Provo River Project Rate Order No. WAPA-165, 7863-7864 [2015-02981]
Download as PDF
Federal Register / Vol. 80, No. 29 / Thursday, February 12, 2015 / Notices
Where: The Grand Colonial, 86 Route
173 West, Hampton, New Jersey
08827.
These public meetings will be posted
on the Commission calendar located at
www.ferc.gov/EventCalendar/
EventsList.aspx along with other related
information. Additional information
about the project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link and the project docket
number (i.e., PF15–1).
Dated: February 5, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–02932 Filed 2–11–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14253–003]
Rmajette on DSK2VPTVN1PROD with NOTICES
Lock+ Hydro Friends Fund IV; Notice
of Successive Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On January 20, 2015, the Lock+ Hydro
Friends Fund IV filed an application for
a successive preliminary permit under
section 4(f) of the Federal Power Act
proposing to study the feasibility of the
proposed USACE MSR LD 17 Project
No. 14253–003, to be located at the
existing Mississippi River Lock and
Dam No. 17 on the Mississippi River,
near the city of New Boston, in Mercer
County, Illinois and Louisa County,
Iowa. The Mississippi River Lock and
Dam No. 17 is owned by the United
States government and operated by the
Army Corps of Engineers. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist
of: (1) Three new 109-foot-wide by 40foot-high steel lock frame modules each
containing ten 650-kilowatt hydropower
turbines having a total combined
generating capacity of 19.5 megawatts;
(2) one new 109-foot-wide and one new
220-foot-wide tailrace extending 75–150
feet downstream; (3) a new 25-foot by
50-foot switchyard; (4) a new intake
structure of undetermined size; (5) a
VerDate Sep<11>2014
13:54 Feb 11, 2015
Jkt 235001
new 6-mile-long, 69-kilovolt
transmission line; and (6) appurtenant
facilities. The project would have an
estimated annual generation of 119,655
megawatt-hours.
Applicant Contact: Mr. Wayne F.
Krouse, P.O. Box 43796, Birmingham,
AL 35243; (877) 556–6566, extension
709.
FERC Contact: Tyrone A. Williams,
(202) 502–6331.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. The Commission strongly
encourages electronic filing. Please file
comments, motions to intervene, notices
of intent, and competing applications
using the Commission’s eFiling system
at https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14253–003.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14253) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: February 5, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015–02931 Filed 2–11–15; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
Provo River Project Rate Order No.
WAPA–165
Western Area Power
Administration, DOE.
ACTION: Notice of Rate Order Concerning
a Formula Rate.
AGENCY:
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
7863
Western Area Power
Administration (Western) extends, on
an interim basis, the existing Provo
River Project Formula Rate through
March 31, 2020. The existing Formula
Rate under Rate Order No. WAPA–149
expires on March 31, 2015. The Formula
Rate will be in effect until the Federal
Energy Regulatory Commission (FERC)
places it into effect on a final basis or
until it is replaced by another rate.
DATES: This action is effective April 1,
2015.
FOR FURTHER INFORMATION CONTACT: Ms.
Lynn C. Jeka, Colorado River Storage
Project (CRSP) Manager, CRSP
Management Center, 150 East Social
Hall Avenue, Suite 300, Salt Lake City,
UT 84111–1580, telephone (801) 524–
6372, email: jeka@wapa.gov, or Mr.
Rodney Bailey, Power Marketing
Manager, CRSP Management Center,
150 East Social Hall Avenue, Suite 300,
Salt Lake City, UT 84111–1580,
telephone (801) 524–4007, email:
rbailey@wapa.gov.
SUPPLEMENTARY INFORMATION: By
Delegation Order No. 00–037.00A, the
Secretary of Energy delegated: (1) The
authority to develop power and
transmission rates to Western’s
Administrator; (2) the authority to
confirm, approve, and place such rates
into effect on an interim basis to the
Deputy Secretary of Energy; and (3) the
authority to confirm, approve, and place
into effect on a final basis, to remand or
to disapprove such rates to FERC. This
extension is issued pursuant to
Delegation Order No. 00–37.00A and
Department of Energy (DOE) rate
extension procedures at 10 CFR
903.23(a).
