Corpus Christi Liquefaction, LLC; Cheniere Corpus Christi Pipeline, LP; Notice of Availability of the Draft Environmental Impact Statement for the Proposed Corpus Christi LNG Project, 35344-35345 [2014-14375]
Download as PDF
35344
Federal Register / Vol. 79, No. 119 / Friday, June 20, 2014 / Notices
free at (866) 208–3676, or for TTY, (202)
502–8659.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
For further information contact Andy
Bernick at (202) 502–8660.
Dated: June 13, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–14374 Filed 6–19–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP12–507–000; CP12–508–
000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Corpus Christi Liquefaction, LLC;
Cheniere Corpus Christi Pipeline, LP;
Notice of Availability of the Draft
Environmental Impact Statement for
the Proposed Corpus Christi LNG
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a draft
environmental impact statement (EIS)
for the Corpus Christi LNG Project
(Project), proposed by Corpus Christi
Liquefaction, LLC and Cheniere Corpus
Christ Pipeline, LP (collectively
Cheniere) in the above-referenced
docket. Cheniere requests authorization
to construct and operate the facilities
necessary to import, export, store,
vaporize, and liquefy natural gas and
deliver the resulting product either into
existing interstate and intrastate natural
gas pipelines in the Corpus Christi area,
or export liquefied natural gas (LNG)
elsewhere.
The draft EIS assesses the potential
environmental effects of the
construction and operation of the
Project in accordance with the
requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that approval of
the proposed Project, with the
mitigation measures recommended in
the EIS, would ensure that impacts in
the Project area would be avoided or
minimized and would not be
significant. Construction and operation
of the Project would result in mostly
temporary and short-term
environmental impacts; however, some
long-term and permanent environmental
impacts would occur.
VerDate Mar<15>2010
22:31 Jun 19, 2014
Jkt 232001
The U.S. Army Corps of Engineers
(COE), U.S. Coast Guard, U.S.
Department of Energy (DOE), U.S.
Environmental Protection Agency
(EPA), and U.S. Department of
Transportation (DOT) participated as
cooperating agencies in the preparation
of the EIS. Cooperating agencies have
jurisdiction by law or special expertise
with respect to resources potentially
affected by the proposal and participate
in the NEPA analysis. The DOE will
adopt and use the EIS in issuing their
permit. The U.S. Coast Guard, EPA, and
DOT cooperated in the preparation of
this EIS because of their special
expertise with respect to resources
potentially affected by the proposal.
Although the cooperating agencies
provide input to the conclusions and
recommendations presented in the draft
EIS, the agencies will present their own
conclusions and recommendations in
their respective Records of Decision for
the Project.
The draft EIS addresses the potential
environmental effects of the
construction and operation of the
following Project facilities:
• Liquefaction facilities, including
three liquefaction trains capable of
producing 782 million British thermal
units (MMBtu) per year of LNG;
• vaporization facilities, including
two trains of ambient air vaporizers and
send out pumps capable of vaporizing
sufficient LNG volume for each to send
out 200 MMBtu per day of natural gas;
• LNG storage facilities, including
three LNG storage tanks each capable of
storing 160,000 cubic meters of LNG;
• marine terminal with two LNG
carrier berths;
• 23 miles of 42-inch-diameter
pipeline;
• one 41,000 horsepower compressor
station and one 12,260 horsepower
compressor station; and
• ancillary facilities.
The FERC staff mailed copies of the
draft EIS to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
newspapers and libraries in the Project
area; and parties to this proceeding.
Everyone on our environmental mailing
list will receive a CD version of the draft
EIS. In addition, the draft EIS is
available for public viewing on the
FERC’s Web site (www.ferc.gov) using
the eLibrary link. A limited number of
copies are available for distribution and
public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street NE.,
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
Room 2A, Washington, DC 20426, (202)
502–8371.
If you would like a hard copy of the
draft EIS, please contact the Public
Reference Room.
Any person wishing to comment on
the draft EIS may do so. To ensure
consideration of your comments on the
proposal in the final EIS, it is important
that the Commission receive your
comments before August 4, 2014.
For your convenience, there are four
methods you can use to submit your
comments to the Commission. In all
instances, please reference the Project
docket numbers (CP12–507–000 and
CP12–508–000) with your submission.
The Commission encourages electronic
filing of comments and has expert staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ If you are filing
a comment on a particular project,
please select ‘‘Comment on a Filing’’ as
the filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
(4) In lieu of sending written or
electronic comments, the Commission
invites you to attend the public
comment meeting its staff will conduct
in the Project area to receive comments
on the draft EIS. We encourage
interested groups and individuals to
attend and present oral comments on
the draft EIS. Transcripts of the
meetings will be available for review in
eLibrary under the Project docket
numbers. The meeting will begin at 7:00
p.m. and is scheduled as follows:
Date
Location
July 15, 2014 ....
Portland Community Center, 2000 Billy G Webb
Drive, Portland, TX
78374.
