Paiute Pipeline Company; Notice of Application, 42307-42308 [2014-17046]
Download as PDF
42307
Federal Register / Vol. 79, No. 139 / Monday, July 21, 2014 / Notices
FERC–512: APPLICATION FOR PRELIMINARY PERMIT
Number of
respondents
Annual number of
responses per
respondent
Total number of
responses
Average burden/$ per
response 16
Total annual burden
hours (total annual
cost)
Cost per respondent
($)
(1)
(2)
(1)*(2)=(3)
(4)
(3)*(4)=(5)
(5)÷(1)
125
1
125
37,$2,608.50
4,625, $326,062.50
$2,608.50
FERC–588, Emergency Natural Gas
Transportation, Sale, and Exchange
Transportation
OMB Control No.: 1902–0144.
Abstract: The Commission uses the
information collected under the
requirements of FERC–588 to
implement the statutory provisions of
sections 7(c) of the Natural Gas Act
(NGA) (P.L. 75–688) (15 USC 717–717w)
and provisions of the Natural Gas Policy
Act of 1978 (NGPA), 15 USC. 3301–
3432. Under the NGA, a natural gas
company must obtain Commission
approval to engage in the transportation,
sale or exchange of natural gas in
interstate commerce. However, section
7(c) exempts from certificate
requirements ‘‘temporary acts or
operations for which the issuance of a
certificate will not be required in the
public interest.’’ The NGPA also
provides for non-certificated interstate
transactions involving intrastate
pipelines and local distribution
companies.
A temporary operation, or emergency,
is defined as any situation in which an
actual or expected shortage of gas
supply would require an interstate
pipeline company, intrastate pipeline,
local distribution company, or Hinshaw
pipeline to curtail deliveries of gas or
provide less than the projected level of
service to the customer. The natural gas
companies which provide the temporary
assistance to the companies which are
having the ‘‘emergency’’ must file the
necessary information described in Part
284, Subpart I of the Commission’s
Regulations with the Commission so
that it may determine if their assisting
transaction/operation qualifies for
exemption. The assisting company may
or may not be under the Commission’s
jurisdiction and if their assisting actions
qualify for the exemption, they will not
become subject to the Commission’s
jurisdiction for such actions.
A report within forty-eight hours of
the commencement of the
transportation, sale or exchange, a
request to extend the sixty-day term of
the emergency transportation, if needed,
and a termination report are required.
The data required to be filed for the
forty-eight hour report is specified by 18
CFR 284.270.
Type of Respondents: Natural Gas
Pipelines.
Estimate of Annual Burden: The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–588: EMERGENCY NATURAL GAS TRANSPORTATION, SALE, AND EXCHANGE TRANSPORTATION
Number of
respondents
Annual number of
responses per
respondent
Total number of
responses
Average burden/$ per
response 17
Total annual burden
hours (total annual
cost)
Cost per respondent
($)
(1)
(2)
(1)*(2)=(3)
(4)
(3)*(4)=(5)
(5)÷(1)
8
1
8
10, $705
80, $5,640
$705
Dated: July 11, 2014.
Kimberly D. Bose,
Secretary.
Take notice that on June 27, 2014,
Paiute Pipeline Company (Paiute), P.O.
Box 94197, Las Vegas, Nevada 89193–
4197, filed an application in Docket No.
CP14–509–000, pursuant to section 7(c)
of the Natural Gas Act (NGA), and Part
157 of the Commission’s regulations, for
authority to construct, and operate
certain pipeline and associated facilities
for its 2015 Elko Area Expansion Project
(Project) located in Elko County,
Nevada. The Project will consist of
construction of approximately 35.2
miles of 8-inch diameter pipeline
extending from a new interconnect with
Ruby Pipeline, L.L.C. to Paiute’s
existing Elko Lateral near the Elko
Nevada City Gate, all as more fully set
forth in the application, which is on file
with the Commission and open to
public inspection. This filing may also
be viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
16 The estimates for cost per response are derived
using the following formula: Average Burden Hours
per Response * $70.50 per hour.
17 The estimates for cost per response are derived
using the following formula: Average Burden Hours
per Response * $70.50 per hour.
[FR Doc. 2014–17044 Filed 7–18–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP14–509–000; PF14–4–000]
emcdonald on DSK67QTVN1PROD with NOTICES
Paiute Pipeline Company; Notice of
Application
VerDate Mar<15>2010
17:14 Jul 18, 2014
Jkt 232001
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed to Mark
A. Litwin, Vice President/General
Manager, Paiute Pipeline Company, P.O.
Box 94197, Las Vegas, Nevada 89193–
4197 or by calling 702–364–3195.
On October 31, 2013, Commission
staff granted Paiute’s request to use the
pre-filing process and assigned Docket
No. PF14–4–000 to staff activities
involving the project. Now, as of the
filing of this application on June 27,
2014, the NEPA Pre-Filing Process for
this project has ended. From this time
forward, this proceeding will be
conducted in Docket No. CP14–509 as
noted in the caption of this Notice.
