Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information, 60515-60521 [2014-23428]
Download as PDF
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
reference in this finding, the NRC
concludes that the proposed action will
not have a significant effect on the
quality of the human environment.
Accordingly, the NRC staff has
determined that a finding of no
significant impact is appropriate.
This assessment is based on the
licensee’s letter dated July 31, 2013, as
supplemented by letters dated
December 11, 2013, and January 10,
2014. The KPS Supplemental Generic
Environmental Impact Statement for
License Renewal, dated August 2010,
was also considered in this review.
Otherwise, there are no other
environmental documents associated
with this review. These documents are
available for public inspection as
indicated above.
Dated at Rockville, Maryland, this 26th day
of September, 2014.
For the Nuclear Regulatory Commission.
Douglas A. Broaddus,
Chief, Plant Licensing IV–2 and
Decommissioning Transition Branch,
Division of Operating Reactor Licensing,
Office of Nuclear Reactor Regulation.
[FR Doc. 2014–23945 Filed 10–6–14; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2014–0205]
Applications and Amendments to
Facility Operating Licenses and
Combined Licenses Involving
Proposed No Significant Hazards
Considerations and Containing
Sensitive Unclassified Non-Safeguards
Information and Order Imposing
Procedures for Access to Sensitive
Unclassified Non-Safeguards
Information
Nuclear Regulatory
Commission.
ACTION: License amendment request;
opportunity to comment, request a
hearing, and petition for leave to
intervene; order.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) received and is
considering approval of three
amendment requests. The amendment
requests are for Columbia Generating
Station; Waterford Steam Electric
Station, Unit 3; and Seabrook Station,
Unit 1. For each amendment request,
the NRC proposes to determine that they
involve no significant hazards
consideration. In addition, each
amendment request contains sensitive
unclassified non-safeguards information
(SUNSI).
asabaliauskas on DSK5VPTVN1PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
Comments must be filed by
November 6, 2014. A request for a
hearing must be filed by December 8,
2014. Any potential party as defined in
§ 2.4 of Title 10 of the Code of Federal
Regulations (10 CFR), who believes
access to SUNSI is necessary to respond
to this notice must request document
access by October 17, 2014.
ADDRESSES: You may submit comments
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0205. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Office of Administration, Mail Stop:
3WFN–06–A44M, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
For additional direction on obtaining
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Sandra Figueroa, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington DC
20555–0001; telephone: 301–415–1262,
email: Sandra.Figueroa@nrc.gov.
SUPPLEMENTARY INFORMATION:
DATES:
I. Obtaining Information and
Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC–2014–
0205 when contacting the NRC about
the availability of information for this
action. You may obtain publiclyavailable information related to this
action by any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0205.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
60515
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in the SUPPLEMENTARY
INFORMATION section.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2014–
0205 in the subject line of your
comment submission, in order to ensure
that the NRC is able to make your
comment submission available to the
public in this docket.
The NRC cautions you not to include
identifying or contact information that
you do not want to be publicly
disclosed in your comment submission.
The NRC posts all comment
submissions at https://
www.regulations.gov as well as entering
the comment submissions into ADAMS.
The NRC does not routinely edit
comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information that
they do not want to be publicly
disclosed in their comment submission.
Your request should state that the NRC
does not routinely edit comment
submissions to remove such information
before making the comment
submissions available to the public or
entering the comment submissions into
ADAMS.
II. Background
Pursuant to Section 189a.(2) of the
Atomic Energy Act of 1954, as amended
(the Act), the NRC is publishing this
notice. The Act requires the
Commission to publish notice of any
amendments issued, or proposed to be
issued and grants the Commission the
authority to issue and make
immediately effective any amendment
to an operating license or combined
license, as applicable, upon a
determination by the Commission that
such amendment involves no significant
hazards consideration, notwithstanding
the pendency before the Commission of
a request for a hearing from any person.
This notice includes notices of
amendments containing SUNSI.
E:\FR\FM\07OCN1.SGM
07OCN1
60516
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
III. Notice of Consideration of Issuance
of Amendments to Facility Operating
Licenses and Combined Licenses,
Proposed No Significant Hazards
Consideration Determination, and
Opportunity for a Hearing
asabaliauskas on DSK5VPTVN1PROD with NOTICES
The Commission has made a
proposed determination that the
following amendment requests involve
no significant hazards consideration.
Under the Commission’s regulations in
10 CFR 50.92, this means that operation
of the facility in accordance with the
proposed amendment would not (1)
involve a significant increase in the
probability or consequences of an
accident previously evaluated, or (2)
create the possibility of a new or
different kind of accident from any
accident previously evaluated, or (3)
involve a significant reduction in a
margin of safety. The basis for this
proposed determination for each
amendment request is shown below.
The Commission is seeking public
comments on this proposed
determination. Any comments received
within 30 days after the date of
publication of this notice will be
considered in making any final
determination.
Normally, the Commission will not
issue the amendment until the
expiration of 60 days after the date of
publication of this notice. The
Commission may issue the license
amendment before expiration of the 60day period provided that its final
determination is that the amendment
involves no significant hazards
consideration. In addition, the
Commission may issue the amendment
prior to the expiration of the 30-day
comment period should circumstances
change during the 30-day comment
period such that failure to act in a
timely way would result, for example in
derating or shutdown of the facility.
Should the Commission take action
prior to the expiration of either the
comment period or the notice period, it
will publish in the Federal Register a
notice of issuance. Should the
Commission make a final No Significant
Hazards Consideration Determination,
any hearing will take place after
issuance. The Commission expects that
the need to take this action will occur
very infrequently.
A. Opportunity To Request a Hearing
and Petition for Leave To Intervene
Within 60 days after the date of
publication of this notice, any person(s)
whose interest may be affected by this
action may file a request for a hearing
and a petition to intervene with respect
to issuance of the amendment to the
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
subject facility operating license or
combined license. Requests for a
hearing and a petition for leave to
intervene shall be filed in accordance
with the Commission’s ‘‘Agency Rules
of Practice and Procedure’’ in 10 CFR
Part 2. Interested person(s) should
consult a current copy of 10 CFR 2.309,
which is available at the NRC’s PDR,
located at One White Flint North, Room
O1–F21, 11555 Rockville Pike (first
floor), Rockville, Maryland 20852. The
NRC’s regulations are accessible
electronically from the NRC Library on
the NRC’s Web site at https://
www.nrc.gov/reading-rm/doccollections/cfr/. If a request for a hearing
or petition for leave to intervene is filed
within 60 days, the Commission or a
presiding officer designated by the
Commission or by the Chief
Administrative Judge of the Atomic
Safety and Licensing Board Panel, will
rule on the request and/or petition; and
the Secretary or the Chief
Administrative Judge of the Atomic
Safety and Licensing Board will issue a
notice of a hearing or an appropriate
order.
As required by 10 CFR 2.309, a
petition for leave to intervene shall set
forth with particularity the interest of
the petitioner in the proceeding, and
how that interest may be affected by the
results of the proceeding. The petition
should specifically explain the reasons
why intervention should be permitted
with particular reference to the
following general requirements: (1) The
name, address, and telephone number of
the requestor or petitioner; (2) the
nature of the requestor’s/petitioner’s
right under the Act to be made a party
to the proceeding; (3) the nature and
extent of the requestor’s/petitioner’s
property, financial, or other interest in
the proceeding; and (4) the possible
effect of any decision or order which
may be entered in the proceeding on the
requestor’s/petitioner’s interest. The
petition must also set forth the specific
contentions which the requestor/
petitioner seeks to have litigated at the
proceeding.
