Pennamaquan Tidal Power LLC; Notice of Initial Study Plan Meetings and Revised Process Plan, 38883-38884 [2014-15997]

Download as PDF 38883 Federal Register / Vol. 79, No. 131 / Wednesday, July 9, 2014 / Notices a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to Section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such motions or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission encourages electronic submission of comments, protests, and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: June 30, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–15995 Filed 7–8–14; 8:45 am] BILLING CODE 6717–01–P Pre-filing milestone Pennamaquan .................. Pennamaquan .................. FERC ............................... FERC ............................... Issue Public Notice for NOI/PAD .......................... File NOI/PAD with FERC ...................................... Initiate Tribal Consultation ..................................... Issue Notice of Commencement of Proceeding; Scoping Document 1 (SD1). Project Environmental Site Review and Scoping Meetings. PAD/SD1 Comments and Study Requests Due ... Issue Scoping Document 2 (if needed) ................ File Proposed Study Plan (PSP) ........................... Proposed Study Plan Meeting (scheduled for 8/6/ 14 to 8/8/14). Proposed Study Plan Comments Due .................. File Revised Study Plan ........................................ Revised Study Plan Comments Due .................... sroberts on DSK5SPTVN1PROD with NOTICES All stakeholders ............... FERC ............................... Pennamaquan .................. All stakeholders ............... All stakeholders ............... Pennamaquan .................. All stakeholders ............... VerDate Mar<15>2010 20:08 Jul 08, 2014 Jkt 232001 PO 00000 Frm 00034 Federal Energy Regulatory Commission [Project No. 13884–001] Pennamaquan Tidal Power LLC; Notice of Initial Study Plan Meetings and Revised Process Plan On June 5, 2014, Commission staff issued a letter to Pennamaquan Tidal Power LLC (Pennamaquan Tidal) stating that Pennamaquan Tidal’s proposed study plan for the Pennamaquan Tidal Power Plant Project (P–13884) filed on December 12, 2013, meets the requirements of section 5.11 of the Commission’s regulations and that the Integrated Licensing Process (ILP) can resume. According to section 5.11(e) of the Commission’s regulations, the next step in the ILP is the initial study plan meeting. In its June 5, 2014, letter, Commission staff indicated that the initial study plan meeting must be held within 75 days of, but no sooner than 60 days from, June 5, 2014. Accordingly, Pennamaquan Tidal has scheduled the meetings listed below: Meetings in Bangor, ME Dates and Times: August 6 and 7, 2014. 8:00 a.m. to 5:00 p.m. Location: Maine Department of Environmental Protection, Eastern Maine Regional Office, 106 Hogan Road, Bangor, Maine 04401. Contact: Ramez Attiya, Pennamaquan Tidal, (281) 467–0846. Meeting in Pembroke, ME Date and Time: August 8, 2014. 12:00 p.m. to 2:00 p.m. Location: Pembroke Town Office, 48 Old County Road, Pembroke, ME 04666. Contact: Ramez Attiya, Pennamaquan Tidal, (281) 467–0846. A revised process plan that includes new dates for completing the ILP is provided below: FERC regulation Date 1 Responsible party FERC ............................... DEPARTMENT OF ENERGY Fmt 4703 7/19/12 7/19/12 8/18/12 9/14/12 5.3(d)(2) 5.5, 5.6 5.7 5.8 10/25/12 10/26/12 12/4/12 1/18/13 12/12/13 Between 8/4/14 and 8/19/14 2 5.8(b)(viii) 5.9 5.1 5.11(a) 5.11(e) 10/18/14 11/17/14 12/2/14 5.12 5.13(a) 5.13(b) Sfmt 4703 E:\FR\FM\09JYN1.SGM 09JYN1 38884 Federal Register / Vol. 79, No. 131 / Wednesday, July 9, 2014 / Notices FERC regulation Date 1 Responsible party Pre-filing milestone FERC ............................... Mandatory Conditioning Agencies. Dispute Panel .................. Dispute Panel .................. Pennamaquan .................. Dispute Panel .................. Dispute Panel .................. FERC ............................... Pennamaquan .................. Pennamaquan .................. All stakeholders ............... Pennamaquan .................. All stakeholders ............... Director’s Study Plan Determination ..................... Any Study Disputes Due ....................................... 12/17/14 1/6/15 5.13(c) 5.14(a) Third Dispute Panel Member Selected ................. Dispute Resolution Panel Convenes .................... Applicant Comments on Study Disputes Due ....... Dispute Resolution Panel Technical Conference Dispute Resolution Panel Findings Issued ........... Director’s Study Dispute Determination ................ First Study Season ................................................ Initial Study Report ................................................ Initial Study Report Meeting .................................. Initial Study Report Meeting Summary ................. Any Disputes/Requests to Amend Study Plan Due. Responses to Disputes/Amendment Requests Due. Director’s Determination on Disputes/Amendments. 1/21/15 1/26/15 1/31/15 2/5/15 2/25/15 3/17/15 Spring/Summer 2015 12/17/15 1/1/16 1/16/16 2/15/16 5.14(d)(3) 5.14(d) 5.14(j) 5.14(j) 5.14(k) 5.14(l) 5.15(a) 5.15(c)(1) 5.15(c)(2) 5.15(c)(3) 5.15(c)(4) 3/16/16 5.15(c)(5) 4/15/16 5.15(c)(6) All stakeholders ............... FERC ............................... Second study season if necessary. Schedule would be adjusted accordingly. Pennamaquan .................. All stakeholders ............... File Preliminary Licensing Proposal (PLP) ........... PLP Comments Due ............................................. 12/14/16 3 3/14/17 5.16(a) 5.16(e) 1 If a due date falls on a weekend or holiday, the due date is the following business day. Dates prior to August 2014 are the dates when the events occurred, rather than due dates. 2 Commission staff issued a letter on June 5, 2014, requiring the proposed study plan meeting to be held between August 4, 2014, and August 19, 2014. Subsequent deadlines in the process plan were calculated from the deadline of August 19, 2014. 3 The date for filing of the PLP is a staff estimate. Dated: July 1, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–15997 Filed 7–8–14; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OPP–2014–0379; FRL–9912–90] Pesticide Experimental Use Permit; Receipt of Application; Comment Request Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: This notice announces EPA’s receipt of an application, 67760–EUP–R, from Cheminova, Inc., 160 Wilson Blvd., Suite 700, Arlington, VA 22209, requesting an experimental use permit (EUP) for the chemical Flutriafol. The Agency has determined that the permit may be of regional and national significance. Therefore, because of the potential significance, EPA is seeking comments on this application. DATES: Comments must be received on or before August 8, 2014. ADDRESSES: Submit your comments, identified by docket identification (ID) number EPA–HQ–OPP–2014–0379, by one of the following methods: sroberts on DSK5SPTVN1PROD with NOTICES SUMMARY: VerDate Mar<15>2010 20:08 Jul 08, 2014 Jkt 232001 • Federal eRulemaking Portal: https:// www.regulations.gov. Follow the online instructions for submitting comments. Do not submit electronically any information you consider to be Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. • Mail: OPP Docket, Environmental Protection Agency Docket Center (EPA/ DC), (28221T), 1200 Pennsylvania Ave. NW., Washington, DC 20460–0001. • Hand Delivery: To make special arrangements for hand delivery or delivery of boxed information, please follow the instructions at https:// www.epa.gov/dockets/contacts.html. Additional instructions on commenting or visiting the docket, along with more information about dockets generally, is available at https://www.epa.gov/dockets. FOR FURTHER INFORMATION CONTACT: Lois Rossi, Registration Division (7505P), Office of Pesticide Programs, Environmental Protection Agency, 1200 Pennsylvania Ave. NW., Washington, DC 20460–0001; main telephone number: (703) 305–7090; email address: RDFRNotices@epa.gov. SUPPLEMENTARY INFORMATION: I. General Information A. Does this action apply to me? This action is directed to the public in general. Although this action may be of particular interest to those persons PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 who conduct or sponsor research on pesticides, the Agency has not attempted to describe all the specific entities that may be affected by this action. B. What should I consider as I prepare my comments for EPA? 1. Submitting CBI. Do not submit this information to EPA through regulations.gov or email. Clearly mark the part or all of the information that you claim to be CBI. For CBI information in a disk or CD–ROM that you mail to EPA, mark the outside of the disk or CD–ROM as CBI and then identify electronically within the disk or CD–ROM the specific information that is claimed as CBI. In addition to one complete version of the comment that includes information claimed as CBI, a copy of the comment that does not contain the information claimed as CBI must be submitted for inclusion in the public docket. Information so marked will not be disclosed except in accordance with procedures set forth in 40 CFR part 2. 2. Tips for preparing your comments. When submitting comments, remember to: i. Identify the document by docket ID number and other identifying information (subject heading, Federal Register date and page number). ii. Follow directions. The Agency may ask you to respond to specific questions or organize comments by referencing a E:\FR\FM\09JYN1.SGM 09JYN1

