Plains & Eastern Clean Line Transmission Project Draft Environmental Impact Statement Notice of Availability and Public Hearings; Correction, 78079-78080 [2014-30393]

Download as PDF Federal Register / Vol. 79, No. 248 / Monday, December 29, 2014 / Notices tkelley on DSK3SPTVN1PROD with NOTICES In addition, in making a competitive grant award, the Secretary also requires various assurances including those applicable to Federal civil rights laws that prohibit discrimination in programs or activities receiving Federal financial assistance from the Department of Education (34 CFR 100.4, 104.5, 106.4, 108.8, and 110.23). 3. Special Conditions: Under current 34 CFR 74.14 and, when grants are made under this NIA, 2 CFR 3474.10, the Secretary may impose special conditions and, in appropriate circumstances, high-risk conditions on a grant if the applicant or grantee is not financially stable; has a history of unsatisfactory performance; has a financial or other management system that does not meet the standards in 34 CFR part 74, as applicable or, when grants are awarded, the standards in 2 CFR 200, subpart D; has not fulfilled the conditions of a prior grant; or is otherwise not responsible. VI. Award Administration Information 1. Award Notices: If your application is successful, we notify your U.S. Representative and U.S. Senators and send you a Grant Award Notification (GAN); or we may send you an email containing a link to access an electronic version of your GAN. We may notify you informally, also. If your application is not evaluated or not selected for funding, we notify you. 2. Administrative and National Policy Requirements: We identify administrative and national policy requirements in the application package and reference these and other requirements in the Applicable Regulations section of this notice. We reference the regulations outlining the terms and conditions of an award in the Applicable Regulations section of this notice and include these and other specific conditions in the GAN. The GAN also incorporates your approved application as part of your binding commitments under the grant. 3. Reporting: (a) If you apply for a grant under this competition, you must ensure that you have in place the necessary processes and systems to comply with the reporting requirements in 2 CFR part 170 should you receive funding under the competition. This does not apply if you have an exception under 2 CFR 170.110(b). (b) At the end of your project period, you must submit a final performance report, including financial information, as directed by the Secretary. If you receive a multi-year award, you must submit an annual performance report that provides the most current performance and financial expenditure VerDate Sep<11>2014 19:09 Dec 24, 2014 Jkt 235001 information as directed by the Secretary under 34 CFR 75.118. The Secretary may also require more frequent performance reports under 34 CFR 75.720(c). For specific requirements on reporting, please go to www.ed.gov/ fund/grant/apply/appforms/ appforms.html. 4. Performance Measures: Under the Government Performance and Results Act of 1993 (GPRA), the Department developed the following performance measures to evaluate the overall effectiveness of CAMP: (1) the percentage of CAMP participants completing the first academic year of their postsecondary program, and (2) the percentage of CAMP participants who, after completing the first academic year of college, continue their postsecondary education. Applicants must propose annual targets for these measures in their applications. The national target for GPRA measure 1 for FY 2015 is that 86 percent of CAMP participants will complete the first academic year of their postsecondary program. The national target for GPRA measure 2 for FY 2015 is that 85 percent of CAMP participants continue their postsecondary education after completing the first academic year of college. The national targets for subsequent years may be adjusted based on additional baseline data. The panel readers will score related selection criteria on the basis of how well an applicant addresses these GPRA measures. Therefore, applicants will want to consider how to demonstrate a sound capacity to provide reliable data on GPRA measures, including the project’s annual performance targets for addressing the GPRA performance measures, as is required by the Office of Management and Budget approved annual performance report that is included in the application package. All grantees will be required to submit, as part of their annual performance report, information with respect to these GPRA performance measures. 5. Continuation Awards: In making a continuation award under 34 CFR 75.253, the Secretary considers, among other things: Whether a grantee has made substantial progress in achieving the goals and objectives of the project; whether the grantee has expended funds in a manner that is consistent with its approved application and budget; and, if the Secretary has established performance measurement requirements, the performance targets in the grantee’s approved application. In making a continuation grant, the Secretary also considers whether the grantee is operating in compliance with the assurances in its approved PO 00000 Frm 00055 Fmt 4703 Sfmt 4703 78079 application, including those applicable to Federal civil rights laws that prohibit discrimination in programs or activities receiving Federal financial assistance from the Department (34 CFR 100.4, 104.5, 106.4, 108.8, and 110.23). VII. Agency Contact FOR FURTHER INFORMATION CONTACT: Nathan Weiss, U.S. Department of Education, Office of Migrant Education, 400 Maryland Avenue SW., room 3E321, Washington, DC 20202–6135. Telephone Number: (202) 260–7496, or by email: nathan.weiss@ed.gov. If you use a TDD or a TYY, call the FRS, toll free, at 1–800–877–8339. VIII. Other Information Accessible Format: Individuals with disabilities can obtain this document and a copy of the application package in an accessible format (e.g., braille, large print, audiotape, or compact disc) on request to the program contact person listed under FOR FURTHER INFORMATION CONTACT in section VII of this notice. Electronic Access to This Document: The official version of this document is the document published in the Federal Register. Free Internet access to the official edition of the Federal Register and the Code of Federal Regulations is available via the Federal Digital System at: www.gpo.gov/fdsys. At this site you can view this document, as well as all other documents of this Department published in the Federal Register, in text or Adobe Portable Document Format (PDF). To use PDF you must have Adobe Acrobat