Each contention must consist of a
specific statement of the issue of law or
fact to be raised or controverted. In
addition, the requestor/petitioner shall
provide a brief explanation of the bases
for the contention and a concise
statement of the alleged facts or expert
opinion which support the contention
and on which the requestor/petitioner
intends to rely in proving the contention
at the hearing. The requestor/petitioner
must also provide references to those
specific sources and documents of
which the petitioner is aware and on
which the requestor/petitioner intends
PO 00000
Frm 00073
Fmt 4703
Sfmt 4703
to rely to establish those facts or expert
opinion. The petition must include
sufficient information to show that a
genuine dispute exists with the
applicant on a material issue of law or
fact. Contentions shall be limited to
matters within the scope of the
amendment under consideration. The
contention must be one which, if
proven, would entitle the requestor/
petitioner to relief. A requestor/
petitioner who fails to satisfy these
requirements with respect to at least one
contention will not be permitted to
participate as a party.
Those permitted to intervene become
parties to the proceeding, subject to any
limitations in the order granting leave to
intervene, and have the opportunity to
participate fully in the conduct of the
hearing.
If a hearing is requested, and the
Commission has not made a final
determination on the issue of no
significant hazards consideration, the
Commission will make a final
determination on the issue of no
significant hazards consideration. The
final determination will serve to decide
when the hearing is held. If the final
determination is that the amendment
request involves no significant hazards
consideration, the Commission may
issue the amendment and make it
immediately effective, notwithstanding
the request for a hearing. Any hearing
held would take place after issuance of
the amendment. If the final
determination is that the amendment
request involves a significant hazards
consideration, then any hearing held
would take place before the issuance of
any amendment unless the Commission
finds an imminent danger to the health
or safety of the public, in which case it
will issue an appropriate order or rule
under 10 CFR part 2.
B. Electronic Submissions (E-Filing)
All documents filed in NRC
adjudicatory proceedings, including a
request for hearing, a petition for leave
to intervene, any motion or other
document filed in the proceeding prior
to the submission of a request for
hearing or petition to intervene, and
documents filed by interested
governmental entities participating
under 10 CFR 2.315(c), must be filed in
accordance with the NRC’s E-Filing rule
(72 FR 49139; August 28, 2007). The EFiling process requires participants to
submit and serve all adjudicatory
documents over the internet, or in some
cases to mail copies on electronic
storage media. Participants may not
submit paper copies of their filings
unless they seek an exemption in
E:\FR\FM\07OCN1.SGM
07OCN1
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
accordance with the procedures
described below.
To comply with the procedural
requirements of E-Filing, at least 10
days prior to the filing deadline, the
participant should contact the Office of
the Secretary by email at
hearing.docket@nrc.gov, or by telephone
at 301–415–1677, to request (1) a digital
identification (ID) certificate, which
allows the participant (or its counsel or
representative) to digitally sign
documents and access the E-Submittal
server for any proceeding in which it is
participating; and (2) advise the
Secretary that the participant will be
submitting a request or petition for
hearing (even in instances in which the
participant, or its counsel or
representative, already holds an NRCissued digital ID certificate). Based upon
this information, the Secretary will
establish an electronic docket for the
hearing in this proceeding if the
Secretary has not already established an
electronic docket.
Information about applying for a
digital ID certificate is available on the
NRC’s public Web site at https://
www.nrc.gov/site-help/e-submittals/
getting-started.html. System
requirements for accessing the ESubmittal server are detailed in the
NRC’s ‘‘Guidance for Electronic
Submission,’’ which is available on the
agency’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html. Participants may
attempt to use other software not listed
on the Web site, but should note that the
NRC’s E-Filing system does not support
unlisted software, and the NRC Meta
System Help Desk will not be able to
offer assistance in using unlisted
software.
If a participant is electronically
submitting a document to the NRC in
accordance with the E-Filing rule, the
participant must file the document
using the NRC’s online, Web-based
submission form. In order to serve
documents through the Electronic
Information Exchange System, users
will be required to install a Web
browser plug-in from the NRC’s Web
site. Further information on the Webbased submission form, including the
installation of the Web browser plug-in,
is available on the NRC’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html.
Once a participant has obtained a
digital ID certificate and a docket has
been created, the participant can then
submit a request for hearing or petition
for leave to intervene. Submissions
should be in Portable Document Format
(PDF) in accordance with NRC guidance
available on the NRC’s public Web site
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered
complete at the time the documents are
submitted through the NRC’s E-Filing
system. To be timely, an electronic
filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern
Time on the due date. Upon receipt of
a transmission, the E-Filing system
time-stamps the document and sends
the submitter an email notice
confirming receipt of the document. The
E-Filing system also distributes an email
notice that provides access to the
document to the NRC’s Office of the
General Counsel and any others who
have advised the Office of the Secretary
that they wish to participate in the
proceeding, so that the filer need not
serve the documents on those
participants separately. Therefore,
applicants and other participants (or
their counsel or representative) must
apply for and receive a digital ID
certificate before a hearing request/
petition to intervene is filed so that they
can obtain access to the document via
the E-Filing system.
A person filing electronically using
the NRC’s adjudicatory E-Filing system
may seek assistance by contacting the
NRC Meta System Help Desk through
the ‘‘Contact Us’’ link located on the
NRC’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html, by email to
MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC
Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have a good cause for not submitting
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial paper
filing requesting authorization to
continue to submit documents in paper
format. Such filings must be submitted
by: (1) First class mail addressed to the
Office of the Secretary of the
Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, Attention: Rulemaking and
Adjudications Staff; or (2) courier,
express mail, or expedited delivery
service to the Office of the Secretary,
Sixteenth Floor, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland, 20852, Attention:
Rulemaking and Adjudications Staff.
Participants filing a document in this
manner are responsible for serving the
document on all other participants.
Filing is considered complete by firstclass mail as of the time of deposit in
the mail, or by courier, express mail, or
expedited delivery service upon
PO 00000
Frm 00074
Fmt 4703
Sfmt 4703
60517
depositing the document with the
provider of the service. A presiding
officer, having granted an exemption
request from using E-Filing, may require
a participant or party to use E-Filing if
the presiding officer subsequently
determines that the reason for granting
the exemption from use of E-Filing no
longer exists.
Documents submitted in adjudicatory
proceedings will appear in the NRC’s
electronic hearing docket which is
available to the public at https://
ehd1.nrc.gov/ehd/, unless excluded
pursuant to an order of the Commission,
or the presiding officer. Participants are
requested not to include personal
privacy information, such as social
security numbers, home addresses, or
home phone numbers in their filings,
unless an NRC regulation or other law
requires submission of such
information. However, a request to
intervene will require including
information on local residence in order
to demonstrate a proximity assertion of
interest in the proceeding. With respect
to copyrighted works, except for limited
excerpts that serve the purpose of the
adjudicatory filings and would
constitute a Fair Use application,
participants are requested not to include
copyrighted materials in their
submission.
Petitions for leave to intervene must
be filed no later than 60 days from the
date of publication of this notice.
Requests for hearing, petitions for leave
to intervene, and motions for leave to
file new or amended contentions that
are filed after the 60-day deadline will
not be entertained absent a
determination by the presiding officer
that the filing demonstrates good cause
by satisfying the three factors in 10 CFR
2.309(c)(1)(i)–(iii).
For further details with respect to this
amendment action, see the application
for amendment which is available for
public inspection at the NRC’s PDR,
located at One White Flint North, Room
O1–F21, 11555 Rockville Pike (first
floor), Rockville, Maryland 20852.
Publicly available documents created or
received at the NRC are accessible
electronically through ADAMS in the
NRC Library at https://www.nrc.gov/
reading-rm/adams.html. If you do not
have access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the PDR’s
Reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov.
E:\FR\FM\07OCN1.SGM
07OCN1
60518
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Energy Northwest, Docket No. 50–397,
Columbia Generating Station,
(Columbia) Benton County, Washington
Date of amendment request: June 25,
2014. A publicly-available version is in
ADAMS under Accession No.
ML14188C091.