Any person seeking to become a party
to the proceeding must file a motion to
E:\FR\FM\20JNN1.SGM
20JNN1
Federal Register / Vol. 79, No. 119 / Friday, June 20, 2014 / Notices
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (18 CFR Part 385.214).1 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
The Commission grants affected
landowners and others with
environmental concerns intervenor
status upon showing good cause by
stating that they have a clear and direct
interest in this proceeding which no
other party can adequately represent.
Simply filing environmental comments
will not give you intervenor status, but
you do not need intervenor status to
have your comments considered.
Questions?
Additional information about the
Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search,’’ and enter the docket
number excluding the last three digits in
the Docket Number field (i.e., CP12–507
and CP12–508). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676; for TTY,
contact (202) 502–8659. The eLibrary
link also provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
docs-filing/esubscription.asp.
Dated: June 13, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–14375 Filed 6–19–14; 8:45 am]
mstockstill on DSK4VPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
1 See the previous discussion on the methods for
filing comments.
VerDate Mar<15>2010
22:31 Jun 19, 2014
Jkt 232001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP12–509–000; CP12–29–000]
Freeport LNG Development, L.P., FLNG
Liquefaction, LLC, FLNG Liquefaction
2, LLC, FLNG Liquefaction 3, LLC;
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed Phase II Modification and
Liquefaction Projects
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a final
Environmental Impact Statement (EIS)
for the Freeport LNG Phase II
Modification Project and the
Liquefaction Project (Projects) proposed
by Freeport LNG Development, L.P.,
FLNG Liquefaction LLC, FLNG
Liquefaction 2, LLC, and FLNG
Liquefaction 3, LLC (collectively
referred to as Freeport LNG) in the
above-referenced dockets. Freeport LNG
requests authorization to export up to
13.2 million tons of liquefied natural gas
(LNG) per year from its proposed
Liquefaction Plant and associated
facilities in Brazoria County, Texas and
modify its previously approved Phase II
Project facilities within the Town of
Quintana.
The final EIS assesses the potential
environmental effects of the
construction and operation of the
Projects in accordance with the
requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that approval of
the Projects would have some adverse
impacts; however, most of these impacts
would be reduced to less than
significant levels with the
implementation of Freeport LNG’s
proposed mitigation and the additional
measures recommended by the FERC
staff in the final EIS.
The United States Department of
Energy (USDOE), United States
Environmental Protection Agency
(USEPA), United States Department of
Transportation (USDOT), the United
States Army Corps of Engineers
(USACE), and the National Oceanic
Atmospheric Administration (NOAA)
Fisheries participated as cooperating
agencies in the preparation of the final
EIS. Cooperating agencies have
jurisdiction by law or special expertise
with respect to resources potentially
affected by the proposal and participate
in the NEPA analysis. The USACE,
USEPA, and USDOE can adopt and use
the EIS to support their respective
permit decisions after an independent
review of the document. The USDOT
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
35345
and NOAA Fisheries cooperated in the
preparation of this final EIS because of
their special expertise with respect to
resources potentially affected by the
proposal. Although the cooperating
agencies provided input on the
conclusions and recommendations
presented in the final EIS, the agencies
will present their own conclusions and
recommendations in their respective
Records of Decision or other
determinations for the Projects.
The proposed Phase II Modification
Project includes modification to the
previously authorized, but not
constructed, LNG vessel berthing dock,
LNG transfer pipelines, LNG unloading
arms; and the access road system. In
addition, Freeport LNG would either
eliminate or modify components of the
previously authorized facility.
The Liquefaction Project consists of
multiple components, including
facilities at and adjacent to the existing
Quintana Island terminal and facilities
located beyond Quintana Island. The
Liquefaction Plant, located at and
adjacent to the existing Quintana Island
terminal, would consist of three
propane pre-cooled mixed refrigerant
liquefaction trains, each capable of
producing a nominal 4.4 million metric
tons per annum of LNG for export,
which equates to a total liquefaction
capacity of approximately 1.8 billion
cubic feet per day of natural gas.
To support the Liquefaction Plant,
Freeport LNG proposes to construct a
natural gas Pretreatment Plant located
about 2.5 miles north of the existing
Quintana Island terminal. The
Pretreatment Plant would process the
gas for liquefaction. In addition several
interconnecting pipelines and utility
lines including a five-mile-long, 12inch-diameter boil-off gas feed pipeline
from the Quintana Island terminal to the
Pretreatment Plant (referred together as
the Pipeline/Utility Line System). The
Liquefaction Plant, the Pretreatment
Plant, and the Pipeline/Utility Line
System, together with the associated
appurtenant structures, are collectively
referred to as the Liquefaction Project.
The FERC staff mailed copies of the
EIS to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
newspapers and libraries in the project
area; and parties to this proceeding.
Paper copy versions of this EIS were
mailed to those specifically requesting
them; all others received a CD version.