Under Delegation Order No. 0204–108
and existing DOE procedures for public
participation in rate adjustments at 10
CFR part 903, Western’s Provo River
Formula Rate was submitted to FERC for
confirmation and approval on February
2, 2010. The Provo River Formula Rate,
Rate Order No. WAPA–149, was
approved for 5 years beginning April 1,
2010, and ending March 31, 2015.
The Provo River Project, which
includes Deer Creek Dam on the Provo
River in Utah, was authorized in 1935.
Construction of the dam began in 1938
and was completed in 1951. The Deer
Creek Powerplant was authorized on
August 20, 1951; construction began in
1956 and was completed in 1958;
generation began that same year. Its
maximum operating capacity is 5,200
kilowatts.
The Provo River Project’s power is
sold according to a marketing plan that
was published in the Federal Register
on November 21, 1994 (59 FR 60010).
SUMMARY:
E:\FR\FM\12FEN1.SGM
12FEN1
7864
Federal Register / Vol. 80, No. 29 / Thursday, February 12, 2015 / Notices
This marketing plan allows Western to
sell the output of the Provo River Project
to Utah Municipal Power Agency, Utah
Associated Municipal Power Systems,
and Heber Light and Power (Customers)
in the Provo River drainage area.
Contract Nos. 94–SLC–0253, 94–SLC–
0254, and 07–SLC–0601 between the
United States and Customers require
that each fiscal year (FY) a new annual
installment be calculated in advance by
Western and submitted to the Customers
on or before August 31 of the year
preceding the applicable FY. Each FY
Western prepares a power repayment
study, which includes estimates of
operation, maintenance, and
replacement costs for the Deer Creek
Powerplant. The annual installment is
adjusted on or before August 31 of the
year preceding the FY to which it
pertains, and Western identifies this
amount in contract revisions. Each
annual installment pays the amortized
portion of the United States’ investment
in the Deer Creek hydroelectric
facilities, with interest, and the
associated operation, maintenance, and
administrative costs. This repayment
schedule is not dependent upon the
capacity and associated energy made
available for sale each year.
Rate extensions are authorized under
10 CFR 903.23. Rates previously
confirmed and approved by FERC for
which no adjustment is contemplated
may be extended by the Deputy
Secretary on an interim basis following
notice of proposed extension at least 30
days before expiration. On October 6,
2014, Western published a notice of
proposed extension in the Federal
Register [(79 FR 60153)].
Following review of Western’s
proposal within DOE, I hereby approve,
on an interim basis, Rate Order No.
WAPA–165, which extends, without
adjustment, the existing Formula Rate
through March 31, 2020. Rate Order No.
WAPA–165 will be submitted to FERC
for confirmation and approval on a final
basis.
Dated: February 4, 2015.
Elizabeth Sherwood-Randall,
Deputy Secretary.
Rmajette on DSK2VPTVN1PROD with NOTICES
Department of Energy
Deputy Secretary
In the matter of:
Western Area Power Administration
Formula Rate for the Provo River
Project
Rate Order No. WAPA–165
VerDate Sep<11>2014
13:54 Feb 11, 2015
Jkt 235001
Order Confirming, Approving, and
Placing the Formula Rate for the Provo
River Project Into Effect on an Interim
Basis
Section 302 of the Department of
Energy (DOE) Organization Act (42
U.S.C. 7152) transferred to and vested in
the Secretary of Energy the power
marketing functions of the Secretary of
the Department of the Interior and the
Bureau of Reclamation under the
Reclamation Act of 1902 (ch. 1093, 32
Stat. 388), as amended and
supplemented by subsequent laws,
particularly section 9(c) of the
Reclamation Project Act of 1939 (43
U.S.C. 485h(c)), and other acts that
specifically apply to the project
involved.