Description of amendment request:
This amendment request contains
sensitive unclassified non-safeguards
information (SUNSI). The amendment
would revise the Columbia Generating
Station Cyber Security Plan (CSP)
Milestone 8 full implementation date as
set forth in the CSP Implementation
Schedule.
Basis for proposed no significant
hazards consideration determination:
As required by 10 CFR 50.91(a), the
licensee has provided its analysis of the
issue of no significant hazards
consideration, which is presented
below:
1. Do the proposed changes involve a
significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
The proposed change to the Columbia CSP
Implementation Schedule is administrative
in nature. This change does not alter any
accident analysis assumptions, add any
initiators, or affect the function of plant
systems or the manner in which systems are
operated, maintained, modified, tested, or
inspected. Although implementation of the
CSP may require modifications involving
digital assets, the proposed change does [not]
affect the nature, function, or configuration of
those modifications, only the timing of their
required completion. Similarly, the manner
in which other activities involve in CSP
implementation, such as performance of
assessments, update of existing procedures,
preparation of new procedures, and changes
to, or development of, programs, will not be
affected; only their required completion date.
Measures have or will be taken in the interim
to provide adequate protection of critical
digital assets.
Therefore, the proposed change does not
involve a significant increase in the
probability or consequences of an accident
previously evaluated.
2. Do the proposed changes create the
possibility of a new or different kind of
accident from any accident previously
evaluated?
Response: No.
The proposed change to the Columbia CSP
Implementation Schedule is administrative
in nature. The proposed change does not add
any accident initiators. Although
implementation of the CSP may alter plant
systems or components or the manner in
which systems and components are operated,
maintained, modified, tested, or inspected,
the proposed change only affects the
completion date for such alterations.
Therefore, the proposed change does not
create the possibility of a new or different
kind of accident from any accident
previously evaluated.
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
3. Do the proposed changes involve a
significant reduction in a margin of safety?
Response: No.
Plant safety margins are established
through limiting conditions for operation,
limiting safety system settings, and safety
limits specified in the Technical
Specifications which are part of the plant
license. The proposed change to the
Columbia CSP Implementation Schedule is
administrative in nature in that it only affects
the required completion date for certain
activities, and does not affect the nature of
those activities nor does it affect any safety
margins.
Therefore, the proposed change does not
involve a reduction in a margin of safety.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
proposes to determine that the
amendment request involves no
significant hazards consideration.
Attorney for licensee: William A.
Horin, Esq., Winston & Strawn, 1700 K
Street NW., Washington, DC 20006–
3817.
Acting NRC Branch Chief: Eric R.
Oesterle.
Entergy Operations, Inc., Docket No. 50–
382, Waterford Steam Electric Station,
(Waterford 3), Unit 3, St. Charles Parish,
Louisiana
Date of amendment request: August 4,
2014. A publicly-available version is in
ADAMS under Accession Nos.
ML14217A498, ML14217A496, and
ML14217A497.
Description of amendment request:
This amendment request contains
sensitive unclassified non-safeguards
information (SUNSI). The amendment
would change the Waterford 3, Cyber
Security Plan (CSP) Implementation
Schedule Milestone 8 full
implementation date and revise the
existing operating license physical
protection license condition.
Basis for proposed no significant
hazards consideration determination:
As required by 10 CFR 50.91(a), the
licensee has provided its analysis of the
issue of no significant hazards
consideration, which is presented
below:
1. Does the proposed change involve a
significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
The proposed change to the CSP
Implementation Schedule is administrative
in nature. This change does not alter accident
analysis assumptions, add any initiators, or
affect the function of plant systems or the
manner in which systems are operated,
maintained, modified, tested, or inspected.
The proposed change does not require any
PO 00000
Frm 00075
Fmt 4703
Sfmt 4703
plant modifications which affect the
performance capability of the structures,
systems, and components relied upon to
mitigate the consequences of postulated
accidents and has no impact on the
probability or consequences of an accident
previously evaluated.
Therefore, the proposed change does not
involve a significant increase in the
probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the
possibility of a new or different kind of
accident from any accident previously
evaluated?
Response: No.
The proposed change to the CSP
Implementation Schedule is administrative
in nature. This proposed change does not
alter accident analysis assumptions, add any
initiators, or affect the function of plant
systems or the manner in which systems are
operated, maintained, modified, tested, or
inspected. The proposed change does not
require any plant modifications which affect
the performance capability of the structures,
systems, and components relied upon to
mitigate the consequences of postulated
accidents and does not create the possibility
of a new or different kind of accident from
any accident previously evaluated.
Therefore, the proposed change does not
create the possibility of a new or different
kind of accident from any accident
previously evaluated.
3. Does the proposed change involve a
significant reduction in a margin of safety?
Response: No.
Plant safety margins are established
through limiting conditions for operation,
limiting safety system settings, and safety
limits specified in the technical
specifications. The proposed change to the
CSP Implementation Schedule is
administrative in nature. In addition, the
milestone date delay for full implementation
of the CSP has no substantive impact because
other measures have been taken which
provide adequate protection during this
period of time. Because there is no change to
established safety margins as a result of this
change, the proposed change does not
involve a significant reduction in a margin of
safety.
Therefore, the proposed change does not
involve a significant reduction in a margin of
safety.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
proposes to determine that the
amendment request involves no
significant hazards consideration.
Attorney for licensee: Joseph A.
Aluise, Associate General Counsel—
Nuclear, Entergy Services, Inc., 639
Loyola Avenue, New Orleans, LA
70113.
NRC Branch Chief: Douglas A.
Broaddus.
E:\FR\FM\07OCN1.SGM
07OCN1
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
NextEra Energy Seabrook LLC, Docket
No. 50–443, Seabrook Station, Unit 1,
Rockingham County, New Hampshire
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Date of amendment request: July 10,
2014, as supplemented by letter dated
July 22, 2014. Publicly-available
versions are in ADAMS under
Accession Nos. ML14198A085 and
ML14205A421, respectively.
Description of amendment request:
This amendment request contains
sensitive unclassified non-safeguards
information (SUNSI). The proposed
amendment would revise the Seabrook
Station, Unit 1, Cyber Security Plan
(CSP) Milestone 8 full implementation
date, as set forth in the Cyber Security
Plan Implementation Schedule.
Basis for proposed no significant
hazards consideration determination:
As required by 10 CFR 50.91(a), the
licensee has provided its analysis of the
issue of no significant hazards
consideration, which is presented
below:
1. Does the proposed change involve a
significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
The proposed change to the Cyber Security
Plan implementation schedule is
administrative in nature. The change does
not alter accident analysis assumptions, add
any initiators, or affect the function of plant
systems or the manner in which systems are
operated, maintained, tested, or inspected.
The proposed change does not require any
plant modifications which affect the
performance capability or the structures,
systems, and components relied upon to
mitigate the consequences of postulated
accidents and has no impact on the
probability or consequences of an accident
previously evaluated.
Therefore, the proposed change does not
involve a significant increase in the
probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the
possibility of a new or different kind of
accident from any accident previously
evaluated?
Response: No.
The proposed change to the Cyber Security
Plan implementation schedule is
administrative in nature. This proposed
change does not alter accident analysis
assumptions, add any initiators, or affect the
function of plant systems or the manner in
which systems are operated, maintained,
tested, or inspected. The proposed change
does not require any plant modifications
which affect the performance capability or
the structures, systems, and components
relied upon to mitigate the consequences of
postulated accidents and does not create the
possibility of a new or different kind of
accident from any accident previously
evaluated.
Therefore, the proposed change does not
create the possibility of a new or different
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
kind of accident from any accident
previously evaluated.
3. Does the proposed change involve a
significant reduction in a margin of safety?
Response: No.
