Notice of Availability of Final Guidance on the Application of United States Code on Corridor Preservation, 67238-67239 [2014-26705]
Download as PDF
67238
Federal Register / Vol. 79, No. 218 / Wednesday, November 12, 2014 / Notices
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
[Docket Number: FTA–2013–0019]
Notice of Availability of Final Guidance
on the Application of United States
Code on Corridor Preservation
Federal Transit Administration
(FTA), DOT.
ACTION: Notice of availability of final
guidance.
AGENCY:
The FTA announces the
availability of final guidance on the
application of a provision of the Moving
Ahead for Progress in the 21st Century
Act (MAP–21) regarding corridor
preservation for future transit projects.
MAP–21 modified Federal transit law
by amending a previously existing
provision such that FTA can now, under
certain conditions, assist in the
acquisition of both non-railroad and
railroad right-of-way (ROW) for corridor
preservation before the environmental
review process under the National
Environmental Policy Act (NEPA) is
complete for any transit project that
could eventually use that ROW or could
later receive FTA financial assistance.
The final guidance defines the type of
ROW to which this MAP–21 provision
applies and explains the conditions and
requirements pertaining to its
application. On December 11, 2013,
FTA announced in the Federal Register
under docket number FTA–2013–0019
the availability of draft guidance and
requested public comment. FTA
received six comment letters and
presents its responses to those
comments in this notice.
DATES: This final guidance is effective
on November 12, 2014.
ADDRESSES: The final guidance is
available in the U.S. Government’s
electronic docket site at https://
www.regulations.gov under docket
number FTA–2013–0019 and on the
FTA Web site at https://www.fta.dot.gov.
FOR FURTHER INFORMATION CONTACT:
Nancy-Ellen Zusman, Office of Chief
Counsel, (312) 353–2577 or Terence
Plaskon, Office of Human and Natural
Environment, (202) 366–0442. FTA is
located at 1200 New Jersey Avenue SE.,
Washington, DC 20590. Office hours are
from 9:00 a.m. to 5:30 p.m., Monday
through Friday, except Federal holidays.
SUPPLEMENTARY INFORMATION:
TKELLEY on DSK3SPTVN1PROD with NOTICES
SUMMARY:
Background
Section 20016 of the Moving Ahead
for Progress in the 21st Century Act
(MAP–21) amended Federal transit law
by revising a pre-existing provision and
VerDate Sep<11>2014
17:55 Nov 10, 2014
Jkt 235001
moving it to 49 U.S.C. 5323(q) such that
FTA can now, under certain conditions,
assist in the acquisition of non-railroad
right-of-way (ROW) before the
completion of the National
Environmental Policy Act (NEPA)
environmental review process for any
project that could eventually use that
ROW or later receive FTA financial
assistance. The ‘‘environmental review
process’’ is defined in 23 U.S.C.
139(a)(3). The new provision of MAP–
21, which became effective on October
1, 2012, states:
(q) CORRIDOR PRESERVATION.—
(1) IN GENERAL.—The Secretary may
assist a recipient in acquiring right-of-way
before the completion of the environmental
reviews for any project that may use the
right-of-way if the acquisition is otherwise
permitted under Federal law. The Secretary
may establish restrictions on such an
acquisition as the Secretary determines to be
necessary and appropriate.
(2) ENVIRONMENTAL REVIEWS.—Rightof-way acquired under this subsection may
not be developed in anticipation of the
project until all required environmental
reviews for the project have been completed.
Prior to October 1, 2012, FTA allowed
this type of corridor preservation only
for pre-existing railroad ROW to be used
in a future transit project, pursuant to
the former provision of Federal transit
law that was modified and moved by
MAP–21. MAP–21 removed the word
‘‘railroad’’ from the provision formerly
in 49 U.S.C. 5324(c) and moved it to 49
U.S.C. 5323(q). Pursuant to authority
delegated by the Secretary, FTA
developed guidance that would (1)
specify the conditions under which this
provision may be used and (2) discuss
the application of that provision to
specific situations.
Comments
On December 11, 2013, FTA
announced in the Federal Register (78
FR 75446) the availability of the draft
guidance and requested comment on it.
The notice of availability of the draft
guidance contained a deadline of
January 10, 2014, for comment. As of
the date of issuance of this notice of
availability of the final guidance, FTA
considered all comments received in the
docket. FTA received comments from
two trade associations, two transit
agencies, and two members of the
public. Commenters provided 21
individual comments on the draft
guidance. FTA organized these
comments by topic. This notice
discusses the comments FTA received,
provides FTA’s responses to those
comments, and identifies resulting
changes FTA made to the guidance.
