinations (because they must be served on a 
presiding officer or the Commission, as applicable), but not to the 
initial SUNSI request submitted to the NRC staff under these 
procedures.
---------------------------------------------------------------------------

    I. The Commission expects that the NRC staff and presiding officers 
(and any other reviewing officers) will consider and resolve requests 
for access to SUNSI, and motions for protective orders, in a timely 
fashion in order to minimize any unnecessary delays in identifying 
those petitioners who have standing and who have propounded contentions 
meeting the specificity and basis requirements in 10 CFR part 2. 
Attachment 1 to this Order summarizes the general target schedule for 
processing and resolving requests under these procedures.

    It is so ordered.
    Dated at Rockville, Maryland, this 9th day of February, 2015.

    For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.

   ATTACHMENT 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards Information
                           in this Proceeding
------------------------------------------------------------------------
                Day                            Event/Activity
------------------------------------------------------------------------
0.................................  Publication of Federal Register
                                     notice of hearing and opportunity
                                     to petition for leave to intervene,
                                     including order with instructions
                                     for access requests.
10................................  Deadline for submitting requests for
                                     access to Sensitive Unclassified
                                     Non-Safeguards Information (SUNSI)
                                     with information: Supporting the
                                     standing of a potential party
                                     identified by name and address;
                                     describing the need for the
                                     information in order for the
                                     potential party to participate
                                     meaningfully in an adjudicatory
                                     proceeding.
60................................  Deadline for submitting petition for
                                     intervention containing: (i)
                                     Demonstration of standing; and (ii)
                                     all contentions whose formulation
                                     does not require access to SUNSI
                                     (+25 Answers to petition for
                                     intervention; +7 petitioner/
                                     requestor reply).
20................................  U.S. Nuclear Regulatory Commission
                                     (NRC) staff informs the requester
                                     of the staff's determination
                                     whether the request for access
                                     provides a reasonable basis to
                                     believe standing can be established
                                     and shows need for SUNSI. (NRC
                                     staff also informs any party to the
                                     proceeding whose interest
                                     independent of the proceeding would
                                     be harmed by the release of the
                                     information.) If NRC staff makes
                                     the finding of need for SUNSI and
                                     likelihood of standing, NRC staff
                                     begins document processing
                                     (preparation of redactions or
                                     review of redacted documents).
25................................  If NRC staff finds no ``need'' or no
                                     likelihood of standing, the
                                     deadline for petitioner/requester
                                     to file a motion seeking a ruling
                                     to reverse the NRC staff's denial
                                     of access; NRC staff files copy of
                                     access determination with the
                                     presiding officer (or Chief
                                     Administrative Judge or other
                                     designated officer, as
                                     appropriate). If NRC staff finds
                                     ``need'' for SUNSI, the deadline
                                     for any party to the proceeding
                                     whose interest independent of the
                                     proceeding would be harmed by the
                                     release of the information to file
                                     a motion seeking a ruling to
                                     reverse the NRC staff's grant of
                                     access.
30................................  Deadline for NRC staff reply to
                                     motions to reverse NRC staff
                                     determination(s).
40................................  (Receipt +30) If NRC staff finds
                                     standing and need for SUNSI,
                                     deadline for NRC staff to complete
                                     information processing and file
                                     motion for Protective Order and
                                     draft Non-Disclosure Affidavit.
                                     Deadline for applicant/licensee to
                                     file Non-Disclosure Agreement for
                                     SUNSI.
A.................................  If access granted: Issuance of
                                     presiding officer or other
                                     designated officer decision on
                                     motion for protective order for
                                     access to sensitive information
                                     (including schedule for providing
                                     access and submission of
                                     contentions) or decision reversing
                                     a final adverse determination by
                                     the NRC staff.
A + 3.............................  Deadline for filing executed Non-
                                     Disclosure Affidavits. Access
                                     provided to SUNSI consistent with
                                     decision issuing the protective
                                     order.

[[Page 8711]]

 
A + 28............................  Deadline for submission of
                                     contentions whose development
                                     depends upon access to SUNSI.
                                     However, if more than 25 days
                                     remain between the petitioner's
                                     receipt of (or access to) the
                                     information and the deadline for
                                     filing all other contentions (as
                                     established in the notice of
                                     hearing or opportunity for
                                     hearing), the petitioner may file
                                     its SUNSI contentions by that later
                                     deadline.
A + 53............................  (Contention receipt +25) Answers to
                                     contentions whose development
                                     depends upon access to SUNSI.
A + 60............................  (Answer receipt +7) Petitioner/
                                     Intervenor reply to answers.
>A + 60...........................  Decision on contention admission.
------------------------------------------------------------------------

[FR Doc. 2015-03384 Filed 2-17-15; 8:45 am]
BILLING CODE 7590-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.