City of Corvallis, Oregon; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 27598-27599 [2014-11094]

Agencies

[Federal Register Volume 79, Number 93 (Wednesday, May 14, 2014)]
[Notices]
[Pages 27598-27599]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-11094]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD14-19-000]


City of Corvallis, Oregon; Notice of Preliminary Determination of 
a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On April 24, 2014, City of Corvallis, Oregon filed a notice of 
intent to construct a qualifying conduit hydropower facility, pursuant 
to section 30 of the Federal Power Act (FPA), as amended by section 4 
of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The 
proposed City of Corvallis Rock Creek Water Treatment Plant Hydropower 
Project would have an installed capacity of 28 kilowatts (kW) and would 
utilize an existing 16-inch diameter water supply pipeline. The project 
would be located near the City of Corvallis in Benton County, Oregon.
    Applicant Contact: Brian Tingwood, City of Corvallis, Oregon, P.O. 
Box 1083, Corvallis, OR 97339, Phone No. (541) 766-6916.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
robert.bell@ferc.gov.
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A proposed 12-inch-diameter bifurcation 
pipe, (2) a proposed 4-foot-long, 12-inch-diameter intake pipe; (3) a 
proposed powerhouse containing one generating unit with an installed 
capacity of 28 kW; (4) a proposed 10-foot-long, 12-inch-diameter 
discharge pipe back into the main pipeline; and (5) appurtenant 
facilities. The proposed project would have an estimated annual 
generating capacity of 219.113 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
      Statutory provision              Description       Satisfies (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by   The conduit the                      Y
 HREA.                            facility uses is a
                                  tunnel, canal,
                                  pipeline, aqueduct,
                                  flume, ditch, or
                                  similar manmade water
                                  conveyance that is
                                  operated for the
                                  distribution of water
                                  for agricultural,
                                  municipal, or
                                  industrial
                                  consumption and not
                                  primarily for the
                                  generation of
                                  electricity.
FPA 30(a)(3)(C)(i), as amended   The facility is                      Y
 by HREA.                         constructed,
                                  operated, or
                                  maintained for the
                                  generation of
                                  electric power and
                                  uses for such
                                  generation only the
                                  hydroelectric
                                  potential of a non-
                                  federally owned
                                  conduit.
FPA 30(a)(3)(C)(ii), as amended  The facility has an                  Y
 by HREA.                         installed capacity
                                  that does not exceed
                                  5 megawatts.
FPA 30(a)(3)(C)(iii), as         On or before August 9,               Y
 amended by HREA.                 2013, the facility is
                                  not licensed, or
                                  exempted from the
                                  licensing
                                  requirements of Part
                                  I of the FPA.
------------------------------------------------------------------------


[[Page 27599]]

    Preliminary Determination: Based upon the above criteria, 
Commission staff preliminarily determines that the proposal satisfies 
the requirements for a qualifying conduit hydropower facility, which is 
not required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    Deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2013).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at https://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD14-19-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, 
call (202) 502-8659.

    Dated: May 8, 2014.
Kimberly D. Bose,
Secretary.