Texas Eastern Transmission, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed Uniontown to Gas City Project and Request for Comments on Environmental Issues, 25859-25861 [2014-10316]
Download as PDF
Federal Register / Vol. 79, No. 87 / Tuesday, May 6, 2014 / Notices
The Complainant certifies that copies
of the complaint were served on the
Respondent as listed on the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on May 15, 2014.
Dated: April 29, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–10318 Filed 5–5–14; 8:45 am]
sroberts on DSK5SPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
VerDate Mar<15>2010
17:34 May 05, 2014
Jkt 232001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–104–000]
Texas Eastern Transmission, LP;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Uniontown to Gas City
Project and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Uniontown to Gas City Project
(Project) involving construction and
operation of facilities by Texas Eastern
Transmission, LP (Texas Eastern) in
Pennsylvania, Ohio and Indiana. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on May 29,
2014.
You may submit comments in written
form or verbally. Further details on how
to submit written comments are in the
Public Participation section of this
notice.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this
proposed Project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the Project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Texas Eastern provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
25859
To Know?’’ This fact sheet addresses a
number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Summary of the Proposed Project
The purpose of the Project is to make
new firm pipeline capacity available to
transport production of five shippers
that have executed precedent
agreements with Texas Eastern. It would
allow additional natural gas from the
Appalachian production area to be
transported to markets in the Midwest.
This would be accomplished by
modifying 23 existing aboveground
facilities along Texas Eastern’s system.
These facilities include:
• In Greene County, Pennsylvania,
modifications at the Waynesburg
Compressor Station would include new
sample lines at the 70009 meter and
regulator (M&R) station and 70037 M&R
station, a new gas chromatograph/
electronic gas measurement (GC/EGM)
building, removal of a deanalyzer
building, and a new GC sample line at
the Waynesburg Suction; new GC/EGM
buildings at the 70020 and 73152 M&R
station, and gas turbine modifications at
the existing Holbrook Compressor
Station;
• in Monroe County, Ohio, a new GC
and Remote Terminal Units (RTU) at the
70983 and 70471 M&R Stations, and a
new launcher/receiver and filter
separator at the Berne Compressor
Station;
• in Noble County, Ohio, a new
launcher/receiver at the Summerfield
Compressor Station, and new receiver
on Somerset Line 65;
• in Perry County, Ohio, new
launcher/receiver at the Coserset
Compressor Station;
• in Fairfield County, Ohio, a new GC
building at the 73715 and 70077 M&R
Stations;
• in Pickaway County, Ohio, a new
crossover and receiver at the Five Points
Line 1, and gas turbine modifications at
the Five Points Compressor Station;
• in Fayette County, Ohio, new
receiver at the Lebanon Discharge Line
1 and new GC at the 70081 M&R
Station;
• in Clinton County, Ohio, a new GC
at the 73105 M&R Station;
• in Warren County, Ohio, gas turbine
modifications at the Lebanon
Compressor Station, a new GC building
at 70041 M&R Station, reversal
modifications at the 72945 M&R Station,
a new GC/RTU building at 72908 M&R
Station, and a new GC at 71353 M&R
Station;
E:\FR\FM\06MYN1.SGM
06MYN1
25860
Federal Register / Vol. 79, No. 87 / Tuesday, May 6, 2014 / Notices
• in Darke County, Ohio, new RTU
building at the 72902 M&R Station, and
reverse compressor modifications at the
Glen Karn Compressor Station; and
• in Grant County, Indiana, a new
delivery meter station, and reverse
compressor modifications at the Gas
City Compressor Station.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
With the exception of the proposed
20-inch-diameter crossover pipeline
located at the Five Points Line 1 in
Pickaway County, Ohio, all of the
proposed activities associated with the
Project would take place within Texas
Eastern’s existing right-of-way. About
4.8 acres would be disturbed during
construction at all the modified
facilities combined within the existing
right-of-way. The crossover at the Five
Points Line 1 would disturb an
additional 0.07 acre outside of the
existing right-of-way.
