Notice of Availability of the Final Environmental Impact Statement for the Proposed Right-of-Way Amendment for the Blythe Solar Power Project, California, 31133-31134 [2014-12572]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 79, No. 104 / Friday, May 30, 2014 / Notices
Backfilling into the pit is limited due to
existing topography constraints, rehandling issues, and safety concerns
when backfilling and mining
concurrently within Panel G’s pit
configuration. The lease modification is
necessary to accommodate all of the
overburden generated from mining
Panel G, as analyzed in the 2007 Final
EIS. At the time the RODs for the 2007
Final EIS were issued, neither the BLM
nor the USFS had the regulatory
authority to approve Simplot’s original
plan for overburden storage. In 2009, the
rules were modified giving the BLM
authority to approve a lease
modification for the purpose of
overburden storage.
Regional mitigation strategies for
cumulative effects from phosphate
mining to wildlife habitat are currently
being developed in the Pocatello Field
Office. Although regional mitigation
will not be applied in this case because
the proposed action would not result in
impacts drastically different than those
from the existing mine plan already
approved in 2008 (evaluated as the No
Action Alternative in the Draft EIS), onsite mitigation is proposed to reduce
water quality effects. For example, to
further reduce or eliminate water
quality impacts due to increasing the
size of the currently approved mine,
Simplot is proposing to cover all
seleniferous overburden in Panel G with
a GCLL. They feel it is in the best
interest of increased long-term
environmental protection and may lend
itself to a more expeditious review of
the proposed modifications. In addition,
Simplot is proposing storm water
control features to address surface water
run-off from the proposed GCLL. It is
estimated that up to 11 acres of new
disturbance would be necessary for
these storm water features. Portions of
these features would be situated on
lease, within the proposed lease
modification area, or off lease. Off-lease
disturbance would require USFS special
use authorization.
In total, approximately 170 acres are
proposed for new disturbance.
Compared to what was analyzed in the
2007 Final EIS, there would be an
additional 8 acres disturbed for the ore
conveyor system (mostly at the north
end of Panel F); 20 acres for the Panel
G south ODA expansion of temporary
chert storage; up to 11 acres for storm
water control features to address run-off
from the GCLL at Panel G; and 131 acres
for the Panel G east seleniferous ODA
expansion.
Two additional Action Alternatives
were developed to address concerns
raised during public scoping about the
long term durability and use of a
VerDate Mar<15>2010
18:23 May 29, 2014
Jkt 232001
synthetic liner such as a GCLL at Panel
G and/or reducing the amount of new
disturbance within the Inventoried
Roadless Area (IRA). Alternatives 1 and
2 would include all components of the
Proposed Action, but would limit use of
the GCLL by utilizing the previously
approved geologic cover on portions of
the disturbed areas. In addition,
Alternative 2 would reduce the east
ODA expansion within the Sage Creek
IRA by approximately 45 acres and
reduce the proposed lease modification
area by approximately 40 acres.
Under the No Action Alternative in
the Draft EIS, the proposed lease and
mine plan modifications and special use
authorizations would not be approved,
and mining would continue under the
current mine plan as approved by the
2008 RODs. Under the No Action
Alternative, Simplot estimates that
approximately 50 percent of the
phosphate ore in Panel G, previously
considered economically recoverable,
would not be mined but the overall
disturbance would remain unchanged
from the 2008 mine plan approval. In
addition, the proposed conveyor system
would not be approved, thus no new
disturbance associated with the
conveyor would occur. The previously
approved geologic cover would be used
to limit or prevent the release of
contaminants to the environment.
A Notice of Intent (NOI) to prepare
this EIS was published in the Federal
Register on June 24, 2013. Publication
of the NOI in the Federal Register
initiated a 30-day public scoping period
for the Proposed Action that provided
for acceptance of written comments.
The scoping process identified concerns
that primarily involved impacts to water
resources and watersheds, and
selenium, but also include potential
effects and/or cumulative effects of the
proposed project on Inventoried
Roadless Areas, wetlands, climate
change, socioeconomics, visual
resources, and mitigation and
monitoring for mine operations.
