Dominion Transmission, Inc.: Notice of Intent To Prepare an Environmental Assessment for the Proposed Clarington Project and Request for Comments on Environmental Issues, 44448-44450 [2014-18006]
Download as PDF
wreier-aviles on DSK5TPTVN1PROD with NOTICES
44448
Federal Register / Vol. 79, No. 147 / Thursday, July 31, 2014 / Notices
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. See, 18
VerDate Mar<15>2010
14:56 Jul 30, 2014
Jkt 232001
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Comment Date: 5:00 p.m. Eastern
Time on August 14, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–18007 Filed 7–30–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–496–000]
Dominion Transmission, Inc.: Notice of
Intent To Prepare an Environmental
Assessment for the Proposed
Clarington Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Clarington Project (Project)
involving construction and operation of
facilities by Dominion Transmission,
Inc. (DTI) in Marshall County, West
Virginia and Monroe County, Ohio. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on August 23,
2014.
You may submit comments in written
form or verbally. Further details on how
to submit written comments are in the
Public Participation section of this
notice.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this
proposed Project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the Project, that approval
conveys with it the right of eminent
PO 00000
Frm 00066
Fmt 4703
Sfmt 4703
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
DTI provided landowners with a fact
sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically-asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
Summary of the Proposed Project
DTI proposes to construct, install,
own, operate and maintain certain
compression facilities located in
Marshall County, West Virginia and
Monroe County, Ohio. The Project
would provide 250,000 dekatherms per
day of firm transportation service for
CNX Gas Company, LLC at a proposed
new interconnect known as the TETArman Hill Interconnect and at a
proposed new interconnect known as
the REX-German Ridge Interconnect,
both of which are located in Monroe
County, OH. According to DTI, its
Project would create increased access
for production in this region to major
natural gas markets of the Northeast and
Mid-Atlantic regions of the United
States.
The Clarington Project would consist
of the following facilities:
• A new 6,130 horsepower (hp) gas
turbine/compressor package and
auxiliary equipment at DTI’s existing
Burch Ridge Station in Marshall County,
WV;
• Two new 5,000 hp reciprocating
compression units and auxiliary
equipment at DTI’s existing Mullett
Station in Monroe County, OH;
• 2,612 feet of new 20-inch-diameter
suction piping and 2,756 feet of new 16inch-diameter discharge piping which
would connect the Mullett Compressor
Station to two proposed new
interconnects;
• Two new metering and regulation
facilities in Monroe County, OH: The
TET-Arman Hill Interconnect and the
REX-German Ridge Interconnect; and
• A 987-foot-long 16-inch-diameter
pipeline section to connect the new
proposed REX-German Ridge
Interconnect to the Rockies Express
Pipeline in Monroe County, OH.
E:\FR\FM\31JYN1.SGM
31JYN1
Federal Register / Vol. 79, No. 147 / Thursday, July 31, 2014 / Notices
The general location of the Project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
at the Burch Ridge Station would occur
within the confines of the existing
station and disturb 8.47 acres of land.
Following construction, DTI would
maintain 3.18 acres for permanent
operation of the Project’s facilities; the
remaining acreage would be restored
and revert to former uses. Construction
of the proposed aboveground and
pipeline facilities at the existing Mullett
Station as well as the two new metering
and regulation facilities in Monroe
County, OH would disturb 29.69 acres
of land. Following construction, DTI
would maintain 8.97 acres for
permanent operation of the Project’s
facilities; the remaining acreage would
be restored and revert to former uses.
The EA Process
wreier-aviles on DSK5TPTVN1PROD with NOTICES
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed Project under these general
headings:
• geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
and
• public safety; and
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Mar<15>2010
14:56 Jul 30, 2014
Jkt 232001
• cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed Project or
portions of the Project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section
below.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this Project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Offices (SHPO), and to solicit their
views and those of other government
agencies, interested Indian tribes, and
the public on the Project’s potential
effects on historic properties.4 We will
define the Project-specific Area of
Potential Effects (APE) in consultation
with the SHPOs as the Project develops.
On natural gas facility projects, the APE
at a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA for this project will document
our findings on the impacts on historic
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
44449
properties and summarize the status of
consultations under section 106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before August 23,
2014.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number (CP14–496–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You can file your comments
electronically using the eFiling feature
on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
includes: Federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
E:\FR\FM\31JYN1.SGM
31JYN1
44450
Federal Register / Vol. 79, No. 147 / Thursday, July 31, 2014 / Notices
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project. If we publish
and distribute the EA, copies will be
sent to the environmental mailing list
for public review and comment. If you
would prefer to receive a paper copy of
the document instead of the CD version
or would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
wreier-aviles on DSK5TPTVN1PROD with NOTICES
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP14–496). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
docs-filing/esubscription.asp.
VerDate Mar<15>2010
14:56 Jul 30, 2014
Jkt 232001
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: July 24, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–18006 Filed 7–30–14; 8:45 am]
BILLING CODE 6717–01–P
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on August 13, 2014.
Dated: July 23, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–18009 Filed 7–30–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Docket No. RM13–7–001]
Federal Energy Regulatory
Commission
Protection System Maintenance
Reliability Standard: Notice of Filing
[Project No. 14286–001]
Take notice that on June 4, 2014, the
North American Electric Reliability
Corporation filed a proposed revision to
a Violation Severity Level assigned to
Requirement R1 in Protection System
Maintenance Reliability Standard PRC–
005–2, pursuant to Order No. 793.1
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
Haiwee Ridge Pumped Storage
Project; Notice of Application for
Amendment of Preliminary Permit
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Protests
1 Protection System Maintenance Reliability
Standard, Order No. 793, 145 FERC ¶ 61,253
(2013).
