Download as PDF emcdonald on DSK67QTVN1PROD with NOTICES Federal Register / Vol. 79, No. 139 / Monday, July 21, 2014 / Notices Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 7 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE., Washington, DC 20426. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed VerDate Mar<15>2010 17:14 Jul 18, 2014 Jkt 232001 docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on August 1, 2014. Dated: July 11, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–17042 Filed 7–18–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [City of Radford Electric Utilities; Project No. 1235–016] Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process a. Type of Filing: Notice of Intent to File License Application and Request to Use the Traditional Licensing Process. b. Project No.: 1235–016. c. Date Filed: May 23, 2014. d. Submitted By: City of Radford Electric Utilities. e. Name of Project: Municipal Hydroelectric Project. f. Location: The Municipal Hydroelectric Project is located on the Little River near the city of Radford, in Montgomery and Pulaski counties, Virginia. The project does not affect federal lands. g. Filed Pursuant to: 18 CFR 5.3 of the Commission’s regulations. h. Applicant Contact: Tim Logwood, City of Radford Electric Utilities, 701 17th Street, Radford, Virginia 24141; (540) 731–3641 or email at tlogwood@ radford.va.us. i. FERC Contact: Allyson Conner at (202) 502–6082 or email at allyson.conner@ferc.gov. j. City of Radford Electric Utilities (Radford) filed its request to use the Traditional Licensing Process on May 23, 2014. Radford provided public notice of its request on May 21, 2014. In a letter dated July 11, 2014, the Director of the Division of Hydropower Licensing approved Radford’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; and (b) the Virginia State Historic Preservation Officer, as required by section 106, National PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 42309 Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Radford as the Commission’s nonfederal representative for carrying out informal consultation pursuant to section 7 of the Endangered Species Act and consultation pursuant to section 106 of the National Historic Preservation Act. m. Radford filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). A copy is also available for inspection and reproduction at the address in paragraph h. o. The licensee states its unequivocal intent to submit an application for a subsequent license for Project No. 1235– 016. Pursuant to CFR 16.8, 16.9, and 16.10 each application for a subsequent license and any competing license applications must be filed with the Commission at least 24 months prior to the expiration of the existing license. All applications for license for this project must be filed by May 31, 2017. p. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: July 11, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–17049 Filed 7–18–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER14–781–003. E:\FR\FM\21JYN1.SGM 21JYN1

Agencies

[Federal Register Volume 79, Number 139 (Monday, July 21, 2014)]
[Notices]
[Page 42309]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-17049]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[City of Radford Electric Utilities; Project No. 1235-016]


Notice of Intent To File License Application, Filing of Pre-
Application Document, and Approving Use of the Traditional Licensing 
Process

    a. Type of Filing: Notice of Intent to File License Application and 
Request to Use the Traditional Licensing Process.
    b. Project No.: 1235-016.
    c. Date Filed: May 23, 2014.
    d. Submitted By: City of Radford Electric Utilities.
    e. Name of Project: Municipal Hydroelectric Project.
    f. Location: The Municipal Hydroelectric Project is located on the 
Little River near the city of Radford, in Montgomery and Pulaski 
counties, Virginia. The project does not affect federal lands.
    g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
    h. Applicant Contact: Tim Logwood, City of Radford Electric 
Utilities, 701 17th Street, Radford, Virginia 24141; (540) 731-3641 or 
email at tlogwood@radford.va.us.
    i. FERC Contact: Allyson Conner at (202) 502-6082 or email at 
allyson.conner@ferc.gov.
    j. City of Radford Electric Utilities (Radford) filed its request 
to use the Traditional Licensing Process on May 23, 2014. Radford 
provided public notice of its request on May 21, 2014. In a letter 
dated July 11, 2014, the Director of the Division of Hydropower 
Licensing approved Radford's request to use the Traditional Licensing 
Process.
    k. With this notice, we are initiating informal consultation with: 
(a) The U.S. Fish and Wildlife Service under section 7 of the 
Endangered Species Act and the joint agency regulations thereunder at 
50 CFR, Part 402; and (b) the Virginia State Historic Preservation 
Officer, as required by section 106, National Historic Preservation 
Act, and the implementing regulations of the Advisory Council on 
Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Radford as the Commission's 
non-federal representative for carrying out informal consultation 
pursuant to section 7 of the Endangered Species Act and consultation 
pursuant to section 106 of the National Historic Preservation Act.
    m. Radford filed a Pre-Application Document (PAD; including a 
proposed process plan and schedule) with the Commission, pursuant to 18 
CFR 5.6 of the Commission's regulations.
    n. A copy of the PAD is available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's Web site 
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at 
the address in paragraph h.
    o. The licensee states its unequivocal intent to submit an 
application for a subsequent license for Project No. 1235-016. Pursuant 
to CFR 16.8, 16.9, and 16.10 each application for a subsequent license 
and any competing license applications must be filed with the 
Commission at least 24 months prior to the expiration of the existing 
license. All applications for license for this project must be filed by 
May 31, 2017.
    p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

    Dated: July 11, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-17049 Filed 7-18-14; 8:45 am]
BILLING CODE 6717-01-P