Three commenters provided general
comments that were supportive of the
PO 00000
Frm 00083
Fmt 4703
Sfmt 4703
draft guidance and requested no
changes. FTA notes these comments for
the record.
Two commenters supported FTA’s
definition of ROW in the context of
corridor preservation and thought its
broad scope had advantages. FTA notes
these comments for the record.
Three commenters questioned FTA’s
position in the draft guidance that once
the environmental review of a proposed
project is initiated corridor preservation
would not be appropriate and FTA
would not assist in any such
acquisition. Commenters stated that
FTA’s guidance should allow ROW
acquisition at any time before the
completion of NEPA review. FTA
considered these comments, agrees with
this recommendation, and revised the
guidance to reflect this. As a safeguard
and to remedy any concern about
prejudicing the NEPA process, FTA
notes in the final guidance that a project
sponsor must certify that the ROW
acquisition will not limit the choice of
reasonable alternatives for the project or
otherwise influence the decision on any
approval required for the project and
would not prevent the lead agencies
from making an impartial decision as to
whether to accept an alternative that is
being considered in the environmental
review process.
One commenter questioned whether
corridor preservation must be the
subject of an environmental review. The
commenter argued that the mere
acquisition of title for corridor
preservation purposes should not be
subject to NEPA review at all. FTA
disagrees with this argument. If an
applicant acquires ROW with FTA
funds, it is a Federal action. FTA and
the applicant must then complete an
environmental review of the acquisition
itself in accordance with NEPA and all
other applicable Federal environmental
laws and regulations. The ROW
acquisition is treated as a stand-alone
project with a separate NEPA document.
If the ROW acquisition does not use
Federal funds and has no Federal
approvals, then NEPA would not apply
to that acquisition; however, NEPA
would apply to the project using that
ROW itself if the project receives FTA
funds.
Two commenters remarked on the
appropriate level of NEPA review for
corridor preservation. One stated that a
categorical exclusion (CE) should be
FTA’s ‘‘default approach’’ and that
approaching corridor preservation in the
context of a CE would be appropriate in
the vast majority of circumstances. The
other commenter felt the guidance
needed clarification regarding this issue.
FTA does not take a ‘‘default approach’’
E:\FR\FM\12NON1.SGM
12NON1
TKELLEY on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 79, No. 218 / Wednesday, November 12, 2014 / Notices
in its environmental review, for corridor
preservation or otherwise. The
environmental review of ROW
acquisition must be completed in
accordance with NEPA and all other
applicable Federal laws and regulations.
FTA acknowledges that the CE found at
23 CFR § 771.118(d)(4), is potentially
available for the appropriate level of
NEPA review for corridor preservation;
FTA notes, however, that if the CE is to
be used then the conditions found in
Sections 771.118(a) and (b) must be met.
To add clarity, FTA revised the
guidance to reflect this discussion.
One commenter questioned the
guidance’s requirement that all FTA
planning requirements be satisfied for
corridor preservation, including having
the project in the Transportation
Improvement Program (TIP) and State
Transportation Improvement Program
(STIP). If ROW is acquired with FTA
funds, it is a Federal action and subject
to FTA’s metropolitan and statewide
planning requirements, meaning that
the corridor preservation project must
be included in Metropolitan
Transportation Plan (MTP), the TIP and
STIP. Moreover, even if the property is
acquired with local funds, the project
should be in the MTP if it is foreseeable
that FTA funds are expected to be used
for the project that would use that ROW.
Two commenters submitted
comments on the grants management/
administration portion of the guidance.
One commenter questioned FTA’s
expectation that a grantee implement a
transit project using the ROW within a
reasonable timeframe. The commenter
requested FTA articulate criteria for this
requirement. FTA declines to articulate
specific criteria, but notes that the
expectation of FTA is that when it
provides Federal funds for corridor
preservation that a project be built on
that property within a reasonable
timeframe. This is to ensure a proper
and appropriate use of Federal funds.
The final guidance is unchanged and
states that, in determining the
appropriate timeframe, FTA will consult
with the project sponsor and will
consider the planning status of any
proposed project that would use the
ROW. A second commenter questioned
the guidance’s requirement regarding
the disposition of the ROW in
accordance with 49 U.S.C. 5334(h)(1)–
(3), 49 U.S.C. 5334(h)(4), or 49 CFR
18.31(c). The commenter recommended
FTA allow for the repayment of Federal
funds when for some reason a project
does not proceed as an option to avoid
disposition of the ROW. One alternative
disposition method involves the
retention of title by the project sponsor
after compensating the Federal
VerDate Sep<11>2014
17:55 Nov 10, 2014
Jkt 235001
awarding agency. This is described in
FTA’s Grant Management Requirements
Circular (5010.1D), which sets forth all
of the real property disposition
requirements. See https://
www.fta.dot.gov/legislation_law/12349_
8640.html.