In addition, the EIS is available for
public viewing on the FERC’s Web site
E:\FR\FM\20JNN1.SGM
20JNN1
Agencies
[Federal Register Volume 79, Number 119 (Friday, June 20, 2014)]
[Notices]
[Pages 35344-35345]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-14375]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP12-507-000; CP12-508-000]
Corpus Christi Liquefaction, LLC; Cheniere Corpus Christi
Pipeline, LP; Notice of Availability of the Draft Environmental Impact
Statement for the Proposed Corpus Christi LNG Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a draft environmental impact statement (EIS)
for the Corpus Christi LNG Project (Project), proposed by Corpus
Christi Liquefaction, LLC and Cheniere Corpus Christ Pipeline, LP
(collectively Cheniere) in the above-referenced docket. Cheniere
requests authorization to construct and operate the facilities
necessary to import, export, store, vaporize, and liquefy natural gas
and deliver the resulting product either into existing interstate and
intrastate natural gas pipelines in the Corpus Christi area, or export
liquefied natural gas (LNG) elsewhere.
The draft EIS assesses the potential environmental effects of the
construction and operation of the Project in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the proposed Project, with the
mitigation measures recommended in the EIS, would ensure that impacts
in the Project area would be avoided or minimized and would not be
significant. Construction and operation of the Project would result in
mostly temporary and short-term environmental impacts; however, some
long-term and permanent environmental impacts would occur.
The U.S. Army Corps of Engineers (COE), U.S. Coast Guard, U.S.
Department of Energy (DOE), U.S. Environmental Protection Agency (EPA),
and U.S. Department of Transportation (DOT) participated as cooperating
agencies in the preparation of the EIS. Cooperating agencies have
jurisdiction by law or special expertise with respect to resources
potentially affected by the proposal and participate in the NEPA
analysis. The DOE will adopt and use the EIS in issuing their permit.
The U.S. Coast Guard, EPA, and DOT cooperated in the preparation of
this EIS because of their special expertise with respect to resources
potentially affected by the proposal. Although the cooperating agencies
provide input to the conclusions and recommendations presented in the
draft EIS, the agencies will present their own conclusions and
recommendations in their respective Records of Decision for the
Project.
The draft EIS addresses the potential environmental effects of the
construction and operation of the following Project facilities:
Liquefaction facilities, including three liquefaction
trains capable of producing 782 million British thermal units (MMBtu)
per year of LNG;
vaporization facilities, including two trains of ambient
air vaporizers and send out pumps capable of vaporizing sufficient LNG
volume for each to send out 200 MMBtu per day of natural gas;
LNG storage facilities, including three LNG storage tanks
each capable of storing 160,000 cubic meters of LNG;
marine terminal with two LNG carrier berths;
23 miles of 42-inch-diameter pipeline;
one 41,000 horsepower compressor station and one 12,260
horsepower compressor station; and
ancillary facilities.
The FERC staff mailed copies of the draft EIS to federal, state,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American tribes;
potentially affected landowners and other interested individuals and
groups; newspapers and libraries in the Project area; and parties to
this proceeding. Everyone on our environmental mailing list will
receive a CD version of the draft EIS. In addition, the draft EIS is
available for public viewing on the FERC's Web site (www.ferc.gov)
using the eLibrary link. A limited number of copies are available for
distribution and public inspection at: Federal Energy Regulatory
Commission, Public Reference Room, 888 First Street NE., Room 2A,
Washington, DC 20426, (202) 502-8371.
If you would like a hard copy of the draft EIS, please contact the
Public Reference Room.
Any person wishing to comment on the draft EIS may do so. To ensure
consideration of your comments on the proposal in the final EIS, it is
important that the Commission receive your comments before August 4,
2014.
For your convenience, there are four methods you can use to submit
your comments to the Commission. In all instances, please reference the
Project docket numbers (CP12-507-000 and CP12-508-000) with your
submission. The Commission encourages electronic filing of comments and
has expert staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
(4) In lieu of sending written or electronic comments, the
Commission invites you to attend the public comment meeting its staff
will conduct in the Project area to receive comments on the draft EIS.
We encourage interested groups and individuals to attend and present
oral comments on the draft EIS. Transcripts of the meetings will be
available for review in eLibrary under the Project docket numbers. The
meeting will begin at 7:00 p.m. and is scheduled as follows:
------------------------------------------------------------------------
Date Location
------------------------------------------------------------------------
July 15, 2014......................... Portland Community Center, 2000
Billy G Webb Drive, Portland,
TX 78374.
------------------------------------------------------------------------
Any person seeking to become a party to the proceeding must file a
motion to
[[Page 35345]]
intervene pursuant to Rule 214 of the Commission's Rules of Practice
and Procedures (18 CFR Part 385.214).\1\ Only intervenors have the
right to seek rehearing of the Commission's decision. The Commission
grants affected landowners and others with environmental concerns
intervenor status upon showing good cause by stating that they have a
clear and direct interest in this proceeding which no other party can
adequately represent. Simply filing environmental comments will not
give you intervenor status, but you do not need intervenor status to
have your comments considered.
---------------------------------------------------------------------------
\1\ See the previous discussion on the methods for filing
comments.
---------------------------------------------------------------------------
Questions?
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search,'' and enter the docket number
excluding the last three digits in the Docket Number field (i.e., CP12-
507 and CP12-508). Be sure you have selected an appropriate date range.
For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676; for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to https://www.ferc.gov/docs-filing/esubscription.asp.
Dated: June 13, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-14375 Filed 6-19-14; 8:45 am]
BILLING CODE 6717-01-P