Go with the Flow Hydro Power, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 29434-29435 [2014-11865]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
29434
Federal Register / Vol. 79, No. 99 / Thursday, May 22, 2014 / Notices
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted,
and is ready for environmental analysis
at this time.
l. Project Description: The existing
Chasm Project consists of: (1) a 201-footlong, 32-foot-high maximum height
concrete gravity-type dam having a
spillway section with crest elevation
1,283.8 feet mean sea level (msl) about
100 feet long, surmounted by 2-foothigh flashboards and having an intake
section with steel trash racks and
headgates; (2) a reservoir having a
surface area of about 22 acres and a
gross storage capacity of 74 acre-feet at
normal pool elevation of 1,285.8 feet
msl; (3) a 7-foot-diameter welded steel
pipeline approximately 3,355 feet in
length connecting to a 6-foot-diameter
steel manifold pipeline just upstream of
the powerhouse; (4) a powerhouse
containing three Francis-type generating
units having a total rated capacity of
3,350 kilowatts operated under a 268foot head and at a flow of 195 cubic feet
per second (cfs); (5) a 20-foot-wide, 850foot-long tailrace; (6) three 2.2-kilovolt
generator leads extending from the
powerhouse about 74 feet to an adjacent
swithchyard; (7) a 4.2-megavolt-ampere
step-up transformer located within the
switchyard, connecting to a
transmission line owned and operated
by the National Grid Corporation; and
(8) appurtenant facilities.
Erie proposes a minimum flow of 15
cfs into the bypassed reach at all times
and would forego its existing ability to
lower the minimum bypass flow to 10
cfs when inflow is less than 85 cfs. In
addition, Erie proposes to maintain the
impoundment elevation within 0.1 foot
of the spillway crest (or flashboards,
when installed) when inflow is less than
85 cfs and 0.25 foot when inflow is
greater than 85 cfs.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
VerDate Mar<15>2010
19:36 May 21, 2014
Jkt 232001
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
o. Procedural Schedule: The
application will be processed according
to the following revised Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Filing of comments, recommendations, terms and
conditions, and prescriptions.
Reply Comments Due ...........
Commission Issues Single
EA.
Comments on Single EA due
July 2014
August 2014
December
2014
January 2014
Dated: May 16, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–11864 Filed 5–21–14; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14538–001]
Go with the Flow Hydro Power, LLC;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Exemption
From Licensing
b. Project No.: P–14538
c. Date filed: May 5, 2014
d. Applicant: Go with the Flow Hydro
Power, LLC
e. Name of Project: Go with the Flow
Hydroelectric Project
f. Location: The proposed project is
located on the Umatilla River,
approximately 1.3 miles southwest of
the city of Hermiston, Umatilla County,
Oregon. The proposed project would not
occupy any federal lands.
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Mark Sigl, Go
with the Flow Hydro Power, LLC, 8021
Firestone Way, Antelope, California
95843
i. FERC Contact: Sean O’Neill at (202)
502–6462; or email at sean.oneill@
ferc.gov
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: July 7, 2014
E:\FR\FM\22MYN1.SGM
22MYN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 79, No. 99 / Thursday, May 22, 2014 / Notices
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first
page of any filing should include docket
number P–14538–001.
m. The application is not ready for
environmental analysis at this time.
n. The proposed project would use
the following existing facilities from an
abandoned hydroelectric project: (1) a
3.5-foot-high, 120-foot-long concrete
diversion weir, (2) a concrete intake
structure with trashrack, (3) a 5,350foot-long earthen power canal, (4) a
concrete penstock headworks structure,
(5) four 5-foot-diameter, 280-foot-long
welded steel penstocks, (6) a 60-foot by
35-foot powerhouse, (7) a 20-foot by 12foot metal controlhouse, (8) four 300kilowatt vertical propeller turbinegenerators, (9) a substation
interconnecting to the transmissions
lines operated by Pacific Power and
Light Company, (10) a 60-foot-wide, 25foot-long screened earthen tailrace
discharging into the Umatilla River, and
(11) appurtenant facilities. The
applicant is proposing a new fish bypass
at the diversion weir, and refurbishing
and replacing the fish screens at the
intake structure. The estimated annual
project generation is 3,000 megawatthours.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Oregon State
Historic Preservation Officer (SHPO), as
required by section 106 of the National
Historic Preservation Act and the
VerDate Mar<15>2010
19:36 May 21, 2014
Jkt 232001
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
q. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate (e.g., if there are no
deficiencies and/or scoping is waived,
the schedule would be shortened).
Issue Deficiency Letter ..........
Issue Notice of Acceptance ..
Issue Scoping Document August 2014.
Issue Notice ready for environmental analysis.
Issue Notice of the availability of the EA.
May 2014
July 2014
October 2014
March 2015
Dated: May 16, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–11865 Filed 5–21–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP13–113–000]
Dominion Cove Point LNG, LP; Notice
of Availability of the Environmental
Assessment and Draft General
Conformity Determination for the
Proposed Cove Point Liquefaction
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared an
environmental assessment (EA) for the
Cove Point Liquefaction Project (Project)
proposed by Dominion Cove Point LNG,
LP (DCP) in the above-referenced
docket. DCP requests authorization to
construct and operate facilities to
process and export domestically
sourced liquefied natural gas (LNG) at
the existing Cove Point LNG Terminal
(LNG Terminal) in Calvert County,
Maryland. The Project would enable
DCP to export approximately 5.75
million metric tons per annum of LNG
via LNG marine carriers that would
dock at the existing offshore pier. A
draft General Conformity Determination
has also been prepared by the FERC to
assess the potential air quality impacts
associated with construction and
operation of the proposed Project and is
included as appendix B of the EA.