One commenter urged FTA to
encourage Congress to recognize the
importance of predictable funding over
improved streamlining. FTA decided
that this comment is outside the scope
of this guidance.
The final guidance is available in the
U.S. Government’s electronic docket site
at https://www.regulations.gov under
docket number FTA–2013–0019 and on
the FTA Web site at https://
www.fta.dot.gov.
Therese W. McMillan,
Acting Administrator, Federal Transit
Administration.
[FR Doc. 2014–26705 Filed 11–10–14; 8:45 am]
BILLING CODE P
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
Limitation on Claims Against Proposed
Public Transportation Projects
Federal Transit Administration
(FTA), DOT.
ACTION: Notice.
AGENCY:
This notice announces final
environmental actions taken by the
Federal Transit Administration (FTA)
for projects in San Diego, CA; Tarrant
County, TX; and Washington, DC. The
purpose of this notice is to announce
publicly the environmental decisions by
FTA on the subject projects and to
activate the limitation on any claims
that may challenge these final
environmental actions.
DATES: By this notice, FTA is advising
the public of final agency actions
subject to Section 139(l) of Title 23,
United States Code (U.S.C.). A claim
seeking judicial review of FTA actions
announced herein for the listed public
transportation projects will be barred
unless the claim is filed on or before
April 13, 2015.
FOR FURTHER INFORMATION CONTACT:
Nancy-Ellen Zusman, Assistant Chief
Counsel, Office of Chief Counsel, (312)
353–2577 or Terence Plaskon,
Environmental Protection Specialist,
Office of Human and Natural
Environment, (202) 366–0442. FTA is
located at 1200 New Jersey Avenue SE.,
Washington, DC 20590. Office hours are
from 9:00 a.m. to 5:30 p.m., Monday
through Friday, except Federal holidays.
SUMMARY:
PO 00000
Frm 00084
Fmt 4703
Sfmt 4703
67239
Notice is
hereby given that FTA has taken final
agency actions by issuing certain
approvals for the public transportation
projects listed below. The actions on the
projects, as well as the laws under
which such actions were taken, are
described in the documentation issued
in connection with the projects to
comply with the National
Environmental Policy Act (NEPA) and
in other documents in the FTA
administrative record for the projects.
Interested parties may contact either the
project sponsor or the relevant FTA
Regional Office for more information on
each project. Contact information for
FTA’s Regional Offices may be found at
https://www.fta.dot.gov.
This notice applies to all FTA
decisions on the listed projects as of the
issuance date of this notice and all laws
under which such actions were taken,
including, but not limited to, NEPA [42
U.S.C. 4321–4375], Section 4(f) of the
Department of Transportation Act of
1966 [49 U.S.C. 303], Section 106 of the
National Historic Preservation Act [16
U.S.C. 470f], and the Clean Air Act [42
U.S.C. 7401–7671q]. This notice does
not, however, alter or extend the
limitation period for challenges of
project decisions subject to previous
notices published in the Federal
Register. The projects and actions that
are the subject of this notice are:
1. Project name and location: MidCoast Corridor Transit Project, San
Diego, CA. Project sponsor: San Diego
Association of Governments (SANDAG).
Project description: SANDAG proposes
to extend operation of the San Diego
Trolley Blue Line from the Santa Fe
Depot in Downtown San Diego north to
the Old Town Transit Center (OTTC)
approximately 3.5 miles via the existing
Trolley tracks, and then north along
new tracks for 10.9 miles to the
University Town Centre Transit Center
in University City, with nine new
stations (four at-grade and five aerial)
and parking facilities at five stations.
The project includes upgrades to
existing facilities between Santa Fe
Depot and the OTTC, park-and-ride
facilities, and the acquisition of new
Trolley vehicles. Final agency actions:
Section 4(f) de minimis impact
determination; Section 106 finding of no
adverse effect; project-level air quality
conformity; and Record of Decision
(ROD), dated October 15, 2014.
Supporting documentation: Final
Supplemental Environmental Impact
Statement/Subsequent Environmental
Impact Report, dated October 15, 2014.
