Kinder Morgan Louisiana Pipeline LLC; Notice of Application, 42308-42309 [2014-17042]

Download as PDF emcdonald on DSK67QTVN1PROD with NOTICES 42308 Federal Register / Vol. 79, No. 139 / Monday, July 21, 2014 / Notices 157.9, within 90 days of this Notice, the Commission’s staff will either complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission’s staff issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to reach a final decision on a request for federal authorization within 90 days of the date of issuance of the Commission staff’s EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 7 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this VerDate Mar<15>2010 17:14 Jul 18, 2014 Jkt 232001 project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. Comment Date: 5:00 p.m. Eastern Time on July 31, 2014. Dated: July 10, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–17046 Filed 7–18–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP14–511–000] Kinder Morgan Louisiana Pipeline LLC; Notice of Application Take notice that on June 30, 2014, Kinder Morgan Louisiana Pipeline LLC (KMLP), 3250 Lacey Road, Suite 700, Downers Grove, Illinois 60515, filed in Docket No. CP14–511–000, an application pursuant to section 7(c) of the Natural Gas Act and Part 157 of the Commission’s regulations, for a certificate of public convenience and necessity to construct and operate certain facilities located in Calcasieu Parish, Louisiana known as the Lake Charles Expansion Project. Specifically, KMLP request to construct approximately 1.3 miles of header pipeline, a new 64,000 PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 horsepower (hp) compressor station, and modification of five existing delivery points in Calcasieu and Acadia Parishes, Louisiana. The proposal will provide 1,400 million cubic feet (MMcf) per day of firm north-to-south transportation capacity to deliver natural gas to the proposed liquefaction and export facility to be constructed by Magnolia LNG, LLC in Docket No.CP14– 347–000. The estimated cost of the project is $201.9 million, all as more fully set forth in the application, which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application should be directed to Bruce H. Newsome, Vice President, Kinder Morgan Louisiana Pipeline LLC, 3250 Lacey Road, Suite 700, Downers Grove, Illinois 60515, phone: (630) 725–3070 or email: bruce_newsome@ kindermorgan.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR § 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and E:\FR\FM\21JYN1.SGM 21JYN1 emcdonald on DSK67QTVN1PROD with NOTICES Federal Register / Vol. 79, No. 139 / Monday, July 21, 2014 / Notices Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 7 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE., Washington, DC 20426. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed VerDate Mar<15>2010 17:14 Jul 18, 2014 Jkt 232001 docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on August 1, 2014. Dated: July 11, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–17042 Filed 7–18–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [City of Radford Electric Utilities; Project No. 1235–016] Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process a. Type of Filing: Notice of Intent to File License Application and Request to Use the Traditional Licensing Process. b. Project No.: 1235–016. c. Date Filed: May 23, 2014. d. Submitted By: City of Radford Electric Utilities. e. Name of Project: Municipal Hydroelectric Project. f. Location: The Municipal Hydroelectric Project is located on the Little River near the city of Radford, in Montgomery and Pulaski counties, Virginia. The project does not affect federal lands. g. Filed Pursuant to: 18 CFR 5.3 of the Commission’s regulations. h. Applicant Contact: Tim Logwood, City of Radford Electric Utilities, 701 17th Street, Radford, Virginia 24141; (540) 731–3641 or email at tlogwood@ radford.va.us. i. FERC Contact: Allyson Conner at (202) 502–6082 or email at allyson.conner@ferc.gov. j. City of Radford Electric Utilities (Radford) filed its request to use the Traditional Licensing Process on May 23, 2014. Radford provided public notice of its request on May 21, 2014. In a letter dated July 11, 2014, the Director of the Division of Hydropower Licensing approved Radford’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; and (b) the Virginia State Historic Preservation Officer, as required by section 106, National PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 42309 Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Radford as the Commission’s nonfederal representative for carrying out informal consultation pursuant to section 7 of the Endangered Species Act and consultation pursuant to section 106 of the National Historic Preservation Act. m. Radford filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). A copy is also available for inspection and reproduction at the address in paragraph h. o. The licensee states its unequivocal intent to submit an application for a subsequent license for Project No. 1235– 016. Pursuant to CFR 16.8, 16.9, and 16.10 each application for a subsequent license and any competing license applications must be filed with the Commission at least 24 months prior to the expiration of the existing license. All applications for license for this project must be filed by May 31, 2017. p. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: July 11, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–17049 Filed 7–18–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER14–781–003. E:\FR\FM\21JYN1.SGM 21JYN1

Agencies

[Federal Register Volume 79, Number 139 (Monday, July 21, 2014)]
[Notices]
[Pages 42308-42309]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-17042]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP14-511-000]


Kinder Morgan Louisiana Pipeline LLC; Notice of Application

    Take notice that on June 30, 2014, Kinder Morgan Louisiana Pipeline 
LLC (KMLP), 3250 Lacey Road, Suite 700, Downers Grove, Illinois 60515, 
filed in Docket No. CP14-511-000, an application pursuant to section 
7(c) of the Natural Gas Act and Part 157 of the Commission's 
regulations, for a certificate of public convenience and necessity to 
construct and operate certain facilities located in Calcasieu Parish, 
Louisiana known as the Lake Charles Expansion Project.
    Specifically, KMLP request to construct approximately 1.3 miles of 
header pipeline, a new 64,000 horsepower (hp) compressor station, and 
modification of five existing delivery points in Calcasieu and Acadia 
Parishes, Louisiana. The proposal will provide 1,400 million cubic feet 
(MMcf) per day of firm north-to-south transportation capacity to 
deliver natural gas to the proposed liquefaction and export facility to 
be constructed by Magnolia LNG, LLC in Docket No.CP14-347-000. The 
estimated cost of the project is $201.9 million, all as more fully set 
forth in the application, which is on file with the Commission and open 
to public inspection. The filing may also be viewed on the web at 
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket 
number excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding this application should be directed to 
Bruce H. Newsome, Vice President, Kinder Morgan Louisiana Pipeline LLC, 
3250 Lacey Road, Suite 700, Downers Grove, Illinois 60515, phone: (630) 
725-3070 or email: bruce_newsome@kindermorgan.com.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR Sec.  
157.9, within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and

[[Page 42309]]

Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA 
(18 CFR 157.10). A person obtaining party status will be placed on the 
service list maintained by the Secretary of the Commission and will 
receive copies of all documents filed by the applicant and by all other 
parties. A party must submit 7 copies of filings made with the 
Commission and must mail a copy to the applicant and to every other 
party in the proceeding. Only parties to the proceeding can ask for 
court review of Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    There is an ``eSubscription'' link on the Web site that enables 
subscribers to receive email notification when a document is added to a 
subscribed docket(s). For assistance with any FERC Online service, 
please email FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll 
free). For TTY, call (202) 502-8659.
    Comment Date: 5:00 p.m. Eastern Time on August 1, 2014.

    Dated: July 11, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-17042 Filed 7-18-14; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.