Agencies

[Federal Register Volume 79, Number 131 (Wednesday, July 9, 2014)]
[Notices]
[Pages 38883-38884]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-15997]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13884-001]


Pennamaquan Tidal Power LLC; Notice of Initial Study Plan 
Meetings and Revised Process Plan

    On June 5, 2014, Commission staff issued a letter to Pennamaquan 
Tidal Power LLC (Pennamaquan Tidal) stating that Pennamaquan Tidal's 
proposed study plan for the Pennamaquan Tidal Power Plant Project (P-
13884) filed on December 12, 2013, meets the requirements of section 
5.11 of the Commission's regulations and that the Integrated Licensing 
Process (ILP) can resume. According to section 5.11(e) of the 
Commission's regulations, the next step in the ILP is the initial study 
plan meeting. In its June 5, 2014, letter, Commission staff indicated 
that the initial study plan meeting must be held within 75 days of, but 
no sooner than 60 days from, June 5, 2014. Accordingly, Pennamaquan 
Tidal has scheduled the meetings listed below:

Meetings in Bangor, ME

    Dates and Times: August 6 and 7, 2014. 8:00 a.m. to 5:00 p.m.
    Location: Maine Department of Environmental Protection, Eastern 
Maine Regional Office, 106 Hogan Road, Bangor, Maine 04401.
    Contact: Ramez Attiya, Pennamaquan Tidal, (281) 467-0846.