Plant safety margins are established
through limiting conditions of operation,
limiting safety systems settings, and safety
limits specified in the technical
specifications. The proposed change to the
Cyber Security Plan implementation
schedule is administrative in nature. Because
there is no change in these established safety
margins as result of this change, the proposed
change does not involve a significant
reduction in a margin of safety.
Therefore, the proposed change does not
involve a significant reduction in a margin of
safety.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
proposes to determine that the
amendment request involves no
significant hazards consideration.
Attorney for licensee: M.S. Ross,
Florida Power & Light Company, P.O.
Box 14000, Juno Beach, Florida 33408–
0420.
Acting NRC Branch Chief: Robert
Schaaf.
Order Imposing Procedures for Access
to Sensitive Unclassified NonSafeguards Information for Contention
Preparation
Energy Northwest, Docket No. 50–397,
Columbia Generating Station, Benton
County, Washington
Entergy Operations, Inc., Docket No.
50–382, Waterford Steam Electric
Station, Unit 3, Charles Parish,
Louisiana
NextEra Energy Seabrook LLC, Docket
No. 50–443, Seabrook Station, Unit 1,
Rockingham County, New Hampshire
Order Imposing Procedures for Access
to Sensitive Unclassified NonSafeguards Information for Contention
Preparation
A. This Order contains instructions
regarding how potential parties to this
proceeding may request access to
documents containing SUNSI.
B. Within 10 days after publication of
this notice of hearing and opportunity to
petition for leave to intervene, any
potential party who believes access to
SUNSI is necessary to respond to this
notice may request such access. A
‘‘potential party’’ is any person who
intends to participate as a party by
demonstrating standing and filing an
admissible contention under 10 CFR
2.309. Requests for access to SUNSI
submitted later than 10 days after
publication of this notice will not be
PO 00000
Frm 00076
Fmt 4703
Sfmt 4703
60519
considered absent a showing of good
cause for the late filing, addressing why
the request could not have been filed
earlier.
C. The requester shall submit a letter
requesting permission to access SUNSI
to the Office of the Secretary, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001, Attention:
Rulemakings and Adjudications Staff,
and provide a copy to the Associate
General Counsel for Hearings,
Enforcement and Administration, Office
of the General Counsel, Washington, DC
20555–0001. The expedited delivery or
courier mail address for both offices is:
U.S. Nuclear Regulatory Commission,
11555 Rockville Pike, Rockville,
Maryland 20852. The email address for
the Office of the Secretary and the
Office of the General Counsel are
Hearing.Docket@nrc.gov and
OGCmailcenter@nrc.gov, respectively.1
The request must include the following
information:
(1) A description of the licensing
action with a citation to this Federal
Register notice;
(2) The name and address of the
potential party and a description of the
potential party’s particularized interest
that could be harmed by the action
identified in C.(1); and
(3) The identity of the individual or
entity requesting access to SUNSI and
the requester’s basis for the need for the
information in order to meaningfully
participate in this adjudicatory
proceeding. In particular, the request
must explain why publicly-available
versions of the information requested
would not be sufficient to provide the
basis and specificity for a proffered
contention.
D. Based on an evaluation of the
information submitted under paragraph
C.(3) the NRC staff will determine
within 10 days of receipt of the request
whether:
(1) There is a reasonable basis to
believe the petitioner is likely to
establish standing to participate in this
NRC proceeding; and
(2) The requestor has established a
legitimate need for access to SUNSI.
E. If the NRC staff determines that the
requestor satisfies both D.(1) and D.(2)
above, the NRC staff will notify the
requestor in writing that access to
SUNSI has been granted. The written
notification will contain instructions on
how the requestor may obtain copies of
the requested documents, and any other
1 While a request for hearing or petition to
intervene in this proceeding must comply with the
filing requirements of the NRC’s ‘‘E-Filing Rule,’’
the initial request to access SUNSI under these
procedures should be submitted as described in this
paragraph.
E:\FR\FM\07OCN1.SGM
07OCN1
60520
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
conditions that may apply to access to
those documents. These conditions may
include, but are not limited to, the
signing of a Non-Disclosure Agreement
or Affidavit, or Protective Order 2 setting
forth terms and conditions to prevent
the unauthorized or inadvertent
disclosure of SUNSI by each individual
who will be granted access to SUNSI.
F. Filing of Contentions. Any
contentions in these proceedings that
are based upon the information received
as a result of the request made for
SUNSI must be filed by the requestor no
later than 25 days after the requestor is
granted access to that information.
However, if more than 25 days remain
between the date the petitioner is
granted access to the information and
the deadline for filing all other
contentions (as established in the notice
of hearing or opportunity for hearing),
the petitioner may file its SUNSI
contentions by that later deadline. This
provision does not extend the time for
filing a request for a hearing and
petition to intervene, which must
comply with the requirements of 10 CFR
2.309.
G. Review of Denials of Access.
(1) If the request for access to SUNSI
is denied by the NRC staff after a
determination on standing and need for
access, the NRC staff shall immediately
notify the requestor in writing, briefly
stating the reason or reasons for the
denial.
(2) The requester may challenge the
NRC staff’s adverse determination by
filing a challenge within five days of
receipt of that determination with: (a)
The presiding officer designated in this
proceeding; (b) if no presiding officer
has been appointed, the Chief
Administrative Judge, or if he or she is
unavailable, another administrative
judge, or an administrative law judge
with jurisdiction pursuant to 10 CFR
2.318(a); or (c) officer if that officer has
been designated to rule on information
access issues.
H. Review of Grants of Access. A
party other than the requester may
challenge an NRC staff determination
granting access to SUNSI whose release
would harm that party’s interest
independent of the proceeding. Such a
challenge must be filed with the Chief
Administrative Judge within five days of
the notification by the NRC staff of its
grant of access.
If challenges to the NRC staff
determinations are filed, these
procedures give way to the normal
process for litigating disputes
concerning access to information. The
availability of interlocutory review by
the Commission of orders ruling on
such NRC staff determinations (whether
granting or denying access) is governed
by 10 CFR 2.311.3
I. The Commission expects that the
NRC staff and presiding officers (and
any other reviewing officers) will
consider and resolve requests for access
to SUNSI, and motions for protective
orders, in a timely fashion in order to
minimize any unnecessary delays in
identifying those petitioners who have
standing and who have propounded
contentions meeting the specificity and
basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes
the general target schedule for
processing and resolving requests under
these procedures.
IT IS SO ORDERED.
Dated at Rockville, Maryland, this 25th day
of September, 2014.
Annette L. Vietti-Cook,
Secretary, Nuclear Regulatory Commission.
ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE
UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING
Day
Event/Activity
0 ...............
Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions
for access requests.
Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the
potential party to participate meaningfully in an adjudicatory proceeding.
Deadline for submitting petition for intervention containing: (i) demonstration of standing; and (ii) all contentions whose formulation
does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply).
U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access
provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any
party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If
NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation
of redactions or review of redacted documents).
If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the
proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion
seeking a ruling to reverse the NRC staff’s grant of access.
Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
(Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file
motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement
for SUNSI.
If access granted: issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse
determination by the NRC staff.
Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective
order.
Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline.
(Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
10 .............
60 .............
20 .............
25 .............
30 .............
40 .............
A ..............
asabaliauskas on DSK5VPTVN1PROD with NOTICES
A + 3 ........
A + 28 ......
A + 53 ......
2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must
be filed with the presiding officer or the Chief
Administrative Judge if the presiding officer has not
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
yet been designated, within 30 days of the deadline
for the receipt of the written access request.
3 Requesters should note that the filing
requirements of the NRC’s E-Filing Rule (72 FR
49139; August 28, 2007) apply to appeals of NRC
PO 00000
Frm 00077
Fmt 4703
Sfmt 4703
staff determinations (because they must be served
on a presiding officer or the Commission, as
applicable), but not to the initial SUNSI request
submitted to the NRC staff under these procedures.
