FFP Missouri 2, LLC; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, and Other Agency Authorizations, 51993-51994 [2014-20760]

Download as PDF Federal Register / Vol. 79, No. 169 / Tuesday, September 2, 2014 / Notices mstockstill on DSK4VPTVN1PROD with NOTICES document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the title ‘‘COMMENTS,’’ ‘‘PROTEST,’’ or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervener must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: August 25, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–20765 Filed 8–29–14; 8:45 am] BILLING CODE 6717–01–P VerDate Mar<15>2010 16:57 Aug 29, 2014 Jkt 232001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13703–002] FFP Missouri 2, LLC; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, and Other Agency Authorizations Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original Major License—Existing Dam. b. Project No.: 13703–002. c. Date filed: November 13, 2013. d. Applicant: FFP Missouri 2, LLC. e. Name of Project: Enid Lake Hydroelectric Project. f. Location: The proposed project would be located at the U.S. Army Corps of Engineers’ (Corps) existing Enid Lake Dam, on the Yocona River, in Yalobusha County, Mississippi. The proposed project would occupy approximately 30 acres of federal lands administered by the Corps. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Thomas Feldman, Vice President, Project Development, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114; (978) 283–2822. i. FERC Contacts: Jeanne Edwards at (202) 502–6181, jeanne.edwards@ ferc.gov or Patti Leppert at (202) 502– 6034, patricia.leppert@ferc.gov. j. The deadline for filing motions to intervene and protests is 60 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file motions to intervene and protests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13703–002. The Commission’s Rules of Practice require all intervenors filing documents PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 51993 with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted, but is not ready for environmental analysis at this time. l. The proposed project would utilize the Corps’ existing Enid Lake Dam outlet works, consisting of a concrete conduit outlet tunnel, regulating gates, and a stilling basin. The project would operate consistent with the Corps’ current operation policy. The proposed project would consist of the following new facilities: (1) A 320foot-long, 10.25-foot-diameter steel liner installed within the Corps’ existing concrete conduit outlet tunnel; (2) a 50foot-long, 20-foot-wide steel-lined concrete bifurcation at the end of the Corps’ existing conduit outlet tunnel to divide the flows between the Corps’ existing stilling basin and the project new powerhouse; (3) a 240-foot-long, 10-foot-diameter steel penstock; (4) a 100-foot-high by 55-foot-wide by 50foot-deep forebay; (5) an 80-foot-long, 50-foot-wide concrete powerhouse with two vertical Kaplan generating units with a total installed capacity of 4.6 megawatts; (6) a 150-foot-long, 75-footwide tailrace channel; (7) a substation; (8) a 2,217-foot-long transmission line consisting of a 181-foot-long, 4.16 kilovolts (kV) buried line from the powerhouse to the substation and a 2,036-foot-long, 12.5 kV overhead line from the substation to an existing utility-owned distribution line; and (9) appurtenant facilities. The project would have an estimated average annual generation of 17.7 gigawatt-hours. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.FERC.gov, using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field, to access the document. For assistance, contact FERC Online Support. A copy is available for inspection and reproduction at the address in item h above. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. E:\FR\FM\02SEN1.SGM 02SEN1 mstockstill on DSK4VPTVN1PROD with NOTICES 51994 Federal Register / Vol. 79, No. 169 / Tuesday, September 2, 2014 / Notices n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice. A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant(s) named in this public notice. o. Anyone may submit a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application. All filings must: (1) Bear in all capital letters the title ‘‘PROTEST,’’ or ‘‘MOTION TO INTERVENE,’’ ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION,’’ or ‘‘COMPETING APPLICATION;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon the representative of the applicant. p. Procedural schedule: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. Issue Notice of Acceptance—August 2014. Issue Scoping Document 1 for comments—October 2014. Comments on Scoping Document 1— November 2014. Issue Scoping Document 2 (if necessary)—December 2014. VerDate Mar<15>2010 16:57 Aug 29, 2014 Jkt 232001 Issue notice of ready for environmental analysis—December 2014. Commission issues EA or draft EA— September 2015. Comments on EA or draft EA—October 2015. Commission issues final EA (if necessary)—April 2016. q. Other Agency Authorizations: Pursuant to section 401 of the Clean Water Act, the Mississippi Department of Environmental Quality (Mississippi DEQ) must certify that discharge from the construction and operation of this proposed project will comply with the Clean Water Act. The Mississippi DEQ is also reviewing the project application under Title 11 Miss. Admin. Code, Pt. 6, Ch.1, Subch.3, which establishes the review of water quality certification applications. Based on an understanding between the Federal Energy Regulatory Commission (FERC) and the Mississippi DEQ, this public notice is also issued for the purpose of advising all interested persons that there is a decision pending before the Mississippi Environmental Quality Permit Board on the request for section 401 water quality certification for this FERC license application. Any comments concerning the water quality certification request may be submitted to the Mississippi Department of Environmental Quality, Office of Pollution Control at Post Office Box 2261, Jackson, Mississippi 39225–2261. The public comment period on the water quality certification extends 30 days from the date of publication of this notice. A copy of the public notice with a description of the project construction and operation is available for review at the Mississippi DEQ’s Jackson office. The complete application may be reviewed at the address listed in paragraph h. Dated: August 25, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–20760 Filed 8–29–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP14–536–000] Northern Natural Gas Company; Notice of Application Take notice that on August 18, 2014, Northern Natural Gas Company (Northern), 1111 South 103rd Street, Omaha, Nebraska 68124, filed an application pursuant to section 7(b) of PO 00000 Frm 00052 Fmt 4703 Sfmt 4703 the Natural Gas Act (NGA) for authorization to abandon in place and by removal approximately 4.74 miles of its 24-inch diameter coupled A-line in Guthrie County, Iowa, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application may be directed to Michael T. Loeffler, Senior Director, Certificates and External Affairs, Northern Natural Gas Company, 1111 South 103rd Street, Omaha, Nebraska 68124, at (402) 398– 7103. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice, the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and E:\FR\FM\02SEN1.SGM 02SEN1