To facilitate understanding and
comments on the Draft EIS, public
meetings are planned to be held in
Afton, Wyoming, and Pocatello and Fort
Hall, Idaho. Meetings will be openhouse style, with displays explaining
the project and a forum for commenting
on the project. The dates, times, and
locations of the public scoping meetings
will be announced in mailings and
public notices issued by the BLM.
Written and electronic comments
regarding the Draft EIS should be
submitted within 45 days of the date of
publication of the Environmental
Protection Agency’s Notice of
Availability in the Federal Register. To
PO 00000
Frm 00056
Fmt 4703
Sfmt 4703
31133
assist the BLM and the USFS in
identifying issues and concerns related
to this project, comments should be as
specific as possible. The portion of the
proposed project related to special use
authorizations for off-lease activities is
subject to the objection process
pursuant to 36 CFR part 218 Subparts A
and B. Only those who provide
comment during this comment period or
who have previously submitted specific
written comments on the Proposed
Action, either during scoping or other
designated opportunity for public
comment, will be eligible as objectors
(36 CFR 218.5). BLM appeal procedures
found in 43 CFR part 4 apply to the
portion of the project related to the
Federal mineral lease(s).
Please note that public comments and
information submitted including names,
street addresses, and email addresses of
respondents will be available for public
review and disclosure at the above BLM
address during regular business hours (8
a.m. to 4 p.m.), Monday through Friday,
except holidays.
Before including your phone number,
email address, or other personal
identifying information in your
comment, you should be aware that
your entire comment—including your
personal identifying information—may
be made publicly available at any time.
While you can ask us in your comment
to withhold your personal identifying
information from public review, we
cannot guarantee that we will be able to
do so.
Authority: 42 U.S.C. 4321 et seq.; 40 CFR
parts 1500–1508; 43 CFR part 46; 43 U.S.C.
1701; and 43 CFR part 3590.
Joe Kraayenbrink,
District Manager, Idaho Falls District, Bureau
of Land Management.
Brent Larson,
Forest Supervisor, Caribou-Targhee National
Forest.
[FR Doc. 2014–12543 Filed 5–29–14; 8:45 am]
BILLING CODE 4310–GG–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[CACA 048811, LLCAD01500,
L51010000.ER0000.14X.LVRWB14B5340]
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed Right-of-Way
Amendment for the Blythe Solar Power
Project, California
Bureau of Land Management,
Interior.
ACTION: Notice of availability.
AGENCY:
E:\FR\FM\30MYN1.SGM
30MYN1
31134
Federal Register / Vol. 79, No. 104 / Friday, May 30, 2014 / Notices
In accordance with the
National Environmental Policy Act of
1969, as amended (NEPA), and the
Federal Land Policy and Management
Act of 1976, as amended (FLPMA), the
Bureau of Land Management (BLM) has
prepared a Final Environmental Impact
Statement (EIS) for the proposed rightof-way (ROW) amendment for the
Blythe Solar Power Project (BSPP),
Riverside County, California, and by
this notice is announcing its
availability.
DATES: The BLM will not issue a final
decision on the proposed ROW
amendment for a minimum of 30 days
after the date that the Environmental
Protection Agency publishes its Notice
of Availability in the Federal Register.
ADDRESSES: Copies of the Final EIS have
been sent to affected Federal, State, and
local government agencies, and to other
stakeholders. Copies of the Final EIS are
available for public inspection at the
Palm Springs/South Coast Field Office,
1201 Bird Center Drive, Palm Springs,
CA 92262 and the California Desert
District Office, 22835 Calle San Juan de
Los Lagos, Moreno Valley, CA 92553–
9046. Interested persons also may
review the Final EIS on the Internet at
https://www.blm.gov/ca/st/en/fo/
palmsprings/Solar_Projects/Blythe_
Solar_Power_Project.html.
FOR FURTHER INFORMATION CONTACT:
Frank McMenimen, BLM Project
Manager, telephone 760–833–7150;
address 1201 Bird Center Drive, Palm
Springs, CA 92262; email
capssolarblythe@blm.gov. Persons who
use a telecommunications device for the
deaf (TDD) may call the Federal
Information Relay Service (FIRS) at 1–
800–877–8339 to contact Mr.
