Rugraw, LLC: Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 25857 [2014-10338]

Download as PDF 25857 Federal Register / Vol. 79, No. 87 / Tuesday, May 6, 2014 / Notices API GRAVITY RANGES ≤20.0 20.1 to 30.0 30.1 to 35.0 35.1 to 40.0 Note that it is expected that the ‘‘unknown’’ category will be rarely used by the respondent companies, typically under exceptional and temporary circumstances. (5) Estimated Number of Survey Respondents: 600 respondents. (6) Annual Estimated Number of Total Responses: The annual number of total responses is 7200. Annual Estimated Number of Burden Hours: The annual estimated burden is 21,600 hours. (7) Annual Estimated Reporting and Recordkeeping Cost Burden: Additional costs to respondents are not anticipated beyond costs associated with response burden hours. (8) Comments submitted in response to this notice will be summarized and/ or included in the request for OMB approval of the form. They also will become a matter of public record. Statutory Authority: Section 13(b) of the Federal Energy Administration Act of 1974, Pub. L. 93–275, codified at 15 U.S.C. 772(b). Issued in Washington, DC on April 30, 2014. Stephen J. Harvey, Assistant Administrator for Energy Statistics, U.S. Energy Information Administration. [FR Doc. 2014–10352 Filed 5–5–14; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12496–002] sroberts on DSK5SPTVN1PROD with NOTICES Rugraw, LLC: Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Major original license b. Project No.: 12496–002 c. Date filed: April 21, 2014 d. Applicant: Rugraw, LLC e. Name of Project: Lassen Lodge Hydroelectric Project f. Location: On the South Fork Battle Creek, nearby the Town of Mineral, Tehama County, California. No federal lands or Indian reservations are located within the proposed project boundary. VerDate Mar<15>2010 17:34 May 05, 2014 Jkt 232001 40.1 to 45.0 45.1 to 50.0 g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r) h. Applicant Contact: Charlie Kuffner, 70 Paseo Mirasol, Tiburon, CA 94920; (415) 652–8553 i. FERC Contact: Adam Beeco at (202) 502–8655; email—adam.beeco@ferc.gov j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: June 20, 2014 The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–12496–002. m. The application is not ready for environmental analysis at this time. n. The proposed Lassen Lodge Project consists of: (1) A 6-foot-high and 94foot-long diversion dam; (2) an impoundment of approximately 0.5 acre; (3) a 20 by 10 foot enclosed concrete intake structure; (4) a 7,258foot-long pipeline and a 5,230-foot-long PO 00000 Frm 00044 Fmt 4703 Sfmt 9990 50.1 to 55.0 ≥55.0 unknown penstock with a net head of 791 feet; (5) a 50 by 50 foot powerhouse containing one generating unit with a 5,000kilowatt capacity; (6) a 50 by 50 foot substation area; (7) a 40 by 35 foot switchyard; (8) 100 by 100 foot multipurpose area; and (9) a new 12mile-long, 60-kilovolt transmission line. The project is estimated to produce approximately 25,000,000 kilowatthours annually. o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural schedule: The application will be processed according to the following preliminary Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. Issue Acceptance or Deficiency Letter. Request Additional Information. Issue Acceptance Letter ........ Issue Scoping Document 1 for Comments. Request Additional Information (if necessary). Issue Scoping Document 2 (if necessary). Notice that application is ready for environmental analysis. Notice of the availability of the draft EA. Notice of the availability of the final EA. June 2014 June 2014 September 2014 October 2014 December 2014 January 2015 January 2015 July 2015 October 2015 Dated: April 29, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–10338 Filed 5–5–14; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\06MYN1.SGM 06MYN1

Agencies

[Federal Register Volume 79, Number 87 (Tuesday, May 6, 2014)]
[Notices]
[Page 25857]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-10338]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12496-002]


Rugraw, LLC: Notice of Application Tendered for Filing With the 
Commission and Soliciting Additional Study Requests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Major original license
    b. Project No.: 12496-002
    c. Date filed: April 21, 2014
    d. Applicant: Rugraw, LLC
    e. Name of Project: Lassen Lodge Hydroelectric Project
    f. Location: On the South Fork Battle Creek, nearby the Town of 
Mineral, Tehama County, California. No federal lands or Indian 
reservations are located within the proposed project boundary.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r)
    h. Applicant Contact: Charlie Kuffner, 70 Paseo Mirasol, Tiburon, 
CA 94920; (415) 652-8553
    i. FERC Contact: Adam Beeco at (202) 502-8655; email_
adam.beeco@ferc.gov
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: June 20, 2014
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket number P-12496-002.
    m. The application is not ready for environmental analysis at this 
time.
    n. The proposed Lassen Lodge Project consists of: (1) A 6-foot-high 
and 94-foot-long diversion dam; (2) an impoundment of approximately 0.5 
acre; (3) a 20 by 10 foot enclosed concrete intake structure; (4) a 
7,258-foot-long pipeline and a 5,230-foot-long penstock with a net head 
of 791 feet; (5) a 50 by 50 foot powerhouse containing one generating 
unit with a 5,000-kilowatt capacity; (6) a 50 by 50 foot substation 
area; (7) a 40 by 35 foot switchyard; (8) 100 by 100 foot multipurpose 
area; and (9) a new 12-mile-long, 60-kilovolt transmission line. The 
project is estimated to produce approximately 25,000,000 kilowatt-hours 
annually.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule: The application will be processed according 
to the following preliminary Hydro Licensing Schedule. Revisions to the 
schedule will be made as appropriate.

 
 
 
Issue Acceptance or Deficiency Letter..  June 2014
Request Additional Information.........  June 2014
Issue Acceptance Letter................  September 2014
Issue Scoping Document 1 for Comments..  October 2014
Request Additional Information (if       December 2014
 necessary).
Issue Scoping Document 2 (if necessary)  January 2015
Notice that application is ready for     January 2015
 environmental analysis.
Notice of the availability of the draft  July 2015
 EA.
Notice of the availability of the final  October 2015
 EA.
 


    Dated: April 29, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-10338 Filed 5-5-14; 8:45 am]
BILLING CODE 6717-01-P