Agencies

[Federal Register Volume 79, Number 169 (Tuesday, September 2, 2014)]
[Notices]
[Pages 51993-51994]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-20760]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13703-002]


FFP Missouri 2, LLC; Notice of Application Accepted for Filing, 
Soliciting Motions To Intervene and Protests, and Other Agency 
Authorizations

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License--Existing Dam.
    b. Project No.: 13703-002.
    c. Date filed: November 13, 2013.
    d. Applicant: FFP Missouri 2, LLC.
    e. Name of Project: Enid Lake Hydroelectric Project.
    f. Location: The proposed project would be located at the U.S. Army 
Corps of Engineers' (Corps) existing Enid Lake Dam, on the Yocona 
River, in Yalobusha County, Mississippi. The proposed project would 
occupy approximately 30 acres of federal lands administered by the 
Corps.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Thomas Feldman, Vice President, Project 
Development, Free Flow Power Corporation, 239 Causeway Street, Suite 
300, Boston, MA 02114; (978) 283-2822.
    i. FERC Contacts: Jeanne Edwards at (202) 502-6181, 
jeanne.edwards@ferc.gov or Patti Leppert at (202) 502-6034, 
patricia.leppert@ferc.gov.
    j. The deadline for filing motions to intervene and protests is 60 
days from the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene and protests and requests for cooperating agency 
status using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 
6,000 characters, without prior registration, using the eComment system 
at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-13703-002.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted, but is not ready for 
environmental analysis at this time.
    l. The proposed project would utilize the Corps' existing Enid Lake 
Dam outlet works, consisting of a concrete conduit outlet tunnel, 
regulating gates, and a stilling basin. The project would operate 
consistent with the Corps' current operation policy.
    The proposed project would consist of the following new facilities: 
(1) A 320-foot-long, 10.25-foot-diameter steel liner installed within 
the Corps' existing concrete conduit outlet tunnel; (2) a 50-foot-long, 
20-foot-wide steel-lined concrete bifurcation at the end of the Corps' 
existing conduit outlet tunnel to divide the flows between the Corps' 
existing stilling basin and the project new powerhouse; (3) a 240-foot-
long, 10-foot-diameter steel penstock; (4) a 100-foot-high by 55-foot-
wide by 50-foot-deep forebay; (5) an 80-foot-long, 50-foot-wide 
concrete powerhouse with two vertical Kaplan generating units with a 
total installed capacity of 4.6 megawatts; (6) a 150-foot-long, 75-
foot-wide tailrace channel; (7) a substation; (8) a 2,217-foot-long 
transmission line consisting of a 181-foot-long, 4.16 kilovolts (kV) 
buried line from the powerhouse to the substation and a 2,036-foot-
long, 12.5 kV overhead line from the substation to an existing utility-
owned distribution line; and (9) appurtenant facilities. The project 
would have an estimated average annual generation of 17.7 gigawatt-
hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.FERC.gov, using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field, to access the document. For assistance, contact 
FERC Online Support. A copy is available for inspection and 
reproduction at the address in item h above.
    Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