E:\FR\FM\07OCN1.SGM
07OCN1
Federal Register / Vol. 79, No. 194 / Tuesday, October 7, 2014 / Notices
60521
ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE
UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued
Day
A + 60 ......
>A + 60 ....
Event/Activity
(Answer receipt +7) Petitioner/Intervenor reply to answers.
Decision on contention admission.
NUCLEAR REGULATORY
COMMISSION
[FR Doc. 2014–23428 Filed 10–6–14; 8:45 am]
BILLING CODE 7590–01–P
[NRC–2014–0001]
NUCLEAR REGULATORY
COMMISSION
Sunshine Act Meeting Notice
Weeks of October 6, 13, 20, 27,
November 3, 10, 2014.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
DATED:
[Docket No. 50–293; NRC–2014–0202]
Entergy Nuclear Operations, Inc.;
Pilgrim Nuclear Power Station;
Extension of Public Comment Period
AGENCY:
Week of October 6, 2014
License amendment application;
opportunity to comment, request a
hearing, and petition for leave to
intervene; extension of public comment
period.
Tuesday, October 7, 2014
9:00 a.m. Briefing on the Status of NearTerm Task Force Recommendation
2 for Seismic Hazard Reevaluations
(Public Meeting) (Contact: Nicholas
DiFrancesco, 301–415–1115)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Nuclear Regulatory
Commission.
ACTION:
This document modifies a
notice appearing in the Federal Register
on September 22, 2014 (79 FR 56608),
by extending the original public
comment period from October 22, 2014,
to October 26, 2014. This action was
requested by concerned stakeholders
who sought additional time to provide
comments.
SUMMARY:
FOR FURTHER INFORMATION CONTACT:
Week of October 13, 2014—Tentative
There are no meetings scheduled for
the week of October 13, 2014.
Week of October 20, 2014—Tentative
There are no meetings scheduled for
the week of October 20, 2014.
Week of October 27, 2014—Tentative
Wednesday, October 29, 2014
SUPPLEMENTARY INFORMATION:
On page
56608, in the third column, in the
paragraph entitled, DATES, the closing of
the public comment period was October
22, 2014. This date has been extended
to October 26, 2014.
asabaliauskas on DSK5VPTVN1PROD with NOTICES
Nadiyah S. Morgan, Project Manager,
Office of Nuclear Reactor Regulation,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone
(301) 415–1016, email:
Nadiyah.Morgan@nrc.gov.
9:00 a.m. Briefing on Watts Bar Unit 2
License Application Review (Public
Meeting) (Contact: Justin Poole,
301–415–2048)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Dated in Rockville, Maryland, this 30th
day of September 2014.
For the Nuclear Regulatory Commission.
Benjamin G. Beasley,
Chief, Plant Licensing Branch I–1, Division
of Operating Reactor Licensing, Office of
Nuclear Reactor Regulation.
Week of November 3, 2014—Tentative
[FR Doc. 2014–23934 Filed 10–6–14; 8:45 am]
BILLING CODE 7590–01–P
VerDate Sep<11>2014
17:15 Oct 06, 2014
Jkt 235001
9:00 a.m. Briefing on Security Issues
(Closed—Ex. 1)
1:30 p.m. Briefing on Security Issues
(Closed—Ex. 1)
Thursday, October 30, 2014
There are no meetings scheduled for
the week of November 3, 2014.
Week of November 10, 2014—Tentative
Thursday, November 13, 2014
9:00 a.m. Strategic Programmatic
Overview of the Nuclear Material
Users and the Fuel Facilities
Business Lines (Public Meeting)
(Contact: Cinthya Roman, 301–287–
9091)
PO 00000
Frm 00078
Fmt 4703
Sfmt 9990
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
*
*
*
*
*
The schedule for Commission
meetings is subject to change on short
notice. For more information or to verify
the status of meetings, contact Rochelle
Bavol at (301) 415–1651 or via email at
Rochelle.Bavol@nrc.gov.
*
*
*
*
*
Additional Information
The Discussion of Management and
Personnel Issues (Closed—Ex. 2 and 6)
previously scheduled for October 15 at
11:00 a.m. will be rescheduled.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
braille, large print), please notify
Kimberly Meyer, NRC Disability
Program Manager, at 301–287–0727, by
videophone at 240–428–3217, or by
email at Kimberly.Meyer-Chambers@
nrc.gov. Determinations on requests for
reasonable accommodation will be
made on a case-by-case basis.
*
*
*
*
*
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Office of
the Secretary, Washington, DC 20555
(301–415–1969), or send an email to
Patricia.Jimenez@nrc.gov or
Brenda.Akstulewicz@nrc.gov.
Dated: October 2, 2014.
Richard J. Laufer,
Technical Coordinator, Office of the
Secretary.
[FR Doc. 2014–23991 Filed 10–3–14; 11:15 am]
BILLING CODE 7590–01–P
E:\FR\FM\07OCN1.SGM
07OCN1
Agencies
[Federal Register Volume 79, Number 194 (Tuesday, October 7, 2014)]
[Notices]
[Pages 60515-60521]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-23428]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2014-0205]
Applications and Amendments to Facility Operating Licenses and
Combined Licenses Involving Proposed No Significant Hazards
Considerations and Containing Sensitive Unclassified Non-Safeguards
Information and Order Imposing Procedures for Access to Sensitive
Unclassified Non-Safeguards Information
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment request; opportunity to comment, request a
hearing, and petition for leave to intervene; order.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) received and is
considering approval of three amendment requests. The amendment
requests are for Columbia Generating Station; Waterford Steam Electric
Station, Unit 3; and Seabrook Station, Unit 1. For each amendment
request, the NRC proposes to determine that they involve no significant
hazards consideration. In addition, each amendment request contains
sensitive unclassified non-safeguards information (SUNSI).
DATES: Comments must be filed by November 6, 2014. A request for a
hearing must be filed by December 8, 2014. Any potential party as
defined in Sec. 2.4 of Title 10 of the Code of Federal Regulations (10
CFR), who believes access to SUNSI is necessary to respond to this
notice must request document access by October 17, 2014.
ADDRESSES: You may submit comments by any of the following methods
(unless this document describes a different method for submitting
comments on a specific subject):
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2014-0205. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
Mail comments to: Cindy Bladey, Office of Administration,
Mail Stop: 3WFN-06-A44M, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Sandra Figueroa, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC
20555-0001; telephone: 301-415-1262, email: Sandra.Figueroa@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2014-0205 when contacting the NRC
about the availability of information for this action. You may obtain
publicly-available information related to this action by any of the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2014-0205.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in the
SUPPLEMENTARY INFORMATION section.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2014-0205 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC posts all comment submissions at https://www.regulations.gov as well as entering the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Background
Pursuant to Section 189a.(2) of the Atomic Energy Act of 1954, as
amended (the Act), the NRC is publishing this notice. The Act requires
the Commission to publish notice of any amendments issued, or proposed
to be issued and grants the Commission the authority to issue and make
immediately effective any amendment to an operating license or combined
license, as applicable, upon a determination by the Commission that
such amendment involves no significant hazards consideration,
notwithstanding the pendency before the Commission of a request for a
hearing from any person.
This notice includes notices of amendments containing SUNSI.
[[Page 60516]]
III. Notice of Consideration of Issuance of Amendments to Facility
Operating Licenses and Combined Licenses, Proposed No Significant
Hazards Consideration Determination, and Opportunity for a Hearing
The Commission has made a proposed determination that the following
amendment requests involve no significant hazards consideration. Under
the Commission's regulations in 10 CFR 50.92, this means that operation
of the facility in accordance with the proposed amendment would not (1)
involve a significant increase in the probability or consequences of an
accident previously evaluated, or (2) create the possibility of a new
or different kind of accident from any accident previously evaluated,
or (3) involve a significant reduction in a margin of safety. The basis
for this proposed determination for each amendment request is shown
below.