2. Project name and location: TEX
Rail Corridor Project, Tarrant County,
TX. Project sponsor: Fort Worth
SUPPLEMENTARY INFORMATION:
E:\FR\FM\12NON1.SGM
12NON1
Agencies
[Federal Register Volume 79, Number 218 (Wednesday, November 12, 2014)]
[Notices]
[Pages 67238-67239]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-26705]
[[Page 67238]]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Transit Administration
[Docket Number: FTA-2013-0019]
Notice of Availability of Final Guidance on the Application of
United States Code on Corridor Preservation
AGENCY: Federal Transit Administration (FTA), DOT.
ACTION: Notice of availability of final guidance.
-----------------------------------------------------------------------
SUMMARY: The FTA announces the availability of final guidance on the
application of a provision of the Moving Ahead for Progress in the 21st
Century Act (MAP-21) regarding corridor preservation for future transit
projects. MAP-21 modified Federal transit law by amending a previously
existing provision such that FTA can now, under certain conditions,
assist in the acquisition of both non-railroad and railroad right-of-
way (ROW) for corridor preservation before the environmental review
process under the National Environmental Policy Act (NEPA) is complete
for any transit project that could eventually use that ROW or could
later receive FTA financial assistance. The final guidance defines the
type of ROW to which this MAP-21 provision applies and explains the
conditions and requirements pertaining to its application. On December
11, 2013, FTA announced in the Federal Register under docket number
FTA-2013-0019 the availability of draft guidance and requested public
comment. FTA received six comment letters and presents its responses to
those comments in this notice.
DATES: This final guidance is effective on November 12, 2014.
ADDRESSES: The final guidance is available in the U.S. Government's
electronic docket site at https://www.regulations.gov under docket
number FTA-2013-0019 and on the FTA Web site at https://www.fta.dot.gov.
FOR FURTHER INFORMATION CONTACT: Nancy-Ellen Zusman, Office of Chief
Counsel, (312) 353-2577 or Terence Plaskon, Office of Human and Natural
Environment, (202) 366-0442. FTA is located at 1200 New Jersey Avenue
SE., Washington, DC 20590. Office hours are from 9:00 a.m. to 5:30
p.m., Monday through Friday, except Federal holidays.
SUPPLEMENTARY INFORMATION:
Background
Section 20016 of the Moving Ahead for Progress in the 21st Century
Act (MAP-21) amended Federal transit law by revising a pre-existing
provision and moving it to 49 U.S.C. 5323(q) such that FTA can now,
under certain conditions, assist in the acquisition of non-railroad
right-of-way (ROW) before the completion of the National Environmental
Policy Act (NEPA) environmental review process for any project that
could eventually use that ROW or later receive FTA financial
assistance. The ``environmental review process'' is defined in 23
U.S.C. 139(a)(3). The new provision of MAP-21, which became effective
on October 1, 2012, states:
(q) CORRIDOR PRESERVATION.--
(1) IN GENERAL.--The Secretary may assist a recipient in
acquiring right-of-way before the completion of the environmental
reviews for any project that may use the right-of-way if the
acquisition is otherwise permitted under Federal law. The Secretary
may establish restrictions on such an acquisition as the Secretary
determines to be necessary and appropriate.
(2) ENVIRONMENTAL REVIEWS.--Right-of-way acquired under this
subsection may not be developed in anticipation of the project until
all required environmental reviews for the project have been
completed.
Prior to October 1, 2012, FTA allowed this type of corridor
preservation only for pre-existing railroad ROW to be used in a future
transit project, pursuant to the former provision of Federal transit
law that was modified and moved by MAP-21. MAP-21 removed the word
``railroad'' from the provision formerly in 49 U.S.C. 5324(c) and moved
it to 49 U.S.C. 5323(q). Pursuant to authority delegated by the
Secretary, FTA developed guidance that would (1) specify the conditions
under which this provision may be used and (2) discuss the application
of that provision to specific situations.
Comments
On December 11, 2013, FTA announced in the Federal Register (78 FR
75446) the availability of the draft guidance and requested comment on
it. The notice of availability of the draft guidance contained a
deadline of January 10, 2014, for comment. As of the date of issuance
of this notice of availability of the final guidance, FTA considered
all comments received in the docket. FTA received comments from two
trade associations, two transit agencies, and two members of the
public. Commenters provided 21 individual comments on the draft
guidance. FTA organized these comments by topic. This notice discusses
the comments FTA received, provides FTA's responses to those comments,
and identifies resulting changes FTA made to the guidance.
Three commenters provided general comments that were supportive of
the draft guidance and requested no changes. FTA notes these comments
for the record.
Two commenters supported FTA's definition of ROW in the context of
corridor preservation and thought its broad scope had advantages. FTA
notes these comments for the record.
