Roaring Springs Ranch; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 40750-40751 [2014-16346]

Download as PDF 40750 Federal Register / Vol. 79, No. 134 / Monday, July 14, 2014 / Notices Division of Hydropower Licensing approved Spartanburg Water System’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; and NOAA Fisheries under section 305(b) of the MagnusonStevens Fishery Conservation and Management Act and implementing regulations at 50 CFR 600.920. We are also initiating consultation with the South Carolina State Historic Preservation Officer, as required by section 106, National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Spartanburg Water System as the Commission’s non-federal representative for carrying out informal consultation pursuant to section 7 of the Endangered Species Act and section 305(b) of the Magnuson-Stevens Fishery Conservation and Management Act; and consultation pursuant to section 106 of the National Historic Preservation Act. m. Spartanburg Water System filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). A copy is also available for inspection and reproduction at the address in paragraph h. o. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: July 7, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–16348 Filed 7–11–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD14–21–000] construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act, as amended by section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The Three Mile Hydropower Project would utilize a newly constructed agricultural water distribution system at the Roaring Springs Ranch in Harney County, Oregon. Applicant Contact: Darryl Anderson, Anderson Engineering & Surveying, Inc., 17681 Highway 395, Lakeview, OR 97630, Phone No. (541) 947–4407. FERC Contact: Christopher Chaney, Phone No. (202) 502–6778, email: christopher.chaney@ferc.gov. Qualifying Conduit Hydropower Facility Description: The proposed project would consist of: (1) A new 12foot-wide by 12-foot-long powerhouse; (2) one proposed 10.5-kilowatt turbine/ generating unit; and (3) appurtenant facilities. A qualifying conduit hydropower facility is one that is determined or deemed to meet all of the criteria shown in the table below. Roaring Springs Ranch; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene On June 23, 2014, Roaring Springs Ranch filed a notice of intent to TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY Statutory provision Description Satisfies (Y/N) FPA 30(a)(3)(A), as amended by HREA ........ The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a nonfederally owned conduit. The facility has an installed capacity that does not exceed 5 megawatts ................ On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA. Y FPA 30(a)(3)(C)(i), as amended by HREA .... mstockstill on DSK4VPTVN1PROD with NOTICES FPA 30(a)(3)(C)(ii), as amended by HREA .... FPA 30(a)(3)(C)(iii), as amended by HREA ... Preliminary Determination: Based upon the above criteria, Commission staff preliminarily determines that the proposal satisfies the requirements for a qualifying conduit hydropower facility not required to be licensed or exempted from licensing. Comments and Motions to Intervene: Deadline for filing comments contesting whether the facility meets the qualifying VerDate Mar<15>2010 19:25 Jul 11, 2014 Jkt 232001 criteria is 45 days from the issuance date of this notice. Deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 Y Y Y deadline date for the particular proceeding. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the ‘‘COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY’’ or ‘‘MOTION TO INTERVENE,’’ as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the E:\FR\FM\14JYN1.SGM 14JYN1 Federal Register / Vol. 79, No. 134 / Monday, July 14, 2014 / Notices filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the Commission’s regulations.1 All comments contesting Commission staff’s preliminary determination that the facility meets the qualifying criteria must set forth their evidentiary basis. The Commission strongly encourages electronic filing. Please file motions to intervene and comments using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Locations of Notice of Intent: Copies of the notice of intent can be obtained directly from the applicant or such copies can be viewed and reproduced at the Commission in its Public Reference Room, Room 2A, 888 First Street NE., Washington, DC 20426. The filing may also be viewed on the Web at https:// www.ferc.gov/docs-filing/elibrary.asp using the ‘‘eLibrary’’ link. Enter the docket number (e.g., CD14–21) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or email FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. Dated: July 7, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–16346 Filed 7–11–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD14–22–000] Roaring Springs Ranch; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene 40751 construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act, as amended by section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The Roaring Springs Headquarters Hydropower Project would utilize a newly constructed agricultural water distribution system at the Roaring Springs Ranch in Harney County, Oregon. Applicant Contact: Darryl Anderson, Anderson Engineering & Surveying, Inc., 17681 Highway 395, Lakeview, OR 97630, Phone No. (541) 947–4407. FERC Contact: Christopher Chaney, Phone No. (202) 502–6778, email: christopher.chaney@ferc.gov. Qualifying Conduit Hydropower Facility Description: The proposed project would consist of: (1) A new 14foot-wide by 17-foot-long powerhouse; (2) one proposed 37-kilowatt turbine/ generating unit; and (3) appurtenant facilities. A qualifying conduit hydropower facility is one that is determined or deemed to meet all of the criteria shown in the table below. On June 23, 2014, Roaring Springs Ranch filed a notice of intent to TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY Statutory provision Description Satisfies (Y/N) FPA 30(a)(3)(A), as amended by HREA ........ The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a nonfederally owned conduit. The facility has an installed capacity that does not exceed 5 megawatts ................ On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA. Y FPA 30(a)(3)(C)(i), as amended by HREA .... mstockstill on DSK4VPTVN1PROD with NOTICES FPA 30(a)(3)(C)(ii), as amended by HREA .... FPA 30(a)(3)(C)(iii), as amended by HREA ... Preliminary Determination: Based upon the above criteria, Commission staff preliminarily determines that the proposal satisfies the requirements for a qualifying conduit hydropower facility not required to be licensed or exempted from licensing. Comments and Motions to Intervene: Deadline for filing comments contesting whether the facility meets the qualifying criteria is 45 days from the issuance date of this notice. 1 18 Deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified deadline date for the particular proceeding. Filing and Service of Responsive Documents: All filings must (1) bear in CFR 385.2001–2005 (2013). VerDate Mar<15>2010 19:25 Jul 11, 2014 1 18 Jkt 232001 PO 00000 Fmt 4703 Sfmt 4703 Y Y all capital letters the ‘‘COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY’’ or ‘‘MOTION TO INTERVENE,’’ as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the Commission’s regulations.1 All CFR 385.2001–2005 (2013). Frm 00047 Y E:\FR\FM\14JYN1.SGM 14JYN1

