Download as PDF Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices Dated: February 12, 2015. Kate Mullan, Acting Director, Information Collection Clearance Division, Privacy, Information and Records Management Services, Office of Management. [FR Doc. 2015–03281 Filed 2–17–15; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13102–003] emcdonald on DSK67QTVN1PROD with NOTICES Birch Power Company; Notice of Scoping Meetings and Environmental Site Review and Soliciting Scoping Comments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original License (Major Project). b. Project No.: 13102–003. c. Date Filed: July 2, 2013. d. Applicant: Birch Power Company. e. Name of Project: Demopolis Lock and Dam Hydroelectric Project. f. Location: At the U.S. Army Corps of Engineers’ (Corps) Demopolis Lock and Dam, on theTombigbee River, west of the city of Demopolis in Marengo and Sumter Counties, Alabama. The proposed project would occupy approximately 23 acres of federal land administered by the Corps. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Nicholas E. Josten, GeoSense, 2742 Saint Charles Ave., Idaho Falls, ID 83404, (208) 528– 6152. i. FERC Contact: Adam Peer, (202) 502–8449 or adam.peer@ferc.gov. j. Deadline for filing scoping comments: April 25, 2015. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13102–003. The Commission’s Rules of Practice and Procedures require all intervenors filing documents with the Commission VerDate Sep<11>2014 19:32 Feb 17, 2015 Jkt 235001 to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application is not ready for environmental analysis at this time. l. The proposed project would utilize the existing Corps’ Demopolis Lock and Dam and Reservoir, and would consist of the following new facilities: (1) A 900-foot-long excavated intake channel (headrace); (2) two 60-foot-long by 32foot-wide trash racks with 2.5-inch bar spacing; (3) a 201-foot-long by 80-footwide powerhouse containing two 24megawatt (MW) Kaplan turbines, having a total installed capacity of 48 MW; (4) a substation; (5) a forebay oxygen diffuser line system to enhance dissolved oxygen; (6) a 1,880-foot-long excavated tailrace channel; (7) a 1,700foot-long retaining wall along the north side of tailrace channel; (8) a 4.4-milelong, 115-kilovolt transmission line; and (9) appurtenant facilities. The average annual generation would be about 213,000 megawatt-hours. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Scoping Process: The Commission intends to prepare an environmental assessment (EA) on the project in accordance with the National Environmental Policy Act. The EA will consider both site-specific and cumulative environmental impacts and reasonable alternatives to the proposed action. Scoping Meetings FERC staff will conduct one agency scoping meeting and one public meeting. The agency scoping meeting will focus on resource agency and nongovernmental organization (NGO) concerns, while the public scoping meeting is primarily for public input. PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 8633 All interested individuals, organizations, and agencies are invited to attend one or both of the meetings, and to assist the staff in identifying the scope of the environmental issues that should be analyzed in the EA. The times and locations of these meetings are as follows: Agency Scoping Meeting DATE: Thursday, March 26, 2015. TIME: 9:00 a.m. (EDT). PLACE: Demopolis Civic Center. ADDRESS: 501 N. Commissioner’s Avenue, Demopolis, AL 36732. Public Scoping Meeting DATE: Thursday, March 26, 2015. TIME: 7:00 p.m. (EDT). PLACE: Demopolis Civic Center. ADDRESS: 501 N. Commissioner’s Avenue, Demopolis, AL 36732. Copies of the Scoping Document (SD1) outlining the subject areas to be addressed in the EA were distributed to the parties on the Commission’s mailing list. Copies of the SD1 will be available at the scoping meeting or may be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link (see item m above). Environmental Site Review The Applicant and FERC staff will conduct a project Environmental Site Review. The time and location of this meeting is as follows: PROJECT: Demopolis Lock and Dam Hydroelectric Project. DATE: Thursday, March 26, 2015. TIME: 2:00 p.m. (EDT). LOCATION: Demopolis Civic Center Parking Lot, 501 N. Commissioner’s Avenue, Demopolis, AL 36732. All interested individuals, organizations, and agencies are invited to attend. All participants should meet at the time and location specified above. All participants are responsible for their own transportation to the site. Anyone with questions about the Environmental Site Review should contact Nicholas E. Josten, GeoSense, 2742 Saint Charles Ave., Idaho Falls, ID 83404, (208) 528– 6152 on or before March 19, 2015. Objectives At the scoping meetings, the staff will: (1) Summarize the environmental issues tentatively identified for analysis in the EA; (2) solicit from the meeting participants all available information, especially quantifiable data, on the resources at issue; (3) encourage statements from experts and the public on issues