McMenimen during normal business
hours. The FIRS is available 24 hours a
day, 7 days a week to leave a message
or question for Mr. McMenimen. You
will receive a reply during normal
business hours.
SUPPLEMENTARY INFORMATION: The
project area is located 8 miles west of
Blythe and 3 miles north of Interstate 10
(I–10). The BSPP originally was
permitted and approved in 2010 as a
1,000-megawatt (MW) solar thermal
generating plant occupying 6,831 acres
(Approved Project). On August 22, 2012,
the BLM approved the assignment of the
ROW Grant from the prior holder, Palo
Verde Solar I, LLC, to NextEra Blythe
Solar Energy, LLC (Grant Holder). The
Grant Holder purchased via bankruptcy
the (un-built) project assets in mid-2012
from Palo Verde Solar I, LLC. The Grant
Holder then requested a Level 3
variance to the existing Approved
Project’s ROW grant. The Grant Holder
mstockstill on DSK4VPTVN1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
18:23 May 29, 2014
Jkt 232001
is proposing to construct, operate,
maintain, and decommission the BSPP
using photovoltaic (PV) technology with
a 485–MW capacity on 4,138 acres of
BLM-administered public land.
To support this proposal, a request to
amend the existing ROW authorization
has been submitted to reduce the
acreage of the project, change the
technology from concentrating solar
trough to PV, adjust the project layout
in response to the new generation
technology and reduce the project’s
capacity from 1,000 to 485 MWs. These
proposed changes are referred to in the
Final EIS as the Modified Project. In
anticipation of the Modified Project, the
Grant Holder voluntarily relinquished
approximately 35 percent of the
previously approved ROW grant area on
March 7, 2013.
The Final EIS fully analyzes the Grant
Holder’s proposal to construct, operate,
maintain, and decommission the
Modified Project (Alternative 1), as well
as the BLM’s denial of the variance
request, which would maintain the
current ROW grant approvals on the site
as modified by the Grant Holder’s
voluntary relinquishment mentioned
above (Alternative 2, No Action). The
Final EIS does not supersede or replace
the 2010 Proposed Plan Amendment/
Final EIS or other elements of the 2010
Approved Project or Plan Amendment,
but rather tiers to those documents as
appropriate. The Final EIS analyzes the
use of PV technology in detail,
including any additional site-specific
impacts resulting from the change in
technology and additional or relocated
ancillary facilities. This includes
impacts to air quality, biological
resources, climate change, cultural
resources, hazards and public health,
lands and realty, mineral resources,
noise, paleontological resources,
recreation and special designations,
socioeconomics and environmental
justice, soil resources, traffic and travel
management, visual resources, water
resources, and wildland fire ecology.
A number of measures would be
implemented to avoid, minimize,
rectify, reduce, or compensate for
adverse impacts of the Modified Project.
These include:
• Biological Resources: Wildlife
would be avoided or relocated (e.g.,
desert tortoise) to the extent feasible
through fencing, clearance surveys, and
relocation/translocation. The Grant
Holder also proposes to implement a
Raven Management Plan, Weed
Management Plan, Bird and Bat
Conservation Strategy, and golden eagle
inventory and monitoring. The Grant
Holder has also proposed off-site
PO 00000
Frm 00057
Fmt 4703
Sfmt 9990
compensatory mitigation to minimize or
offset impacts to biological resources.
• Cultural Resources: The Grant
Holder proposes to employ cultural
resource specialists as monitors during
ground disturbance, and to implement
long-term protection measures.
• Hazards and Visual Resources: The
Grant Holder proposes to document,
investigate, evaluate, and attempt to
resolve all project-related glare
complaints throughout the construction
and operation of the project; to use
textured glass or anti-reflective coating
on all solar panels; and to construct all
exposed PV panel support structures
with matte or non-reflective surfaces.
• Water Resources: Site hydrology
would be designed to retain pre-project
flows on the majority of the site, and the
Grant Holder would implement a
Groundwater Level Monitoring,
Mitigation, and Reporting Plan.