Agencies

[Federal Register Volume 79, Number 134 (Monday, July 14, 2014)]
[Notices]
[Pages 40750-40751]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-16346]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD14-21-000]


Roaring Springs Ranch; Notice of Preliminary Determination of a 
Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On June 23, 2014, Roaring Springs Ranch filed a notice of intent to 
construct a qualifying conduit hydropower facility, pursuant to section 
30 of the Federal Power Act, as amended by section 4 of the Hydropower 
Regulatory Efficiency Act of 2013 (HREA). The Three Mile Hydropower 
Project would utilize a newly constructed agricultural water 
distribution system at the Roaring Springs Ranch in Harney County, 
Oregon.
    Applicant Contact: Darryl Anderson, Anderson Engineering & 
Surveying, Inc., 17681 Highway 395, Lakeview, OR 97630, Phone No. (541) 
947-4407.
    FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email: 
christopher.chaney@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A new 12-foot-wide by 12-foot-long 
powerhouse; (2) one proposed 10.5-kilowatt turbine/generating unit; and 
(3) appurtenant facilities.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
                                                            Satisfies (Y/
       Statutory provision               Description             N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by    The conduit the facility            Y
 HREA.                             uses is a tunnel,
                                   canal, pipeline,
                                   aqueduct, flume, ditch,
                                   or similar manmade
                                   water conveyance that
                                   is operated for the
                                   distribution of water
                                   for agricultural,
                                   municipal, or
                                   industrial consumption
                                   and not primarily for
                                   the generation of
                                   electricity.
FPA 30(a)(3)(C)(i), as amended    The facility is                     Y
 by HREA.                          constructed, operated,
                                   or maintained for the
                                   generation of electric
                                   power and uses for such
                                   generation only the
                                   hydroelectric potential
                                   of a non-federally
                                   owned conduit.
FPA 30(a)(3)(C)(ii), as amended   The facility has an                 Y
 by HREA.                          installed capacity that
                                   does not exceed 5
                                   megawatts.
FPA 30(a)(3)(C)(iii), as amended  On or before August 9,              Y
 by HREA.                          2013, the facility is
                                   not licensed, or
                                   exempted from the
                                   licensing requirements
                                   of Part I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility not 
required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the

[[Page 40751]]

filing responds; (3) state the name, address, and telephone number of 
the person filing; and (4) otherwise comply with the requirements of 
sections 385.2001 through 385.2005 of the Commission's regulations.\1\ 
All comments contesting Commission staff's preliminary determination 
that the facility meets the qualifying criteria must set forth their 
evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2013).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the Web at https://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD14-21) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, call 
(202) 502-8659.

    Dated: July 7, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-16346 Filed 7-11-14; 8:45 am]
BILLING CODE 6717-01-P