By Delegation Order No. 00-037.00A,
the Secretary of Energy delegated: (1)
The authority to develop power and
transmission rates to the Administrator
of Western Area Power Administration
(Western); (2) the authority to confirm,
approve, and place such rates into effect
on an interim basis to the Deputy
Secretary; and (3) the authority to
confirm, approve, and place into effect
on a final basis, to remand, or to
disapprove such rates to the Federal
Energy Regulatory Commission (FERC).
This extension is issued pursuant to the
Delegation Order and DOE rate
extension procedures at 10 CFR
903.23(a).
Background
On November 2, 2010, FERC
confirmed and approved the existing
Formula Rate for the Provo River Project
under Rate Order No. WAPA–149.1
FERC approved this Rate Order for 5
years beginning April 1, 2010, through
March 31, 2015. On October 6, 2014,
pursuant to 10 CFR 903.23(a), Western
filed a notice in the Federal Register
proposing to extend, without
adjustment, Provo River Project’s
Formula Rate as Rate Order No. WAPA–
165.2 Consistent with its regulations at
10 CFR 903.23(a), Western did not hold
a consultation and comment period;
however, the customers were notified of
Western’s intent to extend the current
Formula Rate during the Provo River
Project Annual Customer Meeting on
April 22, 2014, and later through
certified letter. Western has received
notifications from the customers
through letter and email that they wish
to have Western extend the Provo River
Project Formula Rate.
Discussion
The Provo River Project’s Formula
Rate under Rate Order No. WAPA–149
expires on March 31, 2015. Contract
Nos. 94–SLC–0253, 94–SLC–0254, and
07–SLC–0601 between the United States
and customers require that each fiscal
year (FY) a new annual installment be
calculated in advance by Western and
submitted to the customers on or before
August 31 of the year preceding the
appropriate FY. Each FY Western
prepares a power repayment study,
which includes estimates of operation,
maintenance, and replacement costs for
the Deer Creek Powerplant. The annual
installment is adjusted on or before
August 31 of the year preceding the FY
to which it pertains, and Western
identifies this amount in contract
revisions. Each annual installment pays
the amortized portion of the United
States’ investment in the Deer Creek
hydroelectric facilities, with interest,
and the associated operation,
maintenance, and administrative costs.
This repayment schedule is not
dependent upon the capacity and
associated energy made available for
sale each year.
There is no adjustment to the Formula
Rate for the extension period, April 1,
2015, through March 31, 2020. The
forecasted revenue for the extension
period is $2,017,986 with an increase of
approximately $218,060 from the prior
rate period, due mostly to projected
turbine replacements. The data is
projected 6 years because FY 2015 is an
estimate used for the current FY 2015
annual installment.
Order
In view of the foregoing and under the
authority delegated to me, I confirm,
approve, and place into effect on an
interim basis an extension of the
Formula Rate, effective April 1, 2015.
The Formula Rate shall remain in effect
on an interim basis, pending FERC’s
confirmation and approval of this or a
substitute Formula Rate on a final basis,
through March 31, 2020.
Dated: February 4, 2015
Elizabeth Sherwood-Randall
Deputy Secretary
[FR Doc. 2015–02981 Filed 2–11–15; 8:45 am]
BILLING CODE 6450–01–P
1 See U.S. Dept. of Energy, Western Area Power
Admin., Docket No, EF10–5–000, 133 FERC ¶
62,112 (2010).
2 See 79 FR 60153 (October 6, 2014).
PO 00000
Frm 00038
Fmt 4703
Sfmt 9990
E:\FR\FM\12FEN1.SGM
12FEN1
Agencies
[Federal Register Volume 80, Number 29 (Thursday, February 12, 2015)]
[Notices]
[Pages 7863-7864]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2015-02981]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Western Area Power Administration
Provo River Project Rate Order No. WAPA-165
AGENCY: Western Area Power Administration, DOE.
ACTION: Notice of Rate Order Concerning a Formula Rate.
-----------------------------------------------------------------------
SUMMARY: Western Area Power Administration (Western) extends, on an
interim basis, the existing Provo River Project Formula Rate through
March 31, 2020. The existing Formula Rate under Rate Order No. WAPA-149
expires on March 31, 2015. The Formula Rate will be in effect until the
Federal Energy Regulatory Commission (FERC) places it into effect on a
final basis or until it is replaced by another rate.