Three commenters questioned FTA's position in the draft guidance
that once the environmental review of a proposed project is initiated
corridor preservation would not be appropriate and FTA would not assist
in any such acquisition. Commenters stated that FTA's guidance should
allow ROW acquisition at any time before the completion of NEPA review.
FTA considered these comments, agrees with this recommendation, and
revised the guidance to reflect this. As a safeguard and to remedy any
concern about prejudicing the NEPA process, FTA notes in the final
guidance that a project sponsor must certify that the ROW acquisition
will not limit the choice of reasonable alternatives for the project or
otherwise influence the decision on any approval required for the
project and would not prevent the lead agencies from making an
impartial decision as to whether to accept an alternative that is being
considered in the environmental review process.
One commenter questioned whether corridor preservation must be the
subject of an environmental review. The commenter argued that the mere
acquisition of title for corridor preservation purposes should not be
subject to NEPA review at all. FTA disagrees with this argument. If an
applicant acquires ROW with FTA funds, it is a Federal action. FTA and
the applicant must then complete an environmental review of the
acquisition itself in accordance with NEPA and all other applicable
Federal environmental laws and regulations. The ROW acquisition is
treated as a stand-alone project with a separate NEPA document. If the
ROW acquisition does not use Federal funds and has no Federal
approvals, then NEPA would not apply to that acquisition; however, NEPA
would apply to the project using that ROW itself if the project
receives FTA funds.
Two commenters remarked on the appropriate level of NEPA review for
corridor preservation. One stated that a categorical exclusion (CE)
should be FTA's ``default approach'' and that approaching corridor
preservation in the context of a CE would be appropriate in the vast
majority of circumstances. The other commenter felt the guidance needed
clarification regarding this issue. FTA does not take a ``default
approach''
[[Page 67239]]
in its environmental review, for corridor preservation or otherwise.
The environmental review of ROW acquisition must be completed in
accordance with NEPA and all other applicable Federal laws and
regulations. FTA acknowledges that the CE found at 23 CFR Sec.
771.118(d)(4), is potentially available for the appropriate level of
NEPA review for corridor preservation; FTA notes, however, that if the
CE is to be used then the conditions found in Sections 771.118(a) and
(b) must be met. To add clarity, FTA revised the guidance to reflect
this discussion.
One commenter questioned the guidance's requirement that all FTA
planning requirements be satisfied for corridor preservation, including
having the project in the Transportation Improvement Program (TIP) and
State Transportation Improvement Program (STIP). If ROW is acquired
with FTA funds, it is a Federal action and subject to FTA's
metropolitan and statewide planning requirements, meaning that the
corridor preservation project must be included in Metropolitan
Transportation Plan (MTP), the TIP and STIP. Moreover, even if the
property is acquired with local funds, the project should be in the MTP
if it is foreseeable that FTA funds are expected to be used for the
project that would use that ROW.
Two commenters submitted comments on the grants management/
administration portion of the guidance. One commenter questioned FTA's
expectation that a grantee implement a transit project using the ROW
within a reasonable timeframe. The commenter requested FTA articulate
criteria for this requirement. FTA declines to articulate specific
criteria, but notes that the expectation of FTA is that when it
provides Federal funds for corridor preservation that a project be
built on that property within a reasonable timeframe. This is to ensure
a proper and appropriate use of Federal funds. The final guidance is
unchanged and states that, in determining the appropriate timeframe,
FTA will consult with the project sponsor and will consider the
planning status of any proposed project that would use the ROW. A
second commenter questioned the guidance's requirement regarding the
disposition of the ROW in accordance with 49 U.S.C. 5334(h)(1)-(3), 49
U.S.C. 5334(h)(4), or 49 CFR 18.31(c). The commenter recommended FTA
allow for the repayment of Federal funds when for some reason a project
does not proceed as an option to avoid disposition of the ROW. One
alternative disposition method involves the retention of title by the
project sponsor after compensating the Federal awarding agency. This is
described in FTA's Grant Management Requirements Circular (5010.1D),
which sets forth all of the real property disposition requirements. See
https://www.fta.dot.gov/legislation_law/12349_8640.html.
One commenter urged FTA to encourage Congress to recognize the
importance of predictable funding over improved streamlining. FTA
decided that this comment is outside the scope of this guidance.
The final guidance is available in the U.S. Government's electronic
docket site at https://www.regulations.gov under docket number FTA-2013-
0019 and on the FTA Web site at https://www.fta.dot.gov.
Therese W. McMillan,
Acting Administrator, Federal Transit Administration.
[FR Doc. 2014-26705 Filed 11-10-14; 8:45 am]
BILLING CODE P