Notice of Effectiveness of Exempt Wholesale Generator Status, 63115 [2014-25007]
Download as PDF
Federal Register / Vol. 79, No. 204 / Wednesday, October 22, 2014 / Notices
parties an opportunity to comment on
the Project. The FERC is the lead federal
Federal Energy Regulatory
agency responsible for conducting the
Commission
environmental review of this Project.
The Commission’s staff will prepare an
Notice of Effectiveness of Exempt
environmental impact statement (EIS)
Wholesale Generator Status
that discusses the environmental
impacts of the Project. This EIS will be
Docket Nos.
used in-part by the Commission to
determine whether the Project is in the
Dominion Solar Gen-Tie,
LLC ................................
EG14–71–000 public convenience and necessity.
You have been identified as a
Desert Green Solar Farm
LLC ................................
EG14–72–000 landowner or an interested party that
Seiling Wind, LLC .............
EG14–73–000 may be affected by new alternatives
Seiling Wind II, LLC ..........
EG14–74–000 being considered or by the
Mammoth Plains Wind
corresponding segment of the currently
Project, LLC ..................
EG14–75–000 planned route. Information in this
TX Jumbo Road Wind,
Notice was prepared to familiarize you
LLC ................................
EG14–76–000
with these new alternatives, the Project
Palo Duro Wind Energy,
LLC ................................
EG14–77–000 as a whole, and the Commission’s
OCI Alamo 4 LLC .............
EG14–78–000 environmental review process, and
instruct you on how to submit
Newark Energy Center,
LLC ................................
EG14–79–000 comments about the Project and the
alternatives under consideration. This
Take notice that during the months of Notice is also being sent to: Federal,
September 2014, the status of the above- state, and local government agencies;
captioned entities as Exempt Wholesale elected officials; environmental and
Generators became effective by
public interest groups; Native American
operation of the Commission’s
tribes; other interested parties; and local
regulations. 18 CFR 366.7(a).
libraries and newspapers. We encourage
elected officials and government
Dated: October 15, 2014.
representatives to notify their
Kimberly D. Bose,
constituents about the Project and
Secretary.
inform them on how they can comment
[FR Doc. 2014–25007 Filed 10–21–14; 8:45 am]
on their areas of concern. Please note
BILLING CODE 6717–01–P
that comments on this Notice should be
filed with the Commission by November
14, 2014.
DEPARTMENT OF ENERGY
If your property would be affected by
one of the alternatives under
Federal Energy Regulatory
consideration, you should have already
Commission
been contacted by a Sabal Trail
[Docket No. PF14–1–000]
representative. A Sabal Trail
representative may have also contacted
Sabal Trail Transmission, LLC;
you or may contact you in the near
Supplemental Notice of Intent To
future about the acquisition of an
Prepare an Environmental Impact
easement to construct, operate, and
Statement for the Planned Southeast
maintain the planned facilities or
Market Pipelines Project and Request
request permission to perform
for Comments on Environmental
environmental surveys on your
Issues Related to New Alternatives
property. Some landowners may not be
Under Consideration
contacted if the alternative across their
property is found to be either not
In response to concerns raised about
feasible or not environmentally
the Sabal Trail Transmission LLC’s
(Sabal Trail) planned Sabal Trail Project preferable to other alternatives being
considered. If the Commission approves
(Project),1 additional pipeline route
the Project, that approval conveys with
alternatives and compressor station
it the right of eminent domain.
location alternatives are now being
Therefore, if easement negotiations fail
considered. These alternatives which
to produce an agreement, the pipeline
are described below would affect new
company could initiate condemnation
landowners; therefore, the Federal
proceedings where compensation would
Energy Regulatory Commission (FERC
be determined in accordance with state
or Commission) is issuing this
supplemental notice (Notice) to provide law.
To help potentially affected
these landowners and other interested
landowners and other interested parties
better understand the Commission and
1 The Project is one of three projects being
its environmental review process, the
reviewed concurrently as the Southeast Market
Pipelines Project (SMP Project).
‘‘For Citizens’’ section of the FERC Web
mstockstill on DSK4VPTVN1PROD with NOTICES
DEPARTMENT OF ENERGY
VerDate Sep<11>2014
18:22 Oct 21, 2014
Jkt 235001
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
63115
site (www.ferc.gov) provides information
about getting involved in FERC
jurisdictional projects, and a citizens’
guide entitled ‘‘An Interstate Natural
Gas Facility On My Land? What Do I
Need to Know?’’ This guide addresses a
number of frequently asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Project Background
On October 16, 2013 the
Commission’s environmental staff
approved Sabal Trail’s request to use the
Commission Pre-Filing Process for the
Project. The purpose of the Pre-Filing
Process is to encourage the early
involvement of interested stakeholders
to identify and resolve project-related
issues before an application is filed with
the Commission. On February 18, 2014
the Commission issued a Notice of
Intent to Prepare an Environmental
Impact Statement for the Planned
Southeast Market Pipelines Project,
Request for Comments on
Environmental Issues, and Notice of
Public Scoping Meetings.
During the course of the Pre-Filing
Process, numerous concerns have been
expressed about the potential
environmental impacts of the Project.
Based on the merits of these comments
and to ensure that public concerns are
fully considered during the Pre-Filing
Process, additional alternatives have
been identified and are being
considered.
Project Summary
As noted previously, the Project is
part of the SMP Project and will be
reviewed concurrently along with the
Florida Southeast Connection Project
and the Hillabee Expansion Project. The
SMP Project would involve the
construction and operation of over 650
miles of interstate natural gas
transmission pipeline and associated
facilities in Alabama, Georgia, and
Florida. The Project would connect with
the Hillabee Expansion Project in
Alabama, and the Florida Southeast
Connection Project in Florida.
The Sabal Trail portion of the SMP
Project would involve the construction
and operation of approximately 460
miles of 36-inch-diameter natural gas
transmission pipeline beginning in
Tallapoosa County, Alabama and ending
in Osceola County, Florida. Sabal Trail
also plans to construct and operate
approximately 14 miles of 36-inchdiameter natural gas transmission
pipeline in Osceola and Orange
Counties, Florida (Hunters Creek Line)
and approximately 24 miles of 24-inchdiameter natural gas transmission
E:\FR\FM\22OCN1.SGM
22OCN1
Agencies
[Federal Register Volume 79, Number 204 (Wednesday, October 22, 2014)]
[Notices]
[Page 63115]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-25007]
[[Page 63115]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Effectiveness of Exempt Wholesale Generator Status
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
Dominion Solar Gen-Tie, LLC........................... EG14-71-000
Desert Green Solar Farm LLC........................... EG14-72-000
Seiling Wind, LLC..................................... EG14-73-000
Seiling Wind II, LLC.................................. EG14-74-000
Mammoth Plains Wind Project, LLC...................... EG14-75-000
TX Jumbo Road Wind, LLC............................... EG14-76-000
Palo Duro Wind Energy, LLC............................ EG14-77-000
OCI Alamo 4 LLC....................................... EG14-78-000
Newark Energy Center, LLC............................. EG14-79-000
------------------------------------------------------------------------
Take notice that during the months of September 2014, the status of
the above-captioned entities as Exempt Wholesale Generators became
effective by operation of the Commission's regulations. 18 CFR
366.7(a).
Dated: October 15, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-25007 Filed 10-21-14; 8:45 am]