DATES: This action is effective April 1, 2015.
FOR FURTHER INFORMATION CONTACT: Ms. Lynn C. Jeka, Colorado River
Storage Project (CRSP) Manager, CRSP Management Center, 150 East Social
Hall Avenue, Suite 300, Salt Lake City, UT 84111-1580, telephone (801)
524-6372, email: jeka@wapa.gov, or Mr. Rodney Bailey, Power Marketing
Manager, CRSP Management Center, 150 East Social Hall Avenue, Suite
300, Salt Lake City, UT 84111-1580, telephone (801) 524-4007, email:
rbailey@wapa.gov.
SUPPLEMENTARY INFORMATION: By Delegation Order No. 00-037.00A, the
Secretary of Energy delegated: (1) The authority to develop power and
transmission rates to Western's Administrator; (2) the authority to
confirm, approve, and place such rates into effect on an interim basis
to the Deputy Secretary of Energy; and (3) the authority to confirm,
approve, and place into effect on a final basis, to remand or to
disapprove such rates to FERC. This extension is issued pursuant to
Delegation Order No. 00-37.00A and Department of Energy (DOE) rate
extension procedures at 10 CFR 903.23(a).
Under Delegation Order No. 0204-108 and existing DOE procedures for
public participation in rate adjustments at 10 CFR part 903, Western's
Provo River Formula Rate was submitted to FERC for confirmation and
approval on February 2, 2010. The Provo River Formula Rate, Rate Order
No. WAPA-149, was approved for 5 years beginning April 1, 2010, and
ending March 31, 2015.
The Provo River Project, which includes Deer Creek Dam on the Provo
River in Utah, was authorized in 1935. Construction of the dam began in
1938 and was completed in 1951. The Deer Creek Powerplant was
authorized on August 20, 1951; construction began in 1956 and was
completed in 1958; generation began that same year. Its maximum
operating capacity is 5,200 kilowatts.
The Provo River Project's power is sold according to a marketing
plan that was published in the Federal Register on November 21, 1994
(59 FR 60010).
[[Page 7864]]
This marketing plan allows Western to sell the output of the Provo
River Project to Utah Municipal Power Agency, Utah Associated Municipal
Power Systems, and Heber Light and Power (Customers) in the Provo River
drainage area.
Contract Nos. 94-SLC-0253, 94-SLC-0254, and 07-SLC-0601 between the
United States and Customers require that each fiscal year (FY) a new
annual installment be calculated in advance by Western and submitted to
the Customers on or before August 31 of the year preceding the
applicable FY. Each FY Western prepares a power repayment study, which
includes estimates of operation, maintenance, and replacement costs for
the Deer Creek Powerplant. The annual installment is adjusted on or
before August 31 of the year preceding the FY to which it pertains, and
Western identifies this amount in contract revisions. Each annual
installment pays the amortized portion of the United States' investment
in the Deer Creek hydroelectric facilities, with interest, and the
associated operation, maintenance, and administrative costs. This
repayment schedule is not dependent upon the capacity and associated
energy made available for sale each year.
Rate extensions are authorized under 10 CFR 903.23. Rates
previously confirmed and approved by FERC for which no adjustment is
contemplated may be extended by the Deputy Secretary on an interim
basis following notice of proposed extension at least 30 days before
expiration. On October 6, 2014, Western published a notice of proposed
extension in the Federal Register [(79 FR 60153)].
Following review of Western's proposal within DOE, I hereby
approve, on an interim basis, Rate Order No. WAPA-165, which extends,
without adjustment, the existing Formula Rate through March 31, 2020.
Rate Order No. WAPA-165 will be submitted to FERC for confirmation and
approval on a final basis.
Dated: February 4, 2015.
Elizabeth Sherwood-Randall,
Deputy Secretary.