The Commission is seeking public comments on this proposed
determination. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of 60 days after the date of publication of this notice. The
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment
involves no significant hazards consideration. In addition, the
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day
comment period such that failure to act in a timely way would result,
for example in derating or shutdown of the facility. Should the
Commission take action prior to the expiration of either the comment
period or the notice period, it will publish in the Federal Register a
notice of issuance. Should the Commission make a final No Significant
Hazards Consideration Determination, any hearing will take place after
issuance. The Commission expects that the need to take this action will
occur very infrequently.
A. Opportunity To Request a Hearing and Petition for Leave To Intervene
Within 60 days after the date of publication of this notice, any
person(s) whose interest may be affected by this action may file a
request for a hearing and a petition to intervene with respect to
issuance of the amendment to the subject facility operating license or
combined license. Requests for a hearing and a petition for leave to
intervene shall be filed in accordance with the Commission's ``Agency
Rules of Practice and Procedure'' in 10 CFR Part 2. Interested
person(s) should consult a current copy of 10 CFR 2.309, which is
available at the NRC's PDR, located at One White Flint North, Room O1-
F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. The
NRC's regulations are accessible electronically from the NRC Library on
the NRC's Web site at https://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is
filed within 60 days, the Commission or a presiding officer designated
by the Commission or by the Chief Administrative Judge of the Atomic
Safety and Licensing Board Panel, will rule on the request and/or
petition; and the Secretary or the Chief Administrative Judge of the
Atomic Safety and Licensing Board will issue a notice of a hearing or
an appropriate order.
As required by 10 CFR 2.309, a petition for leave to intervene
shall set forth with particularity the interest of the petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following general requirements: (1) The name, address, and telephone
number of the requestor or petitioner; (2) the nature of the
requestor's/petitioner's right under the Act to be made a party to the
proceeding; (3) the nature and extent of the requestor's/petitioner's
property, financial, or other interest in the proceeding; and (4) the
possible effect of any decision or order which may be entered in the
proceeding on the requestor's/petitioner's interest. The petition must
also set forth the specific contentions which the requestor/petitioner
seeks to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
requestor/petitioner shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the requestor/
petitioner intends to rely in proving the contention at the hearing.
The requestor/petitioner must also provide references to those specific
sources and documents of which the petitioner is aware and on which the
requestor/petitioner intends to rely to establish those facts or expert
opinion. The petition must include sufficient information to show that
a genuine dispute exists with the applicant on a material issue of law
or fact. Contentions shall be limited to matters within the scope of
the amendment under consideration. The contention must be one which, if
proven, would entitle the requestor/petitioner to relief. A requestor/
petitioner who fails to satisfy these requirements with respect to at
least one contention will not be permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing.
If a hearing is requested, and the Commission has not made a final
determination on the issue of no significant hazards consideration, the
Commission will make a final determination on the issue of no
significant hazards consideration. The final determination will serve
to decide when the hearing is held. If the final determination is that
the amendment request involves no significant hazards consideration,
the Commission may issue the amendment and make it immediately
effective, notwithstanding the request for a hearing. Any hearing held
would take place after issuance of the amendment. If the final
determination is that the amendment request involves a significant
hazards consideration, then any hearing held would take place before
the issuance of any amendment unless the Commission finds an imminent
danger to the health or safety of the public, in which case it will
issue an appropriate order or rule under 10 CFR part 2.
B. Electronic Submissions (E-Filing)
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene, and documents filed by
interested governmental entities participating under 10 CFR 2.315(c),
must be filed in accordance with the NRC's E-Filing rule (72 FR 49139;
August 28, 2007). The E-Filing process requires participants to submit
and serve all adjudicatory documents over the internet, or in some
cases to mail copies on electronic storage media. Participants may not
submit paper copies of their filings unless they seek an exemption in
[[Page 60517]]
accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at hearing.docket@nrc.gov, or by
telephone at 301-415-1677, to request (1) a digital identification (ID)
certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the E-Submittal
server for any proceeding in which it is participating; and (2) advise
the Secretary that the participant will be submitting a request or
petition for hearing (even in instances in which the participant, or
its counsel or representative, already holds an NRC-issued digital ID
certificate). Based upon this information, the Secretary will establish
an electronic docket for the hearing in this proceeding if the
Secretary has not already established an electronic docket.
Information about applying for a digital ID certificate is
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/getting-started.html. System requirements for accessing
the E-Submittal server are detailed in the NRC's ``Guidance for
Electronic Submission,'' which is available on the agency's public Web
site at https://www.nrc.gov/site-help/e-submittals.html. Participants
may attempt to use other software not listed on the Web site, but
should note that the NRC's E-Filing system does not support unlisted
software, and the NRC Meta System Help Desk will not be able to offer
assistance in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through the Electronic Information Exchange System,
users will be required to install a Web browser plug-in from the NRC's
Web site. Further information on the Web-based submission form,
including the installation of the Web browser plug-in, is available on
the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an email notice confirming receipt of the document. The
E-Filing system also distributes an email notice that provides access
to the document to the NRC's Office of the General Counsel and any
others who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC's public
Web site at https://www.nrc.gov/site-help/e-submittals.html, by email to
MSHD.Resource@nrc.gov, or by a toll-free call at 1-866-672-7640. The
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m.,
Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville,
Maryland, 20852, Attention: Rulemaking and Adjudications Staff.
Participants filing a document in this manner are responsible for
serving the document on all other participants. Filing is considered
complete by first-class mail as of the time of deposit in the mail, or
by courier, express mail, or expedited delivery service upon depositing
the document with the provider of the service. A presiding officer,
having granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in the
NRC's electronic hearing docket which is available to the public at
https://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as social security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information.
However, a request to intervene will require including information on
local residence in order to demonstrate a proximity assertion of
interest in the proceeding. With respect to copyrighted works, except
for limited excerpts that serve the purpose of the adjudicatory filings
and would constitute a Fair Use application, participants are requested
not to include copyrighted materials in their submission.
Petitions for leave to intervene must be filed no later than 60
days from the date of publication of this notice. Requests for hearing,
petitions for leave to intervene, and motions for leave to file new or
amended contentions that are filed after the 60-day deadline will not
be entertained absent a determination by the presiding officer that the
filing demonstrates good cause by satisfying the three factors in 10
CFR 2.309(c)(1)(i)-(iii).
For further details with respect to this amendment action, see the
application for amendment which is available for public inspection at
the NRC's PDR, located at One White Flint North, Room O1-F21, 11555
Rockville Pike (first floor), Rockville, Maryland 20852. Publicly
available documents created or received at the NRC are accessible
electronically through ADAMS in the NRC Library at https://www.nrc.gov/reading-rm/adams.html. If you do not have access to ADAMS or if there
are problems in accessing the documents located in ADAMS, contact the
PDR's Reference staff at 1-800-397-4209, 301-415-4737, or by email to
pdr.resource@nrc.gov.
[[Page 60518]]
Energy Northwest, Docket No. 50-397, Columbia Generating Station,
(Columbia) Benton County, Washington
Date of amendment request: June 25, 2014. A publicly-available
version is in ADAMS under Accession No. ML14188C091.
Description of amendment request: This amendment request contains
sensitive unclassified non-safeguards information (SUNSI). The
amendment would revise the Columbia Generating Station Cyber Security
Plan (CSP) Milestone 8 full implementation date as set forth in the CSP
Implementation Schedule.
Basis for proposed no significant hazards consideration
determination: As required by 10 CFR 50.91(a), the licensee has
provided its analysis of the issue of no significant hazards
consideration, which is presented below:
1. Do the proposed changes involve a significant increase in the
probability or consequences of an accident previously evaluated?
Response: No.