Reader, which is available free at the site. You may also access documents of the Department published in the Federal Register by using the article search feature at: www.federalregister.gov. Specifically, through the advanced search feature at this site, you can limit your search to documents published by the Department. Dated: December 18, 2014. Deborah S. Delisle, Assistant Secretary for Elementary and Secondary Education. [FR Doc. 2014–30210 Filed 12–24–14; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Plains & Eastern Clean Line Transmission Project Draft Environmental Impact Statement Notice of Availability and Public Hearings; Correction Office of Electricity Delivery and Energy Reliability, Department of Energy. AGENCY: E:\FR\FM\29DEN1.SGM 29DEN1 78080 ACTION: Federal Register / Vol. 79, No. 248 / Monday, December 29, 2014 / Notices Correction. On December 17, 2014, the U.S. Department of Energy (DOE) published a notice of availability in the Federal Register of the Draft Environmental Impact Statement for the Plains & Eastern Clean Line Transmission Project (DOE/EIS–0486; Draft EIS). This notice corrects the date of the public comment period. FOR FURTHER INFORMATION CONTACT: Jane Summerson, Ph.D., DOE NEPA Document Manager on behalf of the Office of Electricity Delivery and Energy Reliability, U.S. Department of Energy, NNSA, PO Box 391 Building 401, Kirtland Air Force Base East, Albuquerque, NM 87185; email at Jane.Summerson01@nnsa.doe.gov; or phone (505) 845–4091. SUMMARY: Correction In the Federal Register dated December 17, 2014 in FR Doc. 2014– 29524, please make the following corrections on page 75132: The end of the first sentence in the DATES section, is corrected by removing ‘‘which ends on March 17, 2015’’ and adding ‘‘which begins on December 19, 2014, and ends on March 19, 2015’’ in its place. Issued in Washington, DC on December 19, 2014. Patricia A. Hoffman, Assistant Secretary Office of Electricity Delivery and Energy Reliability. [FR Doc. 2014–30393 Filed 12–24–14; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission tkelley on DSK3SPTVN1PROD with NOTICES Combined Notice Of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER14–2325–000. Applicants: Mosaic Fertilizer, LLC. Description: eTariff filing per 35.19a(b): Mosaic Refund Report to be effective N/A. Filed Date: 12/19/14. Accession Number: 20141219–5107. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER14–2666–002. Applicants: Avalon Solar Partners, LLC. Description: Notice of Non-Material Change in Status of Avalon Solar Partners, LLC. Filed Date: 12/19/14. Accession Number: 20141219–5080. Comments Due: 5 p.m. ET 1/9/15. VerDate Sep<11>2014 19:09 Dec 24, 2014 Jkt 235001 Docket Numbers: ER14–2666–002. Applicants: Avalon Solar Partners, LLC. Description: Errata [Appendix B] to December 19, 2014 Notice of NonMaterial Change in Status of Avalon Solar Partners, LLC. Filed Date: 12/19/14. Accession Number: 20141219–5135. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER14–2937–000. Applicants: American Transmission Systems, Incorporated, PJM Interconnection, L.L.C. Description: eTariff filing per 35.19a(b): ATSI submits Refund Report under Docket No. ER14–2937 to be effective N/A. Filed Date: 12/18/14. Accession Number: 20141218–5317. Comments Due: 5 p.m. ET 1/8/15. Docket Numbers: ER14–2940–001. Applicants: PJM Interconnection, L.L.C. Description: Compliance filing per 35: Compliance Filing per 11/28/2014 Order in Docket No. ER14–2940–000 to be effective 12/1/2014. Filed Date: 12/19/14. Accession Number: 20141219–5145. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER14–2956–002. Applicants: Hoopeston Wind, LLC. Description: Tariff Amendment per 35.17(b): Hoopeston MBRA Amendment to be effective 12/18/2014. Filed Date: 12/19/14. Accession Number: 20141219–5001. Comments Due: 5 p.m. ET 12/29/14. Docket Numbers: ER15–618–001. Applicants: PJM Interconnection, L.L.C., Virginia Electric and Power Company. Description: Tariff Amendment per 35.17(b): Dominion Errata Filing to Resubmit Amended Service Agreement No. 3453 to be effective 12/12/2014. Filed Date: 12/19/14. Accession Number: 20141219–5147. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–660–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Withdrawal per 35.15: Notice of Cancellation of Original Service Agreement No. 3528; Queue No. X3–041 to be effective 12/19/2014. Filed Date: 12/19/14. Accession Number: 20141219–5082. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–661–000. Applicants: Public Service Company of Oklahoma. Description: § 205(d) rate filing per 35.13(a)(2)(iii): PSO–OMPA Marlow Delivery Point Agreement to be effective 12/4/2014. PO 00000 Frm 00056 Fmt 4703 Sfmt 4703 Filed Date: 12/19/14. Accession Number: 20141219–5093. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–662–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Withdrawal per 35.15: Notice of Cancellation of Service Agreement No. 3588 to be effective 1/2/ 2015. Filed Date: 12/19/14. Accession Number: 20141219–5096. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–663–000. Applicants: AEP Generation Resources Inc. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Ohio Power Supply Agreement Amd Reflecting State Commission Mandated Updates to be effective 1/1/2015. Filed Date: 12/19/14. Accession Number: 20141219–5111. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–664–000. Applicants: PacifiCorp. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Certificate of Concurrence to be effective 1/1/2015. Filed Date: 12/19/14. Accession Number: 20141219–5158. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–665–000. Applicants: AP Holdings, LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): AP Holdings—Seller Category Filing to be effective 2/17/ 2015. Filed Date: 12/19/14. Accession Number: 20141219–5192. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–666–000. Applicants: AP Gas & Electric (PA), LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): AP–PA—Seller Category Filing to be effective 2/17/2015. Filed Date: 12/19/14. Accession Number: 20141219–5193. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–667–000. Applicants: AP Gas & Electric (MD), LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): AP–MD—Seller Category Filing to be effective 2/17/2015. Filed Date: 12/19/14. Accession Number: 20141219–5194. Comments Due: 5 p.m. ET 1/9/15. Docket Numbers: ER15–668–000. Applicants: AP Gas & Electric (NJ), LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): AP–NJ Seller Category Filing to be effective 2/17/2015. Filed Date: 12/19/14. Accession Number: 20141219–5195. E:\FR\FM\29DEN1.SGM 29DEN1

