Mr. Ray F. Ward; Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 55786-55787 [2014-22096]

Download as PDF mstockstill on DSK4VPTVN1PROD with NOTICES 55786 Federal Register / Vol. 79, No. 180 / Wednesday, September 17, 2014 / Notices Accession Number: 20140908–5201. Comments Due: 5 p.m. ET 9/29/14. Docket Numbers: ER14–2807–000. Applicants: Southern California Edison Company. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Distribution Service Agreement with US Topco Energy, Inc. to be effective 11/9/2014. Filed Date: 9/9/14. Accession Number: 20140909–5001. Comments Due: 5 p.m. ET 9/30/14. Docket Numbers: ER14–2809–000. Applicants: CPV Maryland, LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Revised Market-Based Rate Tariff Filing to be effective 11/9/2014. Filed Date: 9/9/14. Accession Number: 20140909–5116. Comments Due: 5 p.m. ET 9/30/14. Docket Numbers: ER14–2810–000. Applicants: CPV Sentinel, LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Revised Market-Based Rate Tariff Filing to be effective 11/9/2014. Filed Date: 9/9/14. Accession Number: 20140909–5117. Comments Due: 5 p.m. ET 9/30/14. Docket Numbers: ER14–2811–000. Applicants: CPV Keenan II Renewable Energy Company. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Revised Market-Based Rate Tariff Filing to be effective 11/9/2014. Filed Date: 9/9/14. Accession Number: 20140909–5118. Comments Due: 5 p.m. ET 9/30/14. Docket Numbers: ER14–2812–000. Applicants: CPV Shore, LLC. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Revised Market-Based Rate Tariff Filing to be effective 11/9/2014. Filed Date: 9/9/14. Accession Number: 20140909–5119. Comments Due: 5 p.m. ET 9/30/14. Docket Numbers: ER14–2813–000. Applicants: PacifiCorp. Description: Tariff Withdrawal per 35.15: Termination of Klamath Energy Construction Agreement to be effective 11/12/2014. Filed Date: 9/9/14. Accession Number: 20140909–5125. Comments Due: 5 p.m. ET 9/30/14. Docket Numbers: ER14–2814–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) rate filing per 35.13(a)(2)(iii): Original Service Agreement No. 3940; Queue No. Y3–054 to be effective 8/11/2014. Filed Date: 9/9/14. Accession Number: 20140909–5178. VerDate Sep<11>2014 18:24 Sep 16, 2014 Jkt 232001 Comments Due: 5 p.m. ET 9/30/14. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: September 9, 2014. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2014–22178 Filed 9–16–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 9842–006] Mr. Ray F. Ward; Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Minor New License. b. Project No.: 9842–006. c. Date filed: August 28, 2014. d. Applicant: Mr. Ray F. Ward. e. Name of Project: Ward Mill Hydroelectric Project. f. Location: On the Watauga River, in the Township of Laurel Creek, Watauga County, North Carolina. The project does not occupy lands of the United States. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Andrew C. Givens, Cardinal Energy Service, Inc., 620 N. West St., Suite 103, Raleigh, North Carolina 27603, (919) 834–0909. i. FERC Contact: Adam Peer at (202) 502–8449, adam.peer@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: October 27, 2014 The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–9842–006. m. The application is not ready for environmental analysis at this time. n. The Ward Mill Project consists of: (1) An existing 130-foot-long by 20-foothigh dam; (2) An existing 4.6 acre reservoir with an estimated gross storage capacity of 16.3 acre-feet; (3) a 14-footlong, 5-foot-wide, and 7.5-foot-tall penstock made of rock, concrete and reinforced steel; (4) a powerhouse containing two generating units for a total installed capacity of 168 kilowatts; (5) existing transmission facilities; and (6) appurtenant facilities. The project is estimated to generate from below 290,000 to over 599,000 kilowatt-hours annually. The dam and existing facilities are owned by the applicant. No new project facilities are proposed. o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the E:\FR\FM\17SEN1.SGM 17SEN1 Federal Register / Vol. 79, No. 180 / Wednesday, September 17, 2014 / Notices ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. Issue Acceptance or Deficiency Letter October 2014 Request Additional Information October 2014 Issue Notice of Acceptance January 2015 Issue Scoping Document 1 for comments February 2015 Comments on Scoping Document 1 April 2015 Issue Scoping Document 2 May 2015 Issue notice of ready for environmental analysis May 2015 Commission issues EA January 2016 Comments on EA February 2016 Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: September 10, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–22096 Filed 9–16–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [ Project No. 2503–154] mstockstill on DSK4VPTVN1PROD with NOTICES Duke Energy Carolinas, LLC; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: 2503–154. c. Date Filed: August 27, 2014. d. Applicant: Duke Energy Carolinas, LLC. e. Name of Project: Keowee-Toxaway Hydroelectric Project. f. Location: The existing KeoweeToxaway Project is located on the Toxaway, Keowee, and Little Rivers in Oconee County and Pickens County, South Carolina and Transylvania County, North Carolina. The KeoweeToxaway Project occupies no federal lands. g. Filed Pursuant to: Federal Power Act, 16 U.S. C. 791 (a)–825(r). h. Applicant Contact: Jennifer Huff, Duke Energy Carolinas, LLC, 526 S. Church Street, Charlotte, NC 28202; Telephone (980) 373–4392. i. FERC Contact: Stephen Bowler, (202) 502–6861 or stephen.bowler@ ferc.gov j. This application is not ready for environmental analysis at this time. k. The Project Description: The Keowee-Toxaway Project consists of two developments: The upstream, 710.1–MW Jocassee Development and the downstream, 157.5-megawatt (MW) Keowee Development owned by Duke Energy Carolinas, LLC. The Jocassee Development includes: A 385-foot-high, 1,800-foot-long main earthfill dam with top elevation at 1,125 feet above mean sea level (msl); two circular intake structures passing water to two water conveyance tunnels leading to four turbines; two saddle dikes (825 feet and 500 feet in length); a partially-open powerhouse just downstream of the dam containing four reversible pump-turbine units authorized for an installed capacity of 177.5 MW each; a 50-footwide, concrete, ogee-type spillway with two Taintor gates; a 230-kilovolt (kV) transmission system; and appurtenant facilities. The maximum hydraulic capacity is 36,200 cfs. The Jocassee Development is operated as a pumped-storage project, with the pump-turbines used for generating power during peak demand periods (typically during the day), and for pumping water back through the tunnels to Lake Jocassee (typically during the night). The pumps have a capacity of 32,720 cfs. The Jocassee Development is also the lower lake for the 1,065 MW Bad Creek Hydroelectric Project No. 2740, which is also owned by Duke, but is not part of this relicensing. The Keowee Development includes: a 165-foot-high, 3,500-foot-long earthfill dam impounding the Keowee River, and a 165-foot-high, 1,800-foot-long earthfill dam impounding the Little River; four saddle dikes (1,900 feet, 225 feet, 350 feet, and 650 feet in length); an intake dike at the Oconee Nuclear Station; a 176-foot wide, concrete, ogee-type spillway with four Taintor gates; a concrete intake structure leading to two penstocks; a concrete powerhouse at the base of Keowee dam containing two Francis-type, mixed flow turbinegenerator units authorized for an installed capacity of 78.8 MW each; a 150-foot by 500-foot concrete tailrace; a 230-kV transmission system; and appurtenant facilities. The maximum hydraulic capacity is 24,920 cfs. Duke and several stakeholders signed a relicensing agreement (settlement), which resolves all issues to relicensing the project among the signatories. l. Locations of the Application: A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). A copy is also available for inspection and reproduction at the address in item (h) above. m. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Procedural Schedule: The application will be processed according to the following preliminary Hydro Licensing Schedule. Revisions to the schedule may be made as appropriate. Milestone Target date Notice of Acceptance/Notice of Ready for .............................................................................................................................. Environmental Analysis ........................................................................................................................................................... Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ..................................................... Commission issues Draft EA ................................................................................................................................................... Comments on Draft Environmental Assessment (EA) ............................................................................................................ VerDate Sep<11>2014 18:24 Sep 16, 2014 Jkt 232001 PO 00000 Frm 00044 Fmt 4703 55787 Sfmt 4703 E:\FR\FM\17SEN1.SGM 17SEN1 October 26, 2014. December 25, 2014. June 23, 2015. July 23, 2015.