Department of Energy
Deputy Secretary
In the matter of:
Western Area Power Administration Formula Rate for the Provo River
Project
Rate Order No. WAPA-165
Order Confirming, Approving, and Placing the Formula Rate for the Provo
River Project Into Effect on an Interim Basis
Section 302 of the Department of Energy (DOE) Organization Act (42
U.S.C. 7152) transferred to and vested in the Secretary of Energy the
power marketing functions of the Secretary of the Department of the
Interior and the Bureau of Reclamation under the Reclamation Act of
1902 (ch. 1093, 32 Stat. 388), as amended and supplemented by
subsequent laws, particularly section 9(c) of the Reclamation Project
Act of 1939 (43 U.S.C. 485h(c)), and other acts that specifically apply
to the project involved.
By Delegation Order No. 00-037.00A, the Secretary of Energy
delegated: (1) The authority to develop power and transmission rates to
the Administrator of Western Area Power Administration (Western); (2)
the authority to confirm, approve, and place such rates into effect on
an interim basis to the Deputy Secretary; and (3) the authority to
confirm, approve, and place into effect on a final basis, to remand, or
to disapprove such rates to the Federal Energy Regulatory Commission
(FERC). This extension is issued pursuant to the Delegation Order and
DOE rate extension procedures at 10 CFR 903.23(a).
Background
On November 2, 2010, FERC confirmed and approved the existing
Formula Rate for the Provo River Project under Rate Order No. WAPA-
149.\1\ FERC approved this Rate Order for 5 years beginning April 1,
2010, through March 31, 2015. On October 6, 2014, pursuant to 10 CFR
903.23(a), Western filed a notice in the Federal Register proposing to
extend, without adjustment, Provo River Project's Formula Rate as Rate
Order No. WAPA-165.\2\ Consistent with its regulations at 10 CFR
903.23(a), Western did not hold a consultation and comment period;
however, the customers were notified of Western's intent to extend the
current Formula Rate during the Provo River Project Annual Customer
Meeting on April 22, 2014, and later through certified letter. Western
has received notifications from the customers through letter and email
that they wish to have Western extend the Provo River Project Formula
Rate.
---------------------------------------------------------------------------
\1\ See U.S. Dept. of Energy, Western Area Power Admin., Docket
No, EF10-5-000, 133 FERC ] 62,112 (2010).
\2\ See 79 FR 60153 (October 6, 2014).
---------------------------------------------------------------------------
Discussion
The Provo River Project's Formula Rate under Rate Order No. WAPA-
149 expires on March 31, 2015. Contract Nos. 94-SLC-0253, 94-SLC-0254,
and 07-SLC-0601 between the United States and customers require that
each fiscal year (FY) a new annual installment be calculated in advance
by Western and submitted to the customers on or before August 31 of the
year preceding the appropriate FY. Each FY Western prepares a power
repayment study, which includes estimates of operation, maintenance,
and replacement costs for the Deer Creek Powerplant. The annual
installment is adjusted on or before August 31 of the year preceding
the FY to which it pertains, and Western identifies this amount in
contract revisions. Each annual installment pays the amortized portion
of the United States' investment in the Deer Creek hydroelectric
facilities, with interest, and the associated operation, maintenance,
and administrative costs. This repayment schedule is not dependent upon
the capacity and associated energy made available for sale each year.
There is no adjustment to the Formula Rate for the extension
period, April 1, 2015, through March 31, 2020. The forecasted revenue
for the extension period is $2,017,986 with an increase of
approximately $218,060 from the prior rate period, due mostly to
projected turbine replacements. The data is projected 6 years because
FY 2015 is an estimate used for the current FY 2015 annual installment.
Order
In view of the foregoing and under the authority delegated to me, I
confirm, approve, and place into effect on an interim basis an
extension of the Formula Rate, effective April 1, 2015. The Formula
Rate shall remain in effect on an interim basis, pending FERC's
confirmation and approval of this or a substitute Formula Rate on a
final basis, through March 31, 2020.
Dated: February 4, 2015
Elizabeth Sherwood-Randall
Deputy Secretary
[FR Doc. 2015-02981 Filed 2-11-15; 8:45 am]
BILLING CODE 6450-01-P