Agencies

[Federal Register Volume 79, Number 248 (Monday, December 29, 2014)]
[Notices]
[Pages 78079-78080]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-30393]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY


Plains & Eastern Clean Line Transmission Project Draft 
Environmental Impact Statement Notice of Availability and Public 
Hearings; Correction

AGENCY: Office of Electricity Delivery and Energy Reliability, 
Department of Energy.

[[Page 78080]]


ACTION: Correction.

-----------------------------------------------------------------------

SUMMARY: On December 17, 2014, the U.S. Department of Energy (DOE) 
published a notice of availability in the Federal Register of the Draft 
Environmental Impact Statement for the Plains & Eastern Clean Line 
Transmission Project (DOE/EIS-0486; Draft EIS). This notice corrects 
the date of the public comment period.

FOR FURTHER INFORMATION CONTACT:  Jane Summerson, Ph.D., DOE NEPA 
Document Manager on behalf of the Office of Electricity Delivery and 
Energy Reliability, U.S. Department of Energy, NNSA, PO Box 391 
Building 401, Kirtland Air Force Base East, Albuquerque, NM 87185; 
email at Jane.Summerson01@nnsa.doe.gov; or phone (505) 845-4091.

Correction

    In the Federal Register dated December 17, 2014 in FR Doc. 2014-
29524, please make the following corrections on page 75132:
    The end of the first sentence in the DATES section, is corrected by 
removing ``which ends on March 17, 2015'' and adding ``which begins on 
December 19, 2014, and ends on March 19, 2015'' in its place.

    Issued in Washington, DC on December 19, 2014.
Patricia A. Hoffman,
Assistant Secretary Office of Electricity Delivery and Energy 
Reliability.
[FR Doc. 2014-30393 Filed 12-24-14; 8:45 am]
BILLING CODE 6450-01-P