Questar Overthrust Pipeline Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Jurisdictional Tap Line 139 Delivery Project and Request for Comments on Environmental Issues, 33746-33748 [2014-13696]
Download as PDF
33746
Federal Register / Vol. 79, No. 113 / Thursday, June 12, 2014 / Notices
Scoping Meetings and Environmental
Site Review
OSU and the Commission staff will
hold two scoping meetings, one in the
daytime and one in the evening, to help
us identify the scope of issues to be
addressed in the APEA.
The daytime scoping meeting will
focus on resource agency concerns,
while the evening scoping meeting is
primarily for public input. All
interested individuals, organizations,
and agencies are invited to attend one
or both of the meetings, and to assist the
staff in identifying the environmental
issues that should be analyzed in the
APEA. The times and locations of these
meetings and environmental site review
are as follows:
Daytime Meeting
Wednesday, July 9, 2014
1:00 p.m.
Hatfield Marine Science Center
Guin Library (Seminar Room)
2121 SE Marine Science Drive
Newport, Oregon 97365
Evening Meeting
Wednesday, July 9, 2014
7:00 p.m.
Hatfield Marine Science Center
Visitor Center Auditorium
2030 SE Marine Science Drive
Newport, Oregon 97365
rmajette on DSK7SPTVN1PROD with NOTICES
Environmental Site Review
Thursday, July 10, 2014
Ona Beach State Park
Day Use Beach Parking Lot (west of
Hwy. 101)
Oregon Coast Highway
Waldport, Oregon 97376
Please notify Brenda Langley at
brenda.langley@oregonstate.edu or
(541) 737–6138 by June 25, 2014, if you
plan to attend the site visit.
To help focus discussions, Scoping
Document 1 (SD1) was mailed by OSU
on June 5, 2014, outlining the subject
areas to be addressed in the APEA, to
the parties on the mailing list. Copies of
the SD1 also will be available at the
scoping meetings. OSU will file SD1
with the Commission and the document
will be available for review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
VerDate Mar<15>2010
21:18 Jun 11, 2014
Jkt 232001
For assistance, contact
FERCONlineSupport@ferc.gov.
Based on all written comments
received, a Scoping Document 2 (SD2)
may be issued. SD2 will include a
revised list of issues, based on the
scoping sessions.
Objectives
At the scoping meetings, OSU and
Commission staff will: (1) Summarize
the environmental issues tentatively
identified for analysis in the APEA; (2)
solicit from the meeting participants all
available information, especially
quantifiable data, on the resources at
issue; (3) encourage statements from
experts and the public on issues that
should be analyzed in the APEA,
including viewpoints in opposition to,
or in support of, the OSU and
Commission staff’s preliminary views;
(4) determine the resource issues to be
addressed in the APEA; and (5) identify
those issues that require a detailed
analysis, as well as those issues that do
not require a detailed analysis.
Procedures
The meetings will be recorded by a
stenographer and will become part of
the formal record of the Commission
proceeding on the project.
Individuals, organizations, and
agencies with environmental expertise
and concerns are encouraged to attend
the meetings and to assist OSU in
defining and clarifying the issues to be
addressed in the APEA.
Dated: May 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–13700 Filed 6–11–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–123–000]
Questar Overthrust Pipeline Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Jurisdictional Tap Line 139
Delivery Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Jurisdictional Tap Line (JTL) 139
Delivery Project (Project) involving
construction and operation of facilities
by Questar Overthrust Pipeline
Company (Questar) in Sweetwater
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
County, Wyoming. The Commission
will use this EA in its decision-making
process to determine whether the
Project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on July 7,
2014.
You may submit comments in written
form. Further details on how to submit
written comments are in the Public
Participation section of this notice.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this
proposed Project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the Project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Questar provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically-asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
Summary of the Proposed Project
Questar proposes to construct and
operate a new pipeline between
Questar’s existing Mainline 116 Pipeline
and a new ammonia plant to be built,
owned, and operated by Simplot
Phosphates, LLC (Simplot). The JTL 139
Delivery Project would provide about
19.4 million standard cubic feet (20,000
dekatherms) and potentially up to 58.2
million standard cubic feet (60,000
dekatherms) of natural gas per day to
Simplot’s ammonia plant.
The JTL139 Delivery Project would
consist of the following facilities:
E:\FR\FM\12JNN1.SGM
12JNN1
Federal Register / Vol. 79, No. 113 / Thursday, June 12, 2014 / Notices
• The JTL139 Pipeline: 8 inches in
diameter and 2.54 miles long;
• a tap located at milepost (MP) 0.0;
and
• a District Regulator Station at MP
2.54.
The general location of the Project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 30 acres of land for
the aboveground facilities and the
pipeline. Following construction,
Questar would maintain about 23 acres
for permanent operation of the Project’s
facilities; all remaining acreage affected
by construction would be restored and
revert to former uses.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. The NEPA also requires us 2
to discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed Project under these general
headings:
• Geology and soils;
• land use, recreation, and visual
impacts;
• water resources and wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise; and
• public safety and pipeline
reliability.
We will also evaluate reasonable
alternatives to the proposed Project or
portions of the Project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
rmajette on DSK7SPTVN1PROD with NOTICES
1 The
appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 The pronouns ‘‘we,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Mar<15>2010
21:18 Jun 11, 2014
Jkt 232001
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary.3 Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section of
this notice.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.4 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultations with the
Wyoming State Historic Preservation
Office (SHPO), and to solicit its views,
and those of other government agencies,
interested Indian tribes, and the public
on the Project’s potential effects on
historic properties.5 We will define the
Project-specific area of potential effects
(APE) in consultation with the SHPO as
the Project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
Project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
3 Instructions for using eLibrary can be found in
the Additional Information section of this notice.