The BLM has conducted Native
American tribal consultations in
accordance with Section 106 of the
National Historic Preservation Act and
Federal policy in connection with the
previously approved BSPP, which
resulted in the development of a
Programmatic Agreement. During that
process, tribes expressed their views
and concerns about the importance and
sensitivity of specific cultural resources
to which they attach religious and
cultural significance. The BLM has
amended the Programmatic Agreement,
consistent with its terms, in response to
the Modified Project. In connection with
its review of the Modified Project, the
BLM will carry out its responsibilities to
consult with tribes on a government-togovernment basis and other members of
the public pursuant to the existing
Programmatic Agreement, as amended,
and other authorities to the extent
applicable and will continue to give
tribal concerns due consideration,
including impacts to historic properties
to which tribes attach religious and
cultural significance and Indian trust
assets.
Comments on the Draft EIS received
from the public and based on internal
BLM review were considered and
incorporated as appropriate into the
Final EIS. Public comments resulted in
the addition of clarifying text, but did
not significantly change the substantive
analysis within the Final EIS.
Authority: 40 CFR 1506.6 & 1506.10.
Thomas Pogacnik,
Deputy State Director.
[FR Doc. 2014–12572 Filed 5–29–14; 8:45 am]
BILLING CODE 4310–40–P
E:\FR\FM\30MYN1.SGM
30MYN1
Agencies
[Federal Register Volume 79, Number 104 (Friday, May 30, 2014)]
[Notices]
[Pages 31133-31134]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-12572]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[CACA 048811, LLCAD01500, L51010000.ER0000.14X.LVRWB14B5340]
Notice of Availability of the Final Environmental Impact
Statement for the Proposed Right-of-Way Amendment for the Blythe Solar
Power Project, California
AGENCY: Bureau of Land Management, Interior.
ACTION: Notice of availability.
-----------------------------------------------------------------------
[[Page 31134]]
SUMMARY: In accordance with the National Environmental Policy Act of
1969, as amended (NEPA), and the Federal Land Policy and Management Act
of 1976, as amended (FLPMA), the Bureau of Land Management (BLM) has
prepared a Final Environmental Impact Statement (EIS) for the proposed
right-of-way (ROW) amendment for the Blythe Solar Power Project (BSPP),
Riverside County, California, and by this notice is announcing its
availability.
DATES: The BLM will not issue a final decision on the proposed ROW
amendment for a minimum of 30 days after the date that the
Environmental Protection Agency publishes its Notice of Availability in
the Federal Register.
ADDRESSES: Copies of the Final EIS have been sent to affected Federal,
State, and local government agencies, and to other stakeholders. Copies
of the Final EIS are available for public inspection at the Palm
Springs/South Coast Field Office, 1201 Bird Center Drive, Palm Springs,
CA 92262 and the California Desert District Office, 22835 Calle San
Juan de Los Lagos, Moreno Valley, CA 92553-9046. Interested persons
also may review the Final EIS on the Internet at https://www.blm.gov/ca/st/en/fo/palmsprings/Solar_Projects/Blythe_Solar_Power_Project.html.
FOR FURTHER INFORMATION CONTACT: Frank McMenimen, BLM Project Manager,
telephone 760-833-7150; address 1201 Bird Center Drive, Palm Springs,
CA 92262; email capssolarblythe@blm.gov. Persons who use a
telecommunications device for the deaf (TDD) may call the Federal
Information Relay Service (FIRS) at 1-800-877-8339 to contact Mr.
McMenimen during normal business hours. The FIRS is available 24 hours
a day, 7 days a week to leave a message or question for Mr. McMenimen.
You will receive a reply during normal business hours.
SUPPLEMENTARY INFORMATION: The project area is located 8 miles west of
Blythe and 3 miles north of Interstate 10 (I-10). The BSPP originally
was permitted and approved in 2010 as a 1,000-megawatt (MW) solar
thermal generating plant occupying 6,831 acres (Approved Project). On
August 22, 2012, the BLM approved the assignment of the ROW Grant from
the prior holder, Palo Verde Solar I, LLC, to NextEra Blythe Solar
Energy, LLC (Grant Holder). The Grant Holder purchased via bankruptcy
the (un-built) project assets in mid-2012 from Palo Verde Solar I, LLC.