[[Page 51994]]

    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.
    o. Anyone may submit a protest, or a motion to intervene in 
accordance with the requirements of Rules of Practice and Procedure, 18 
CFR 385.210, 385.211, and 385.214. In determining the appropriate 
action to take, the Commission will consider all protests filed, but 
only those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any protests 
or motions to intervene must be received on or before the specified 
deadline date for the particular application.
    All filings must: (1) Bear in all capital letters the title 
``PROTEST,'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE 
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in 
the heading the name of the applicant and the project number of the 
application to which the filing responds; (3) furnish the name, 
address, and telephone number of the person protesting or intervening; 
and (4) otherwise comply with the requirements of 18 CFR 385.2001 
through 385.2005. Agencies may obtain copies of the application 
directly from the applicant. A copy of any protest or motion to 
intervene must be served upon the representative of the applicant.
    p. Procedural schedule: The application will be processed according 
to the following Hydro Licensing Schedule. Revisions to the schedule 
will be made as appropriate.
Issue Notice of Acceptance--August 2014.
Issue Scoping Document 1 for comments--October 2014.
Comments on Scoping Document 1--November 2014.
Issue Scoping Document 2 (if necessary)--December 2014.
Issue notice of ready for environmental analysis--December 2014.
Commission issues EA or draft EA--September 2015.
Comments on EA or draft EA--October 2015.
Commission issues final EA (if necessary)--April 2016.
    q. Other Agency Authorizations: Pursuant to section 401 of the 
Clean Water Act, the Mississippi Department of Environmental Quality 
(Mississippi DEQ) must certify that discharge from the construction and 
operation of this proposed project will comply with the Clean Water 
Act. The Mississippi DEQ is also reviewing the project application 
under Title 11 Miss. Admin. Code, Pt. 6, Ch.1, Subch.3, which 
establishes the review of water quality certification applications. 
Based on an understanding between the Federal Energy Regulatory 
Commission (FERC) and the Mississippi DEQ, this public notice is also 
issued for the purpose of advising all interested persons that there is 
a decision pending before the Mississippi Environmental Quality Permit 
Board on the request for section 401 water quality certification for 
this FERC license application. Any comments concerning the water 
quality certification request may be submitted to the Mississippi 
Department of Environmental Quality, Office of Pollution Control at 
Post Office Box 2261, Jackson, Mississippi 39225-2261. The public 
comment period on the water quality certification extends 30 days from 
the date of publication of this notice. A copy of the public notice 
with a description of the project construction and operation is 
available for review at the Mississippi DEQ's Jackson office. The 
complete application may be reviewed at the address listed in paragraph 
h.

    Dated: August 25, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-20760 Filed 8-29-14; 8:45 am]
BILLING CODE 6717-01-P