that should be analyzed in the EA, including viewpoints in opposition to, or in support of, the staff’s preliminary views; (4) determine the E:\FR\FM\18FEN1.SGM 18FEN1 8634 Federal Register / Vol. 80, No. 32 / Wednesday, February 18, 2015 / Notices resource issues to be addressed in the EA; and (5) identify those issues that require a detailed analysis, as well as those issues that do not require a detailed analysis. Procedures The meetings are recorded by a stenographer and become part of the formal record of the Commission proceeding on the project. Individuals, organizations, and agencies with environmental expertise and concerns are encouraged to attend the meeting and to assist the staff in defining and clarifying the issues to be addressed in the EA. Dated: February 11, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–03263 Filed 2–17–15; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission emcdonald on DSK67QTVN1PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC15–71–000. Applicants: Enel Cove Fort, LLC, Enel Stillwater, LLC,EGP Stillwater Solar, LLC, Origin Wind Energy, LLC,EFS Green Power Holdings, LLC. Description: Application for Authorization under section 203 of the Federal Power Act and Request for Expedited Action of Enel Cove Fort, LLC, et al. Filed Date: 2/9/15. Accession Number: 20150209–5278. Comments Due: 5 p.m. ET 3/2/15. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER14–822–000. Applicants: PJM Interconnection, L.L.C. Description: Report Filing: Informational Report per May, 9, 2014 Order in Docket No. ER14–822–000. to be effective N/A. Filed Date: 2/9/15. Accession Number: 20150209–5219. Comments Due: 5 p.m. ET 3/2/15. Docket Numbers: ER15–266–001. Applicants: Public Service Company of Colorado. Description: Tariff Amendment per 35.17(b): 2015–2–10_PSCo Sttlmnt Losses Amend Filing to be effective 1/ 1/2015. Filed Date: 2/10/15. Accession Number: 20150210–5145. VerDate Sep<11>2014 19:32 Feb 17, 2015 Jkt 235001 Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–359–002. Applicants: Samchully Power & Utilities 1 LLC. Description: Notice of Non-Material Change in Status of Samchully Power & Utilities 1 LLC. Filed Date: 2/10/15. Accession Number: 20150210–5179. Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–746–001. Applicants: RC Cape May Holdings, LLC. Description: Tariff Amendment per 35.17(b): Supplement to Reactive Rate Schedule Change Request to be effective 12/31/9998. Filed Date: 2/10/15. Accession Number: 20150210–5169. Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–786–000. Applicants: Midcontinent Independent System Operator, Inc. Description: Report Filing: 2015–02– 10_SA 2523 Supplement ITC-Pheasant Run GIA (J075) to be effective N/A. Filed Date: 2/10/15. Accession Number: 20150210–5062. Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–1015–000. Applicants: AltaGas Brush Energy Inc. Description: Section 205(d) rate filing per 35.13(a)(2)(iii): AltaGas Brush Energy Inc. Notice of Succession to be effective 2/10/2015. Filed Date: 2/9/15. Accession Number: 20150209–5147. Comments Due: 5 p.m. ET 3/2/15. Docket Numbers: ER15–1016–000. Applicants: Shafter Solar, LLC. Description: Baseline eTariff Filing per 35.1: Shafter Solar, LLC Application for Market-Based Rates to be effective 3/ 15/2015. Filed Date: 2/9/15. Accession Number: 20150209–5256. Comments Due: 5 p.m. ET 3/2/15. Docket Numbers: ER15–1017–000. Applicants: Southern California Edison Company. Description: Section 205(d) rate filing per 35.13(a)(2)(iii): Tie-Line Facilities Agreement with Valle Del Sol Energy, LLC to be effective 4/12/2015. Filed Date: 2/10/15. Accession Number: 20150210–5000. Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–1018–000. Applicants: Southern California Edison Company. Description: Section 205(d) rate filing per 35.13(a)(2)(iii): LGIA and Distribution Service Agmt with Valle Del Sol Energy, LLC to be effective 4/12/ 2015. Filed Date: 2/10/15. Accession Number: 20150210–5001. PO 00000 Frm 00046 Fmt 4703 Sfmt 9990 Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–1019–000. Applicants: Fowler Ridge IV Wind Farm LLC. Description: Initial rate filing per 35.12 Application for MBR to be effective 2/11/2015. Filed Date: 2/10/15. Accession Number: 20150210–5089. Comments Due: 5 p.m. ET 3/3/15. Docket Numbers: ER15–1020–000. Applicants: Rising Tree Wind Farm III LLC. Description: Initial rate filing per 35.12 MBR Application to be effective 4/11/2015. Filed Date: 2/10/15. Accession Number: 20150210–5114. Comments Due: 5 p.m. ET 3/3/15. Take notice that the Commission received the following land acquisition reports: Docket Numbers: LA14–3–000. Applicants: NextEra Energy Companies. Description: Quarterly Land Acquisition Report of the NextEra Energy Companies. Filed Date: 2/9/15. Accession Number: 20150209–5277. Comments Due: 5 p.m. ET 3/2/15. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: February 10, 2015. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2015–03198 Filed 2–17–15; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\18FEN1.SGM 18FEN1