The Grant Holder then requested a Level 3 variance to the existing
Approved Project's ROW grant. The Grant Holder is proposing to
construct, operate, maintain, and decommission the BSPP using
photovoltaic (PV) technology with a 485-MW capacity on 4,138 acres of
BLM-administered public land.
To support this proposal, a request to amend the existing ROW
authorization has been submitted to reduce the acreage of the project,
change the technology from concentrating solar trough to PV, adjust the
project layout in response to the new generation technology and reduce
the project's capacity from 1,000 to 485 MWs. These proposed changes
are referred to in the Final EIS as the Modified Project. In
anticipation of the Modified Project, the Grant Holder voluntarily
relinquished approximately 35 percent of the previously approved ROW
grant area on March 7, 2013.
The Final EIS fully analyzes the Grant Holder's proposal to
construct, operate, maintain, and decommission the Modified Project
(Alternative 1), as well as the BLM's denial of the variance request,
which would maintain the current ROW grant approvals on the site as
modified by the Grant Holder's voluntary relinquishment mentioned above
(Alternative 2, No Action). The Final EIS does not supersede or replace
the 2010 Proposed Plan Amendment/Final EIS or other elements of the
2010 Approved Project or Plan Amendment, but rather tiers to those
documents as appropriate. The Final EIS analyzes the use of PV
technology in detail, including any additional site-specific impacts
resulting from the change in technology and additional or relocated
ancillary facilities. This includes impacts to air quality, biological
resources, climate change, cultural resources, hazards and public
health, lands and realty, mineral resources, noise, paleontological
resources, recreation and special designations, socioeconomics and
environmental justice, soil resources, traffic and travel management,
visual resources, water resources, and wildland fire ecology.
A number of measures would be implemented to avoid, minimize,
rectify, reduce, or compensate for adverse impacts of the Modified
Project. These include:
Biological Resources: Wildlife would be avoided or
relocated (e.g., desert tortoise) to the extent feasible through
fencing, clearance surveys, and relocation/translocation. The Grant
Holder also proposes to implement a Raven Management Plan, Weed
Management Plan, Bird and Bat Conservation Strategy, and golden eagle
inventory and monitoring. The Grant Holder has also proposed off-site
compensatory mitigation to minimize or offset impacts to biological
resources.
Cultural Resources: The Grant Holder proposes to employ
cultural resource specialists as monitors during ground disturbance,
and to implement long-term protection measures.
Hazards and Visual Resources: The Grant Holder proposes to
document, investigate, evaluate, and attempt to resolve all project-
related glare complaints throughout the construction and operation of
the project; to use textured glass or anti-reflective coating on all
solar panels; and to construct all exposed PV panel support structures
with matte or non-reflective surfaces.
Water Resources: Site hydrology would be designed to
retain pre-project flows on the majority of the site, and the Grant
Holder would implement a Groundwater Level Monitoring, Mitigation, and
Reporting Plan.
The BLM has conducted Native American tribal consultations in
accordance with Section 106 of the National Historic Preservation Act
and Federal policy in connection with the previously approved BSPP,
which resulted in the development of a Programmatic Agreement. During
that process, tribes expressed their views and concerns about the
importance and sensitivity of specific cultural resources to which they
attach religious and cultural significance. The BLM has amended the
Programmatic Agreement, consistent with its terms, in response to the
Modified Project. In connection with its review of the Modified
Project, the BLM will carry out its responsibilities to consult with
tribes on a government-to-government basis and other members of the
public pursuant to the existing Programmatic Agreement, as amended, and
other authorities to the extent applicable and will continue to give
tribal concerns due consideration, including impacts to historic
properties to which tribes attach religious and cultural significance
and Indian trust assets.
Comments on the Draft EIS received from the public and based on
internal BLM review were considered and incorporated as appropriate
into the Final EIS. Public comments resulted in the addition of
clarifying text, but did not significantly change the substantive
analysis within the Final EIS.
Authority: 40 CFR 1506.6 & 1506.10.
Thomas Pogacnik,
Deputy State Director.
[FR Doc. 2014-12572 Filed 5-29-14; 8:45 am]
BILLING CODE 4310-40-P