The EA assesses the potential
environmental effects of the
construction and operation of the
Project in accordance with the
requirements of the National
Environmental Policy Act (NEPA). The
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
29435
draft General Conformity Determination
was prepared to implement the
conformity provision of the Clean Air
Act. The FERC staff concludes that
approval of the proposed Project, with
appropriate mitigating measures, would
not constitute a major federal action
significantly affecting the quality of the
human environment.
The U.S. Department of Energy, U.S.
Department of Transportation, U.S.
Army Corps of Engineers, U.S. Coast
Guard, and Maryland Department of
Natural Resources participated as
cooperating agencies in the preparation
of the EA and draft General Conformity
Determination. Cooperating agencies
have jurisdiction by law or special
expertise with respect to resources
potentially affected by the proposal and
participate in the NEPA analysis.
Although the cooperating agencies
provided input to the conclusions and
recommendations presented in the EA,
the agencies will present their own
conclusions and recommendations in
their respective Records of Decision or
determinations for the Project.
The proposed facilities associated
with the LNG Terminal include the
following:
• One LNG liquefaction train
consisting of gas treatment equipment,
natural gas-fired turbine-driven
refrigerant compressors, waste heat
recovery systems, fire and gas detection
and safety systems, and control systems;
• additional power generation
including waste heat-driven steam
turbine generators and other electrical
accessories to supplement the existing
on-site power generation;
• minor modifications to the existing
pier; and
• the use of two off-site areas to
support construction.
The Project would also include the
addition of up to 62,500 horsepower of
electric-driven compression at DCP’s
existing Pleasant Valley Compressor
Station in Fairfax County, Virginia, and
modifications to an existing metering
and regulating facility at DCP’s Loudoun
Compressor Station in Loudoun County,
Virginia.
The FERC staff mailed copies of the
EA and draft General Conformity
Determination to federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
libraries in the Project area; and parties
to this proceeding. In addition, the EA,
including the draft General Conformity
Determination, has been placed in the
public files of the FERC and is available
E:\FR\FM\22MYN1.SGM
22MYN1
Agencies
[Federal Register Volume 79, Number 99 (Thursday, May 22, 2014)]
[Notices]
[Pages 29434-29435]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-11865]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14538-001]
Go with the Flow Hydro Power, LLC; Notice of Application Tendered
for Filing With the Commission and Soliciting Additional Study Requests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Exemption From Licensing
b. Project No.: P-14538
c. Date filed: May 5, 2014
d. Applicant: Go with the Flow Hydro Power, LLC
e. Name of Project: Go with the Flow Hydroelectric Project
f. Location: The proposed project is located on the Umatilla River,
approximately 1.3 miles southwest of the city of Hermiston, Umatilla
County, Oregon. The proposed project would not occupy any federal
lands.
g. Filed Pursuant to: Public Utility Regulatory Policies Act of
1978, 16 U.S.C. 2705, 2708.
h. Applicant Contact: Mark Sigl, Go with the Flow Hydro Power, LLC,
8021 Firestone Way, Antelope, California 95843
i. FERC Contact: Sean O'Neill at (202) 502-6462; or email at
sean.oneill@ferc.gov
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: July 7, 2014
[[Page 29435]]
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first page of any filing should include
docket number P-14538-001.
m. The application is not ready for environmental analysis at this
time.
n. The proposed project would use the following existing facilities
from an abandoned hydroelectric project: (1) a 3.5-foot-high, 120-foot-
long concrete diversion weir, (2) a concrete intake structure with
trashrack, (3) a 5,350-foot-long earthen power canal, (4) a concrete
penstock headworks structure, (5) four 5-foot-diameter, 280-foot-long
welded steel penstocks, (6) a 60-foot by 35-foot powerhouse, (7) a 20-
foot by 12-foot metal controlhouse, (8) four 300-kilowatt vertical
propeller turbine-generators, (9) a substation interconnecting to the
transmissions lines operated by Pacific Power and Light Company, (10) a
60-foot-wide, 25-foot-long screened earthen tailrace discharging into
the Umatilla River, and (11) appurtenant facilities. The applicant is
proposing a new fish bypass at the diversion weir, and refurbishing and
replacing the fish screens at the intake structure. The estimated
annual project generation is 3,000 megawatt-hours.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. With this notice, we are initiating consultation with the Oregon
State Historic Preservation Officer (SHPO), as required by section 106
of the National Historic Preservation Act and the regulations of the
Advisory Council on Historic Preservation, 36 CFR 800.4.
q. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate (e.g., if there are no deficiencies and/or
scoping is waived, the schedule would be shortened).
------------------------------------------------------------------------
------------------------------------------------------------------------
Issue Deficiency Letter................... May 2014
Issue Notice of Acceptance................ July 2014
Issue Scoping Document August 2014........
Issue Notice ready for environmental October 2014
analysis.
Issue Notice of the availability of the EA March 2015
------------------------------------------------------------------------
Dated: May 16, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-11865 Filed 5-21-14; 8:45 am]
BILLING CODE 6717-01-P