Agencies

[Federal Register Volume 80, Number 32 (Wednesday, February 18, 2015)]
[Notices]
[Pages 8633-8634]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-03263]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13102-003]


Birch Power Company; Notice of Scoping Meetings and Environmental 
Site Review and Soliciting Scoping Comments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original License (Major Project).
    b. Project No.: 13102-003.
    c. Date Filed: July 2, 2013.
    d. Applicant: Birch Power Company.
    e. Name of Project: Demopolis Lock and Dam Hydroelectric Project.
    f. Location: At the U.S. Army Corps of Engineers' (Corps) Demopolis 
Lock and Dam, on theTombigbee River, west of the city of Demopolis in 
Marengo and Sumter Counties, Alabama. The proposed project would occupy 
approximately 23 acres of federal land administered by the Corps.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Nicholas E. Josten, GeoSense, 2742 Saint 
Charles Ave., Idaho Falls, ID 83404, (208) 528-6152.
    i. FERC Contact: Adam Peer, (202) 502-8449 or adam.peer@ferc.gov.
    j. Deadline for filing scoping comments: April 25, 2015.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket number P-13102-003.
    The Commission's Rules of Practice and Procedures require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application is not ready for environmental analysis at this 
time.
    l. The proposed project would utilize the existing Corps' Demopolis 
Lock and Dam and Reservoir, and would consist of the following new 
facilities: (1) A 900-foot-long excavated intake channel (headrace); 
(2) two 60-foot-long by 32-foot-wide trash racks with 2.5-inch bar 
spacing; (3) a 201-foot-long by 80-foot-wide powerhouse containing two 
24-megawatt (MW) Kaplan turbines, having a total installed capacity of 
48 MW; (4) a substation; (5) a forebay oxygen diffuser line system to 
enhance dissolved oxygen; (6) a 1,880-foot-long excavated tailrace 
channel; (7) a 1,700-foot-long retaining wall along the north side of 
tailrace channel; (8) a 4.4-mile-long, 115-kilovolt transmission line; 
and (9) appurtenant facilities. The average annual generation would be 
about 213,000 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Scoping Process:
    The Commission intends to prepare an environmental assessment (EA) 
on the project in accordance with the National Environmental Policy 
Act. The EA will consider both site-specific and cumulative 
environmental impacts and reasonable alternatives to the proposed 
action.

 Scoping Meetings

    FERC staff will conduct one agency scoping meeting and one public 
meeting. The agency scoping meeting will focus on resource agency and 
non-governmental organization (NGO) concerns, while the public scoping 
meeting is primarily for public input. All interested individuals, 
organizations, and agencies are invited to attend one or both of the 
meetings, and to assist the staff in identifying the scope of the 
environmental issues that should be analyzed in the EA. The times and 
locations of these meetings are as follows:

Agency Scoping Meeting

    DATE: Thursday, March 26, 2015.
    TIME: 9:00 a.m. (EDT).
    PLACE: Demopolis Civic Center.
    ADDRESS: 501 N. Commissioner's Avenue, Demopolis, AL 36732.

Public Scoping Meeting

    DATE: Thursday, March 26, 2015.
    TIME: 7:00 p.m. (EDT).
    PLACE: Demopolis Civic Center.
    ADDRESS: 501 N. Commissioner's Avenue, Demopolis, AL 36732.
    Copies of the Scoping Document (SD1) outlining the subject areas to 
be addressed in the EA were distributed to the parties on the 
Commission's mailing list. Copies of the SD1 will be available at the 
scoping meeting or may be viewed on the web at https://www.ferc.gov 
using the ``eLibrary'' link (see item m above).

Environmental Site Review

    The Applicant and FERC staff will conduct a project Environmental 
Site Review. The time and location of this meeting is as follows:
    PROJECT: Demopolis Lock and Dam Hydroelectric Project.
    DATE: Thursday, March 26, 2015.
    TIME: 2:00 p.m. (EDT).
    LOCATION: Demopolis Civic Center Parking Lot, 501 N. Commissioner's 
Avenue, Demopolis, AL 36732.
    All interested individuals, organizations, and agencies are invited 
to attend. All participants should meet at the time and location 
specified above. All participants are responsible for their own 
transportation to the site. Anyone with questions about the 
Environmental Site Review should contact Nicholas E. Josten, GeoSense, 
2742 Saint Charles Ave., Idaho Falls, ID 83404, (208) 528-6152 on or 
before March 19, 2015.

Objectives

    At the scoping meetings, the staff will: (1) Summarize the 
environmental issues tentatively identified for analysis in the EA; (2) 
solicit from the meeting participants all available information, 
especially quantifiable data, on the resources at issue; (3) encourage 
statements from experts and the public on issues that should be 
analyzed in the EA, including viewpoints in opposition to, or in 
support of, the staff's preliminary views; (4) determine the

[[Page 8634]]

resource issues to be addressed in the EA; and (5) identify those 
issues that require a detailed analysis, as well as those issues that 
do not require a detailed analysis.

Procedures

    The meetings are recorded by a stenographer and become part of the 
formal record of the Commission proceeding on the project.
    Individuals, organizations, and agencies with environmental 
expertise and concerns are encouraged to attend the meeting and to 
assist the staff in defining and clarifying the issues to be addressed 
in the EA.

     Dated: February 11, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-03263 Filed 2-17-15; 8:45 am]
BILLING CODE 6717-01-P