Copper Valley Electric Association, Inc.; Notice of Application To Amend License and Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 26748 [2014-10612]

Download as PDF 26748 Federal Register / Vol. 79, No. 90 / Friday, May 9, 2014 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13124–015] ehiers on DSK2VPTVN1PROD with NOTICES Copper Valley Electric Association, Inc.; Notice of Application To Amend License and Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Amendment to License. b. Project No: 13124–015. c. Date Filed: April 14, 2014. d. Applicant: Copper Valley Electric Association, Inc. e. Name of Project: Allison Creek Hydroelectric Project. f. Location: On Allison Creek in Valdez, Alaska. This project does not occupy any federal lands. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Robert A. Wilkinson, CEO, Copper Valley Electric Association, Inc., P.O. Box 45, Mile 187 Glenn Highway, Glennallen, AK 99588, (907) 822–3211. i. FERC Contact: Steven Sachs at (202) 502–8666; or Steven.Sachs@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests, is 30 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file any motion to intervene, protest, comments, and/or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13124–005. k. Description of Request: As licensed, the unconstructed project includes two 3.25-megawatt (MW) turbine-generator units, a 120-foot-long tailrace exiting the west side of the powerhouse, and a 3.8mile-long, 34.5-kilovolt (kV) transmission line following an existing VerDate Mar<15>2010 14:53 May 08, 2014 Jkt 232001 right-of-way. In its application, the licensee proposes to install a single 6.5MW turbine-generator unit, construct a 70.5-foot-long tailrace extending from the north side of the powerhouse, and erect a 3.8-mile-long, 25-kV transmission line south of the original location and following a utility easement entirely on land owned by the State of Alaska. The new transmission line routing would interconnect with the grid at the same location as originally proposed. l. Locations of the Application: This filing may be viewed on the Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number P–13124 in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208- 3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above and at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the license amendment. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: May 1, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–10612 Filed 5–8–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14578–000] Telluride Energy, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On January 15, 2014, Telluride Energy, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Buchanan Dam Hydroelectric Project (Buchanan Dam Project or project) at the U.S. Army Corps of Engineers’ (Corps) Eastman Lake and Buchanan dam on the Chowchilla River, near the city of Chowchilla in Madera County, California. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) A new penstock that E:\FR\FM\09MYN1.SGM 09MYN1

Agencies

[Federal Register Volume 79, Number 90 (Friday, May 9, 2014)]
[Notices]
[Page 26748]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-10612]



[[Page 26748]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13124-015]


Copper Valley Electric Association, Inc.; Notice of Application 
To Amend License and Accepted for Filing, Soliciting Comments, Motions 
To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Amendment to License.
    b. Project No: 13124-015.
    c. Date Filed: April 14, 2014.
    d. Applicant: Copper Valley Electric Association, Inc.
    e. Name of Project: Allison Creek Hydroelectric Project.
    f. Location: On Allison Creek in Valdez, Alaska. This project does 
not occupy any federal lands.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Robert A. Wilkinson, CEO, Copper Valley 
Electric Association, Inc., P.O. Box 45, Mile 187 Glenn Highway, 
Glennallen, AK 99588, (907) 822-3211.
    i. FERC Contact: Steven Sachs at (202) 502-8666; or 
Steven.Sachs@ferc.gov.
    j. Deadline for filing comments, motions to intervene, and 
protests, is 30 days from the issuance date of this notice by the 
Commission. The Commission strongly encourages electronic filing. 
Please file any motion to intervene, protest, comments, and/or 
recommendations using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-13124-005.
    k. Description of Request: As licensed, the unconstructed project 
includes two 3.25-megawatt (MW) turbine-generator units, a 120-foot-
long tailrace exiting the west side of the powerhouse, and a 3.8-mile-
long, 34.5-kilovolt (kV) transmission line following an existing right-
of-way. In its application, the licensee proposes to install a single 
6.5-MW turbine-generator unit, construct a 70.5-foot-long tailrace 
extending from the north side of the powerhouse, and erect a 3.8-mile-
long, 25-kV transmission line south of the original location and 
following a utility easement entirely on land owned by the State of 
Alaska. The new transmission line routing would interconnect with the 
grid at the same location as originally proposed.
    l. Locations of the Application: This filing may be viewed on the 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number P-13124 in the docket number field to access 
the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and 
issuances related to this or other pending projects. For assistance, 
call 1-866-208- 3676 or email FERCOnlineSupport@ferc.gov, for TTY, call 
(202) 502-8659. A copy is also available for inspection and 
reproduction at the address in item (h) above and at the Commission's 
Public Reference Room, located at 888 First Street NE., Room 2A, 
Washington, DC 20426, or by calling (202) 502-8371.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or 
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis and otherwise comply with the requirements of 18 CFR 
4.34(b). All comments, motions to intervene, or protests should relate 
to project works which are the subject of the license amendment. 
Agencies may obtain copies of the application directly from the 
applicant. A copy of any protest or motion to intervene must be served 
upon each representative of the applicant specified in the particular 
application. If an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.

    Dated: May 1, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-10612 Filed 5-8-14; 8:45 am]