The proposed change to the Columbia CSP Implementation Schedule
is administrative in nature. This change does not alter any accident
analysis assumptions, add any initiators, or affect the function of
plant systems or the manner in which systems are operated,
maintained, modified, tested, or inspected. Although implementation
of the CSP may require modifications involving digital assets, the
proposed change does [not] affect the nature, function, or
configuration of those modifications, only the timing of their
required completion. Similarly, the manner in which other activities
involve in CSP implementation, such as performance of assessments,
update of existing procedures, preparation of new procedures, and
changes to, or development of, programs, will not be affected; only
their required completion date. Measures have or will be taken in
the interim to provide adequate protection of critical digital
assets.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Do the proposed changes create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
The proposed change to the Columbia CSP Implementation Schedule
is administrative in nature. The proposed change does not add any
accident initiators. Although implementation of the CSP may alter
plant systems or components or the manner in which systems and
components are operated, maintained, modified, tested, or inspected,
the proposed change only affects the completion date for such
alterations.
Therefore, the proposed change does not create the possibility
of a new or different kind of accident from any accident previously
evaluated.
3. Do the proposed changes involve a significant reduction in a
margin of safety?
Response: No.
Plant safety margins are established through limiting conditions
for operation, limiting safety system settings, and safety limits
specified in the Technical Specifications which are part of the
plant license. The proposed change to the Columbia CSP
Implementation Schedule is administrative in nature in that it only
affects the required completion date for certain activities, and
does not affect the nature of those activities nor does it affect
any safety margins.
Therefore, the proposed change does not involve a reduction in a
margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
Attorney for licensee: William A. Horin, Esq., Winston & Strawn,
1700 K Street NW., Washington, DC 20006-3817.
Acting NRC Branch Chief: Eric R. Oesterle.
Entergy Operations, Inc., Docket No. 50-382, Waterford Steam Electric
Station, (Waterford 3), Unit 3, St. Charles Parish, Louisiana
Date of amendment request: August 4, 2014. A publicly-available
version is in ADAMS under Accession Nos. ML14217A498, ML14217A496, and
ML14217A497.
Description of amendment request: This amendment request contains
sensitive unclassified non-safeguards information (SUNSI). The
amendment would change the Waterford 3, Cyber Security Plan (CSP)
Implementation Schedule Milestone 8 full implementation date and revise
the existing operating license physical protection license condition.
Basis for proposed no significant hazards consideration
determination: As required by 10 CFR 50.91(a), the licensee has
provided its analysis of the issue of no significant hazards
consideration, which is presented below:
1. Does the proposed change involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The proposed change to the CSP Implementation Schedule is
administrative in nature. This change does not alter accident
analysis assumptions, add any initiators, or affect the function of
plant systems or the manner in which systems are operated,
maintained, modified, tested, or inspected. The proposed change does
not require any plant modifications which affect the performance
capability of the structures, systems, and components relied upon to
mitigate the consequences of postulated accidents and has no impact
on the probability or consequences of an accident previously
evaluated.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
The proposed change to the CSP Implementation Schedule is
administrative in nature. This proposed change does not alter
accident analysis assumptions, add any initiators, or affect the
function of plant systems or the manner in which systems are
operated, maintained, modified, tested, or inspected. The proposed
change does not require any plant modifications which affect the
performance capability of the structures, systems, and components
relied upon to mitigate the consequences of postulated accidents and
does not create the possibility of a new or different kind of
accident from any accident previously evaluated.
Therefore, the proposed change does not create the possibility
of a new or different kind of accident from any accident previously
evaluated.
3. Does the proposed change involve a significant reduction in a
margin of safety?
Response: No.
Plant safety margins are established through limiting conditions
for operation, limiting safety system settings, and safety limits
specified in the technical specifications. The proposed change to
the CSP Implementation Schedule is administrative in nature. In
addition, the milestone date delay for full implementation of the
CSP has no substantive impact because other measures have been taken
which provide adequate protection during this period of time.
Because there is no change to established safety margins as a result
of this change, the proposed change does not involve a significant
reduction in a margin of safety.
Therefore, the proposed change does not involve a significant
reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
Attorney for licensee: Joseph A. Aluise, Associate General
Counsel--Nuclear, Entergy Services, Inc., 639 Loyola Avenue, New
Orleans, LA 70113.
NRC Branch Chief: Douglas A. Broaddus.
[[Page 60519]]
NextEra Energy Seabrook LLC, Docket No. 50-443, Seabrook Station, Unit
1, Rockingham County, New Hampshire
Date of amendment request: July 10, 2014, as supplemented by letter
dated July 22, 2014. Publicly-available versions are in ADAMS under
Accession Nos. ML14198A085 and ML14205A421, respectively.
Description of amendment request: This amendment request contains
sensitive unclassified non-safeguards information (SUNSI). The proposed
amendment would revise the Seabrook Station, Unit 1, Cyber Security
Plan (CSP) Milestone 8 full implementation date, as set forth in the
Cyber Security Plan Implementation Schedule.
Basis for proposed no significant hazards consideration
determination: As required by 10 CFR 50.91(a), the licensee has
provided its analysis of the issue of no significant hazards
consideration, which is presented below:
1. Does the proposed change involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The proposed change to the Cyber Security Plan implementation
schedule is administrative in nature. The change does not alter
accident analysis assumptions, add any initiators, or affect the
function of plant systems or the manner in which systems are
operated, maintained, tested, or inspected. The proposed change does
not require any plant modifications which affect the performance
capability or the structures, systems, and components relied upon to
mitigate the consequences of postulated accidents and has no impact
on the probability or consequences of an accident previously
evaluated.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
The proposed change to the Cyber Security Plan implementation
schedule is administrative in nature. This proposed change does not
alter accident analysis assumptions, add any initiators, or affect
the function of plant systems or the manner in which systems are
operated, maintained, tested, or inspected. The proposed change does
not require any plant modifications which affect the performance
capability or the structures, systems, and components relied upon to
mitigate the consequences of postulated accidents and does not
create the possibility of a new or different kind of accident from
any accident previously evaluated.
Therefore, the proposed change does not create the possibility
of a new or different kind of accident from any accident previously
evaluated.
3. Does the proposed change involve a significant reduction in a
margin of safety?
Response: No.
Plant safety margins are established through limiting conditions
of operation, limiting safety systems settings, and safety limits
specified in the technical specifications. The proposed change to
the Cyber Security Plan implementation schedule is administrative in
nature. Because there is no change in these established safety
margins as result of this change, the proposed change does not
involve a significant reduction in a margin of safety.
Therefore, the proposed change does not involve a significant
reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
Attorney for licensee: M.S. Ross, Florida Power & Light Company,
P.O. Box 14000, Juno Beach, Florida 33408-0420.
Acting NRC Branch Chief: Robert Schaaf.
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation
Energy Northwest, Docket No. 50-397, Columbia Generating Station,
Benton County, Washington
Entergy Operations, Inc., Docket No. 50-382, Waterford Steam Electric
Station, Unit 3, Charles Parish, Louisiana
NextEra Energy Seabrook LLC, Docket No. 50-443, Seabrook Station, Unit
1, Rockingham County, New Hampshire
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation
A. This Order contains instructions regarding how potential parties
to this proceeding may request access to documents containing SUNSI.
B. Within 10 days after publication of this notice of hearing and
opportunity to petition for leave to intervene, any potential party who
believes access to SUNSI is necessary to respond to this notice may
request such access. A ``potential party'' is any person who intends to
participate as a party by demonstrating standing and filing an
admissible contention under 10 CFR 2.309. Requests for access to SUNSI
submitted later than 10 days after publication of this notice will not
be considered absent a showing of good cause for the late filing,
addressing why the request could not have been filed earlier.