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
On July 2, 2014, Gridflex Energy, LLC
on behalf of Haiwee Ridge Hydro, LLC
(permitee), filed an amendment to its
preliminary permit issued on March 23,
2012,1 for the proposed Haiwee Ridge
Pumped Storage Project No. 14286
(project) to be located on the South
Haiwee reservoir, near the Town of
Olancha, Inyo County, California.2 The
project would be located almost entirely
on land managed by the Bureau of Land
Management (BLM).
The preliminary permit issued on
March 23, 2012, was issued to the
permittee to maintain priority of
application for a license during the term
of the permit while the permittee
conducts investigations and secures
data necessary to determine the
feasibility of the proposed project and
the alternatives it considers. Each of
following alternatives considered would
consist of a project with a total installed
capacity of 500 megawatts (MW):
South Haiwee Alternative A: (1) An
upper reservoir formed by a 160-foothigh by 2,270-foot-long, rollercompacted concrete (RCC) dam, two
saddle dams (a 35-foot-high by 680-footlong RCC dam and a 65-foot-high by
680-foot-long RCC dam) having a total
storage capacity of 15,100 acre-feet and
a water surface area of 175 acres at full
pool elevation of 5,050 feet msl; (2) a
lower reservoir formed by the 81-foot1 138
FERC ¶ 62,298.
July 15, 2014, Gridflex Energy, LLC, on
behalf of Haiwee Ridge Hydro, LLC, filed a
correction to the July 2, 2014 application to amend
the preliminary permit for the Haiwee Ridge
Pumped Storage Project.
2 On
E:\FR\FM\31JYN1.SGM
31JYN1
Agencies
[Federal Register Volume 79, Number 147 (Thursday, July 31, 2014)]
[Notices]
[Pages 44448-44450]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-18006]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-496-000]
Dominion Transmission, Inc.: Notice of Intent To Prepare an
Environmental Assessment for the Proposed Clarington Project and
Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Clarington Project (Project)
involving construction and operation of facilities by Dominion
Transmission, Inc. (DTI) in Marshall County, West Virginia and Monroe
County, Ohio. The Commission will use this EA in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on August 23, 2014.
You may submit comments in written form or verbally. Further
details on how to submit written comments are in the Public
Participation section of this notice.
This notice is being sent to the Commission's current environmental
mailing list for this Project. State and local government
representatives should notify their constituents of this proposed
Project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
DTI provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
DTI proposes to construct, install, own, operate and maintain
certain compression facilities located in Marshall County, West
Virginia and Monroe County, Ohio. The Project would provide 250,000
dekatherms per day of firm transportation service for CNX Gas Company,
LLC at a proposed new interconnect known as the TET-Arman Hill
Interconnect and at a proposed new interconnect known as the REX-German
Ridge Interconnect, both of which are located in Monroe County, OH.
According to DTI, its Project would create increased access for
production in this region to major natural gas markets of the Northeast
and Mid-Atlantic regions of the United States.
The Clarington Project would consist of the following facilities:
A new 6,130 horsepower (hp) gas turbine/compressor package
and auxiliary equipment at DTI's existing Burch Ridge Station in
Marshall County, WV;
Two new 5,000 hp reciprocating compression units and
auxiliary equipment at DTI's existing Mullett Station in Monroe County,
OH;
2,612 feet of new 20-inch-diameter suction piping and
2,756 feet of new 16-inch-diameter discharge piping which would connect
the Mullett Compressor Station to two proposed new interconnects;
Two new metering and regulation facilities in Monroe
County, OH: The TET-Arman Hill Interconnect and the REX-German Ridge
Interconnect; and
A 987-foot-long 16-inch-diameter pipeline section to
connect the new proposed REX-German Ridge Interconnect to the Rockies
Express Pipeline in Monroe County, OH.
[[Page 44449]]
The general location of the Project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities at the Burch Ridge Station
would occur within the confines of the existing station and disturb
8.47 acres of land. Following construction, DTI would maintain 3.18
acres for permanent operation of the Project's facilities; the
remaining acreage would be restored and revert to former uses.
Construction of the proposed aboveground and pipeline facilities at the
existing Mullett Station as well as the two new metering and regulation
facilities in Monroe County, OH would disturb 29.69 acres of land.
Following construction, DTI would maintain 8.97 acres for permanent
operation of the Project's facilities; the remaining acreage would be
restored and revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed Project under these
general headings:
geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species; and
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
Project or portions of the Project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section below.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this Project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Offices (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the Project's potential effects on
historic properties.\4\ We will define the Project-specific Area of
Potential Effects (APE) in consultation with the SHPOs as the Project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before August
23, 2014.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP14-496-000) with your
submission. The Commission encourages electronic filing of comments and
has expert staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes: Federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for
[[Page 44450]]
project purposes, or who own homes within certain distances of
aboveground facilities, and anyone who submits comments on the project.
We will update the environmental mailing list as the analysis proceeds
to ensure that we send the information related to this environmental
review to all individuals, organizations, and government entities
interested in and/or potentially affected by the proposed project. If
we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP14-
496). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: July 24, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-18006 Filed 7-30-14; 8:45 am]