Agencies

[Federal Register Volume 79, Number 180 (Wednesday, September 17, 2014)]
[Notices]
[Pages 55786-55787]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-22096]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 9842-006]


Mr. Ray F. Ward; Application Tendered for Filing With the 
Commission and Soliciting Additional Study Requests and Establishing 
Procedural Schedule for Relicensing and a Deadline for Submission of 
Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Minor New License.
    b. Project No.: 9842-006.
    c. Date filed: August 28, 2014.
    d. Applicant: Mr. Ray F. Ward.
    e. Name of Project: Ward Mill Hydroelectric Project.
    f. Location: On the Watauga River, in the Township of Laurel Creek, 
Watauga County, North Carolina. The project does not occupy lands of 
the United States.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Andrew C. Givens, Cardinal Energy Service, 
Inc., 620 N. West St., Suite 103, Raleigh, North Carolina 27603, (919) 
834-0909.
    i. FERC Contact: Adam Peer at (202) 502-8449, adam.peer@ferc.gov.
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: October 27, 2014
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket number P-9842-006.
    m. The application is not ready for environmental analysis at this 
time.
    n. The Ward Mill Project consists of: (1) An existing 130-foot-long 
by 20-foot-high dam; (2) An existing 4.6 acre reservoir with an 
estimated gross storage capacity of 16.3 acre-feet; (3) a 14-foot-long, 
5-foot-wide, and 7.5-foot-tall penstock made of rock, concrete and 
reinforced steel; (4) a powerhouse containing two generating units for 
a total installed capacity of 168 kilowatts; (5) existing transmission 
facilities; and (6) appurtenant facilities. The project is estimated to 
generate from below 290,000 to over 599,000 kilowatt-hours annually. 
The dam and existing facilities are owned by the applicant. No new 
project facilities are proposed.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the

[[Page 55787]]

``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC Online Support. A copy is also available for 
inspection and reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary Hydro Licensing 
Schedule. Revisions to the schedule will be made as appropriate.

    Issue Acceptance or Deficiency Letter October 2014
    Request Additional Information October 2014
    Issue Notice of Acceptance January 2015
    Issue Scoping Document 1 for comments February 2015
    Comments on Scoping Document 1 April 2015
    Issue Scoping Document 2 May 2015
    Issue notice of ready for environmental analysis May 2015
    Commission issues EA January 2016
    Comments on EA February 2016
    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: September 10, 2014.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2014-22096 Filed 9-16-14; 8:45 am]