C. The requester shall submit a letter requesting permission to
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, Attention: Rulemakings and
Adjudications Staff, and provide a copy to the Associate General
Counsel for Hearings, Enforcement and Administration, Office of the
General Counsel, Washington, DC 20555-0001. The expedited delivery or
courier mail address for both offices is: U.S. Nuclear Regulatory
Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The email
address for the Office of the Secretary and the Office of the General
Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov,
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------
\1\ While a request for hearing or petition to intervene in this
proceeding must comply with the filing requirements of the NRC's
``E-Filing Rule,'' the initial request to access SUNSI under these
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------
(1) A description of the licensing action with a citation to this
Federal Register notice;
(2) The name and address of the potential party and a description
of the potential party's particularized interest that could be harmed
by the action identified in C.(1); and
(3) The identity of the individual or entity requesting access to
SUNSI and the requester's basis for the need for the information in
order to meaningfully participate in this adjudicatory proceeding. In
particular, the request must explain why publicly-available versions of
the information requested would not be sufficient to provide the basis
and specificity for a proffered contention.
D. Based on an evaluation of the information submitted under
paragraph C.(3) the NRC staff will determine within 10 days of receipt
of the request whether:
(1) There is a reasonable basis to believe the petitioner is likely
to establish standing to participate in this NRC proceeding; and
(2) The requestor has established a legitimate need for access to
SUNSI.
E. If the NRC staff determines that the requestor satisfies both
D.(1) and D.(2) above, the NRC staff will notify the requestor in
writing that access to SUNSI has been granted. The written notification
will contain instructions on how the requestor may obtain copies of the
requested documents, and any other
[[Page 60520]]
conditions that may apply to access to those documents. These
conditions may include, but are not limited to, the signing of a Non-
Disclosure Agreement or Affidavit, or Protective Order \2\ setting
forth terms and conditions to prevent the unauthorized or inadvertent
disclosure of SUNSI by each individual who will be granted access to
SUNSI.
---------------------------------------------------------------------------
\2\ Any motion for Protective Order or draft Non-Disclosure
Affidavit or Agreement for SUNSI must be filed with the presiding
officer or the Chief Administrative Judge if the presiding officer
has not yet been designated, within 30 days of the deadline for the
receipt of the written access request.
---------------------------------------------------------------------------
F. Filing of Contentions. Any contentions in these proceedings that
are based upon the information received as a result of the request made
for SUNSI must be filed by the requestor no later than 25 days after
the requestor is granted access to that information. However, if more
than 25 days remain between the date the petitioner is granted access
to the information and the deadline for filing all other contentions
(as established in the notice of hearing or opportunity for hearing),
the petitioner may file its SUNSI contentions by that later deadline.
This provision does not extend the time for filing a request for a
hearing and petition to intervene, which must comply with the
requirements of 10 CFR 2.309.
G. Review of Denials of Access.
(1) If the request for access to SUNSI is denied by the NRC staff
after a determination on standing and need for access, the NRC staff
shall immediately notify the requestor in writing, briefly stating the
reason or reasons for the denial.
(2) The requester may challenge the NRC staff's adverse
determination by filing a challenge within five days of receipt of that
determination with: (a) The presiding officer designated in this
proceeding; (b) if no presiding officer has been appointed, the Chief
Administrative Judge, or if he or she is unavailable, another
administrative judge, or an administrative law judge with jurisdiction
pursuant to 10 CFR 2.318(a); or (c) officer if that officer has been
designated to rule on information access issues.
H. Review of Grants of Access. A party other than the requester may
challenge an NRC staff determination granting access to SUNSI whose
release would harm that party's interest independent of the proceeding.
Such a challenge must be filed with the Chief Administrative Judge
within five days of the notification by the NRC staff of its grant of
access.
If challenges to the NRC staff determinations are filed, these
procedures give way to the normal process for litigating disputes
concerning access to information. The availability of interlocutory
review by the Commission of orders ruling on such NRC staff
determinations (whether granting or denying access) is governed by 10
CFR 2.311.\3\
---------------------------------------------------------------------------
\3\ Requesters should note that the filing requirements of the
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals
of NRC staff determinations (because they must be served on a
presiding officer or the Commission, as applicable), but not to the
initial SUNSI request submitted to the NRC staff under these
procedures.
---------------------------------------------------------------------------
I. The Commission expects that the NRC staff and presiding officers
(and any other reviewing officers) will consider and resolve requests
for access to SUNSI, and motions for protective orders, in a timely
fashion in order to minimize any unnecessary delays in identifying
those petitioners who have standing and who have propounded contentions
meeting the specificity and basis requirements in 10 CFR part 2.
Attachment 1 to this Order summarizes the general target schedule for
processing and resolving requests under these procedures.
IT IS SO ORDERED.
Dated at Rockville, Maryland, this 25th day of September, 2014.
Annette L. Vietti-Cook,
Secretary, Nuclear Regulatory Commission.
Attachment 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards Information
in This Proceeding
------------------------------------------------------------------------
Day Event/Activity
------------------------------------------------------------------------
0..................... Publication of Federal Register notice of
hearing and opportunity to petition for leave
to intervene, including order with instructions
for access requests.
10.................... Deadline for submitting requests for access to
Sensitive Unclassified Non-Safeguards
Information (SUNSI) with information:
supporting the standing of a potential party
identified by name and address; describing the
need for the information in order for the
potential party to participate meaningfully in
an adjudicatory proceeding.
60.................... Deadline for submitting petition for
intervention containing: (i) demonstration of
standing; and (ii) all contentions whose
formulation does not require access to SUNSI
(+25 Answers to petition for intervention; +7
petitioner/requestor reply).
20.................... U.S. Nuclear Regulatory Commission (NRC) staff
informs the requester of the staff's
determination whether the request for access
provides a reasonable basis to believe standing
can be established and shows need for SUNSI.
(NRC staff also informs any party to the
proceeding whose interest independent of the
proceeding would be harmed by the release of
the information.) If NRC staff makes the
finding of need for SUNSI and likelihood of
standing, NRC staff begins document processing
(preparation of redactions or review of
redacted documents).
25.................... If NRC staff finds no ``need'' or no likelihood
of standing, the deadline for petitioner/
requester to file a motion seeking a ruling to
reverse the NRC staff's denial of access; NRC
staff files copy of access determination with
the presiding officer (or Chief Administrative
Judge or other designated officer, as
appropriate). If NRC staff finds ``need'' for
SUNSI, the deadline for any party to the
proceeding whose interest independent of the
proceeding would be harmed by the release of
the information to file a motion seeking a
ruling to reverse the NRC staff's grant of
access.
30.................... Deadline for NRC staff reply to motions to
reverse NRC staff determination(s).
40.................... (Receipt +30) If NRC staff finds standing and
need for SUNSI, deadline for NRC staff to
complete information processing and file motion
for Protective Order and draft Non-Disclosure
Affidavit. Deadline for applicant/licensee to
file Non-Disclosure Agreement for SUNSI.
A..................... If access granted: issuance of presiding officer
or other designated officer decision on motion
for protective order for access to sensitive
information (including schedule for providing
access and submission of contentions) or
decision reversing a final adverse
determination by the NRC staff.
A + 3................. Deadline for filing executed Non-Disclosure
Affidavits. Access provided to SUNSI consistent
with decision issuing the protective order.
A + 28................ Deadline for submission of contentions whose
development depends upon access to SUNSI.
However, if more than 25 days remain between
the petitioner's receipt of (or access to) the
information and the deadline for filing all
other contentions (as established in the notice
of hearing or opportunity for hearing), the
petitioner may file its SUNSI contentions by
that later deadline.
A + 53................ (Contention receipt +25) Answers to contentions
whose development depends upon access to SUNSI.
[[Page 60521]]
A + 60................ (Answer receipt +7) Petitioner/Intervenor reply
to answers.
>A + 60............... Decision on contention admission.
------------------------------------------------------------------------
[FR Doc. 2014-23428 Filed 10-6-14; 8:45 am]