Meeting in Pembroke, ME

    Date and Time: August 8, 2014. 12:00 p.m. to 2:00 p.m.
    Location: Pembroke Town Office, 48 Old County Road, Pembroke, ME 
04666.
    Contact: Ramez Attiya, Pennamaquan Tidal, (281) 467-0846.
    A revised process plan that includes new dates for completing the 
ILP is provided below:

----------------------------------------------------------------------------------------------------------------
        Responsible party            Pre-filing milestone               Date \1\              FERC  regulation
----------------------------------------------------------------------------------------------------------------
Pennamaquan......................  Issue Public Notice for   7/19/12                        5.3(d)(2)
                                    NOI/PAD.
Pennamaquan......................  File NOI/PAD with FERC..  7/19/12                        5.5, 5.6
FERC.............................  Initiate Tribal           8/18/12                        5.7
                                    Consultation.
FERC.............................  Issue Notice of           9/14/12                        5.8
                                    Commencement of
                                    Proceeding; Scoping
                                    Document 1 (SD1).
FERC.............................  Project Environmental     10/25/12                       5.8(b)(viii)
                                    Site Review and Scoping  10/26/12
                                    Meetings.
All stakeholders.................  PAD/SD1 Comments and      12/4/12                        5.9
                                    Study Requests Due.
FERC.............................  Issue Scoping Document 2  1/18/13                        5.1
                                    (if needed).
Pennamaquan......................  File Proposed Study Plan  12/12/13                       5.11(a)
                                    (PSP).
All stakeholders.................  Proposed Study Plan       Between 8/4/14 and 8/19/14     5.11(e)
                                    Meeting (scheduled for    \2\
                                    8/6/14 to 8/8/14).
All stakeholders.................  Proposed Study Plan       10/18/14                       5.12
                                    Comments Due.
Pennamaquan......................  File Revised Study Plan.  11/17/14                       5.13(a)
All stakeholders.................  Revised Study Plan        12/2/14                        5.13(b)
                                    Comments Due.

[[Page 38884]]

 
FERC.............................  Director's Study Plan     12/17/14                       5.13(c)
                                    Determination.
Mandatory Conditioning Agencies..  Any Study Disputes Due..  1/6/15                         5.14(a)
Dispute Panel....................  Third Dispute Panel       1/21/15                        5.14(d)(3)
                                    Member Selected.
Dispute Panel....................  Dispute Resolution Panel  1/26/15                        5.14(d)
                                    Convenes.
Pennamaquan......................  Applicant Comments on     1/31/15                        5.14(j)
                                    Study Disputes Due.
Dispute Panel....................  Dispute Resolution Panel  2/5/15                         5.14(j)
                                    Technical Conference.
Dispute Panel....................  Dispute Resolution Panel  2/25/15                        5.14(k)
                                    Findings Issued.
FERC.............................  Director's Study Dispute  3/17/15                        5.14(l)
                                    Determination.
Pennamaquan......................  First Study Season......  Spring/Summer 2015             5.15(a)
Pennamaquan......................  Initial Study Report....  12/17/15                       5.15(c)(1)
All stakeholders.................  Initial Study Report      1/1/16                         5.15(c)(2)
                                    Meeting.
Pennamaquan......................  Initial Study Report      1/16/16                        5.15(c)(3)
                                    Meeting Summary.
All stakeholders.................  Any Disputes/Requests to  2/15/16                        5.15(c)(4)
                                    Amend Study Plan Due.
All stakeholders.................  Responses to Disputes/    3/16/16                        5.15(c)(5)
                                    Amendment Requests Due.
FERC.............................  Director's Determination  4/15/16                        5.15(c)(6)
                                    on Disputes/Amendments.
----------------------------------------------------------------------------------------------------------------
                    Second study season if necessary. Schedule would be adjusted accordingly.
----------------------------------------------------------------------------------------------------------------
Pennamaquan......................  File Preliminary          12/14/16 \3\                   5.16(a)
                                    Licensing Proposal
                                    (PLP).
All stakeholders.................  PLP Comments Due........  3/14/17                        5.16(e)
----------------------------------------------------------------------------------------------------------------
\1\ If a due date falls on a weekend or holiday, the due date is the following business day. Dates prior to
  August 2014 are the dates when the events occurred, rather than due dates.
\2\ Commission staff issued a letter on June 5, 2014, requiring the proposed study plan meeting to be held
  between August 4, 2014, and August 19, 2014. Subsequent deadlines in the process plan were calculated from the
  deadline of August 19, 2014.
\3\ The date for filing of the PLP is a staff estimate.


    Dated: July 1, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-15997 Filed 7-8-14; 8:45 am]
BILLING CODE 6717-01-P