Federal Register / Vol. 79, No. 247 / Wednesday, December 24, 2014 / Notices
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability is January 6,
2015.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding(s) are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: December 17, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–30051 Filed 12–23–14; 8:45 am]
BILLING CODE 6717–01–P
mstockstill on DSK4VPTVN1PROD with NOTICES
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–27–000]
Trailblazer Pipeline Company LLC;
Notice of Request Under Blanket
Authorization
Take notice that on December 9, 2014,
Trailblazer Pipeline Company LLC
VerDate Sep<11>2014
16:34 Dec 23, 2014
Jkt 235001
(Trailblazer), 4200 West 115th Street,
Suite 350, Leawood, Kansas 66211–
2609, filed a prior notice application
pursuant to section 7(c) of the Natural
Gas Act (NGA) and sections 157.205 and
157.208 (b) of the Federal Energy
Regulatory Commission’s (Commission)
regulations under the NGA, and
Trailblazer’s blanket certificate issued in
Docket No. CP82–497–000. Trailblazer
seeks authorization to construct and
operate certain natural gas
transportation facilities in Weld County,
Colorado and Kimball County, Nebraska
(Niobrara Lateral). Specifically, Niobrara
Lateral project consists of: (1)
Approximately 16 miles of ten-inch
diameter high-pressure lateral pipeline
that will extend from an existing thirdparty natural gas processing facility in
Weld County, Colorado to Trailblazer’s
mainline, and then continue to a new
interconnect between the proposed
lateral pipeline and the mainline of
Rockies Express Pipeline LLC; (2)
measurement facilities; and (3) certain
ancillary facilities, all as more fully set
forth in the application, which is open
to the public for inspection. The filing
may also be viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding this
application should be directed Skip
George, Manager Regulatory, Tallgrass
Interstate Gas Transmission, LLC, 370
Van Gordon St., Lakewood, Colorado
80228–1519, or by phone (303) 763–
3251.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
PO 00000
Frm 00035
Fmt 4703
Sfmt 9990
77475
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenter will
not receive copies of all documents filed
by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Dated: December 17, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–30054 Filed 12–23–14; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\24DEN1.SGM
24DEN1
Agencies
[Federal Register Volume 79, Number 247 (Wednesday, December 24, 2014)]
[Notices]
[Page 77475]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-30054]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-27-000]
Trailblazer Pipeline Company LLC; Notice of Request Under Blanket
Authorization
Take notice that on December 9, 2014, Trailblazer Pipeline Company
LLC (Trailblazer), 4200 West 115th Street, Suite 350, Leawood, Kansas
66211-2609, filed a prior notice application pursuant to section 7(c)
of the Natural Gas Act (NGA) and sections 157.205 and 157.208 (b) of
the Federal Energy Regulatory Commission's (Commission) regulations
under the NGA, and Trailblazer's blanket certificate issued in Docket
No. CP82-497-000. Trailblazer seeks authorization to construct and
operate certain natural gas transportation facilities in Weld County,
Colorado and Kimball County, Nebraska (Niobrara Lateral). Specifically,
Niobrara Lateral project consists of: (1) Approximately 16 miles of
ten-inch diameter high-pressure lateral pipeline that will extend from
an existing third-party natural gas processing facility in Weld County,
Colorado to Trailblazer's mainline, and then continue to a new
interconnect between the proposed lateral pipeline and the mainline of
Rockies Express Pipeline LLC; (2) measurement facilities; and (3)
certain ancillary facilities, all as more fully set forth in the
application, which is open to the public for inspection. The filing may
also be viewed on the web at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or
TTY, (202) 502-8659.
Any questions regarding this application should be directed Skip
George, Manager Regulatory, Tallgrass Interstate Gas Transmission, LLC,
370 Van Gordon St., Lakewood, Colorado 80228-1519, or by phone (303)
763-3251.
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the regulations under the NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the allowed time for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the NGA.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenter will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
Dated: December 17, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-30054 Filed 12-23-14; 8:45 am]