Pursuant to section 157.9 of the
Commission’s regulations, 18 CFR
E:\FR\FM\21JYN1.SGM
21JYN1
emcdonald on DSK67QTVN1PROD with NOTICES
42308
Federal Register / Vol. 79, No. 139 / Monday, July 21, 2014 / Notices
157.9, within 90 days of this Notice, the
Commission’s staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission’s staff issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to reach a final
decision on a request for federal
authorization within 90 days of the date
of issuance of the Commission staff’s
EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
VerDate Mar<15>2010
17:14 Jul 18, 2014
Jkt 232001
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Comment Date: 5:00 p.m. Eastern
Time on July 31, 2014.
Dated: July 10, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–17046 Filed 7–18–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–511–000]
Kinder Morgan Louisiana Pipeline LLC;
Notice of Application
Take notice that on June 30, 2014,
Kinder Morgan Louisiana Pipeline LLC
(KMLP), 3250 Lacey Road, Suite 700,
Downers Grove, Illinois 60515, filed in
Docket No. CP14–511–000, an
application pursuant to section 7(c) of
the Natural Gas Act and Part 157 of the
Commission’s regulations, for a
certificate of public convenience and
necessity to construct and operate
certain facilities located in Calcasieu
Parish, Louisiana known as the Lake
Charles Expansion Project.
Specifically, KMLP request to
construct approximately 1.3 miles of
header pipeline, a new 64,000
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
horsepower (hp) compressor station,
and modification of five existing
delivery points in Calcasieu and Acadia
Parishes, Louisiana. The proposal will
provide 1,400 million cubic feet (MMcf)
per day of firm north-to-south
transportation capacity to deliver
natural gas to the proposed liquefaction
and export facility to be constructed by
Magnolia LNG, LLC in Docket No.CP14–
347–000. The estimated cost of the
project is $201.9 million, all as more
fully set forth in the application, which
is on file with the Commission and open
to public inspection. The filing may also
be viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding this
application should be directed to Bruce
H. Newsome, Vice President, Kinder
Morgan Louisiana Pipeline LLC, 3250
Lacey Road, Suite 700, Downers Grove,
Illinois 60515, phone: (630) 725–3070 or
email: bruce_newsome@
kindermorgan.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR § 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
E:\FR\FM\21JYN1.SGM
21JYN1
Agencies
[Federal Register Volume 79, Number 139 (Monday, July 21, 2014)]
[Notices]
[Pages 42307-42308]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-17046]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP14-509-000; PF14-4-000]
Paiute Pipeline Company; Notice of Application
Take notice that on June 27, 2014, Paiute Pipeline Company
(Paiute), P.O. Box 94197, Las Vegas, Nevada 89193-4197, filed an
application in Docket No. CP14-509-000, pursuant to section 7(c) of the
Natural Gas Act (NGA), and Part 157 of the Commission's regulations,
for authority to construct, and operate certain pipeline and associated
facilities for its 2015 Elko Area Expansion Project (Project) located
in Elko County, Nevada. The Project will consist of construction of
approximately 35.2 miles of 8-inch diameter pipeline extending from a
new interconnect with Ruby Pipeline, L.L.C. to Paiute's existing Elko
Lateral near the Elko Nevada City Gate, all as more fully set forth in
the application, which is on file with the Commission and open to
public inspection. This filing may also be viewed on the Web at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Any questions regarding this application should be directed to Mark
A. Litwin, Vice President/General Manager, Paiute Pipeline Company,
P.O. Box 94197, Las Vegas, Nevada 89193-4197 or by calling 702-364-
3195.
On October 31, 2013, Commission staff granted Paiute's request to
use the pre-filing process and assigned Docket No. PF14-4-000 to staff
activities involving the project. Now, as of the filing of this
application on June 27, 2014, the NEPA Pre-Filing Process for this
project has ended. From this time forward, this proceeding will be
conducted in Docket No. CP14-509 as noted in the caption of this
Notice.
Pursuant to section 157.9 of the Commission's regulations, 18 CFR
[[Page 42308]]
157.9, within 90 days of this Notice, the Commission's staff will
either complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission's staff issuance of
the EA for this proposal. The filing of the EA in the Commission's
public record for this proceeding or the issuance of a Notice of
Schedule for Environmental Review will serve to notify federal and
state agencies of the timing for the completion of all necessary
reviews, and the subsequent need to reach a final decision on a request
for federal authorization within 90 days of the date of issuance of the
Commission staff's EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 7 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the
Commission's Web site under the ``e-Filing'' link.
Comment Date: 5:00 p.m. Eastern Time on July 31, 2014.
Dated: July 10, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-17046 Filed 7-18-14; 8:45 am]
BILLING CODE 6717-01-P