4 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
5 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
33747
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before July 7,
2014.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the Project
docket number (CP14–123–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You can file your comments
electronically using the eFiling feature
on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials; regional
environmental groups and nongovernmental organizations; potentially
interested Indian tribes; other interested
parties; and local libraries and
newspapers. This list also includes all
affected landowners (as defined in the
Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
Project purposes, or who own homes
E:\FR\FM\12JNN1.SGM
12JNN1
33748
Federal Register / Vol. 79, No. 113 / Thursday, June 12, 2014 / Notices
within certain distances of aboveground
facilities, and anyone who submits
comments on the Project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the compact disc version or would like
to remove your name from the mailing
list, please return the attached
Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site.
rmajette on DSK7SPTVN1PROD with NOTICES
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP14–123). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
docs-filing/esubscription.asp.
VerDate Mar<15>2010
21:18 Jun 11, 2014
Jkt 232001
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: June 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–13696 Filed 6–11–14; 8:45 am]
BILLING CODE 6717–01–P
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on June 20, 2014.
Dated: June 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–13697 Filed 6–11–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Docket No. EF14–8–000]
Federal Energy Regulatory
Commission
Western Area Power Administration;
Notice of Filing
[Docket No. EF14–9–000]
Take notice that on May 21, 2014, the
Western Area Power Administration
submitted a tariff filing per 300.10:
WAPA–163 WestConnect–20140519 to
be effective 6/1/2014, concerning
Formula Rates for Western
Transmission Projects to use under the
WestConnect Point-to-Point Regional
Transmission Service Participation
Agreement.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
Western Area Power Administration;
Notice of Filing
Take notice that on May 28, 2014, the
Western Area Power Administration
submitted a tariff filing per 300.10:
CRSP_FA_WAPA164–20140527 to be
effective 6/8/2014, concerning Falcon
Amistad Formula Rate Extension.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
E:\FR\FM\12JNN1.SGM
12JNN1
Agencies
[Federal Register Volume 79, Number 113 (Thursday, June 12, 2014)]
[Notices]
[Pages 33746-33748]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-13696]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-123-000]
Questar Overthrust Pipeline Company; Notice of Intent To Prepare
an Environmental Assessment for the Proposed Jurisdictional Tap Line
139 Delivery Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Jurisdictional Tap Line (JTL)
139 Delivery Project (Project) involving construction and operation of
facilities by Questar Overthrust Pipeline Company (Questar) in
Sweetwater County, Wyoming. The Commission will use this EA in its
decision-making process to determine whether the Project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on July 7, 2014.
You may submit comments in written form. Further details on how to
submit written comments are in the Public Participation section of this
notice.
This notice is being sent to the Commission's current environmental
mailing list for this Project. State and local government
representatives should notify their constituents of this proposed
Project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Questar provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
Questar proposes to construct and operate a new pipeline between
Questar's existing Mainline 116 Pipeline and a new ammonia plant to be
built, owned, and operated by Simplot Phosphates, LLC (Simplot). The
JTL 139 Delivery Project would provide about 19.4 million standard
cubic feet (20,000 dekatherms) and potentially up to 58.2 million
standard cubic feet (60,000 dekatherms) of natural gas per day to
Simplot's ammonia plant.
The JTL139 Delivery Project would consist of the following
facilities:
[[Page 33747]]
The JTL139 Pipeline: 8 inches in diameter and 2.54 miles
long;
a tap located at milepost (MP) 0.0; and
a District Regulator Station at MP 2.54.
The general location of the Project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 30
acres of land for the aboveground facilities and the pipeline.
Following construction, Questar would maintain about 23 acres for
permanent operation of the Project's facilities; all remaining acreage
affected by construction would be restored and revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. The NEPA also requires
us \2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ The pronouns ``we,'' ``us,'' and ``our'' refer to the
environmental staff of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed Project under these
general headings:
Geology and soils;
land use, recreation, and visual impacts;
water resources and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise; and
public safety and pipeline reliability.
We will also evaluate reasonable alternatives to the proposed
Project or portions of the Project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary.\3\ Depending
on the comments received during the scoping process, we may also
publish and distribute the EA to the public for an allotted comment
period. We will consider all comments on the EA before making our
recommendations to the Commission. To ensure we have the opportunity to
consider and address your comments, please carefully follow the
instructions in the Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ Instructions for using eLibrary can be found in the
Additional Information section of this notice.
---------------------------------------------------------------------------
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\4\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\4\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultations
with the Wyoming State Historic Preservation Office (SHPO), and to
solicit its views, and those of other government agencies, interested
Indian tribes, and the public on the Project's potential effects on
historic properties.\5\ We will define the Project-specific area of
potential effects (APE) in consultation with the SHPO as the Project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this Project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before July
7, 2014.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the Project docket number (CP14-123-000) with your
submission. The Commission encourages electronic filing of comments and
has expert staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials; regional
environmental groups and non-governmental organizations; potentially
interested Indian tribes; other interested parties; and local libraries
and newspapers. This list also includes all affected landowners (as
defined in the Commission's regulations) who are potential right-of-way
grantors, whose property may be used temporarily for Project purposes,
or who own homes
[[Page 33748]]
within certain distances of aboveground facilities, and anyone who
submits comments on the Project. We will update the environmental
mailing list as the analysis proceeds to ensure that we send the
information related to this environmental review to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the compact
disc version or would like to remove your name from the mailing list,
please return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP14-
123). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: June 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-13696 Filed 6-11-14; 8:45 am]