The EA Process
sroberts on DSK5SPTVN1PROD with NOTICES
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. The NEPA also requires us 2
to discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed Project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
VerDate Mar<15>2010
17:34 May 05, 2014
Jkt 232001
• endangered and threatened species;
• reliability; and
• public safety.
We will also evaluate reasonable
alternatives to the proposed Project or
portions of the Project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendation to the Commission. To
ensure your comments are considered,
please carefully follow the instructions
in the Public Participation section of
this notice.
With this notice, we are asking
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to formally
cooperate with us in the preparation of
the EA. Agencies that would like to
request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the Project’s potential effects on
historic properties.3 We will define the
Project-specific Area of Potential Effects
(APE) in consultation with the SHPOs
as the project develops. On natural gas
projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
Project will document our findings on
the impacts on historic properties and
summarize the status on consultations
under section 106.
3 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the Project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send in your comments
so that they will be received in
Washington, DC on or before May 29,
2014.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the Project
docket number (CP14–104–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s Web site at www.ferc.gov
under the link to Documents and
Filings. An eComment is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at www.ferc.gov
under the link to Documents and
Filings. With eFiling you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making. A
comment on a particular project is
considered a ‘‘Comment on a Filing;’’ or
(3) You may file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; interested Indian tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
E:\FR\FM\06MYN1.SGM
06MYN1
Federal Register / Vol. 79, No. 87 / Tuesday, May 6, 2014 / Notices
within certain distances of aboveground
facilities, and anyone who submits
comments on the Project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the compact disc version or would like
to remove your name from the mailing
list, please return the attached
Information Request (appendix 2).
sroberts on DSK5SPTVN1PROD with NOTICES
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits, in the Docket Number
field (i.e., CP14–104). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/docs-filing/
esubscription.asp.
VerDate Mar<15>2010
17:34 May 05, 2014
Jkt 232001
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: April 29, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–10316 Filed 5–5–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER14–1777–000]
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization; Wheelabrator Falls Inc.
This is a supplemental notice in the
above-referenced proceeding of
Wheelabrator Falls Inc.’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is May 19,
2014.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
25861
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: April 29, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–10317 Filed 5–5–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2280–018]
Seneca Generation, LLC; Notice of
Application Accepted for Filing,
Soliciting Motions To Intervene and
Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms
and Conditions, and Preliminary
Fishway Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2280–018.
c. Date filed: December 2, 2013.
d. Applicant: Seneca Generation, LLC.
e. Name of Project: Kinzua Pumped
Storage Hydroelectric Project.
f. Location: The existing project is
located on the Allegheny River in
Warren, Pennsylvania. The project is
located on 226.7 acres of federal lands;
212.1 acres of which is administered by
the U.S. Forest Service and 14.6 acres
administered by the U.S. Army Corps of
Engineers.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Kathy French,
P.E., Assistant VP, Environmental,
Health and Safety, Seneca Generation,
LLC, 1700 Broadway, 35th Floor, New
York, NY 10019; Telephone (212) 547–
4381.
i. FERC Contact: Gaylord Hoisington,
Telephone (202) 502–6032, and email
gaylord.hoisington@ferc.gov.
E:\FR\FM\06MYN1.SGM
06MYN1
Agencies
[Federal Register Volume 79, Number 87 (Tuesday, May 6, 2014)]
[Notices]
[Pages 25859-25861]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-10316]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-104-000]
Texas Eastern Transmission, LP; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Uniontown to Gas City Project
and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Uniontown to Gas City Project
(Project) involving construction and operation of facilities by Texas
Eastern Transmission, LP (Texas Eastern) in Pennsylvania, Ohio and
Indiana. The Commission will use this EA in its decision-making process
to determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on May 29, 2014.
You may submit comments in written form or verbally. Further
details on how to submit written comments are in the Public
Participation section of this notice.
This notice is being sent to the Commission's current environmental
mailing list for this Project. State and local government
representatives should notify their constituents of this proposed
Project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Texas Eastern provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do
I Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
The purpose of the Project is to make new firm pipeline capacity
available to transport production of five shippers that have executed
precedent agreements with Texas Eastern. It would allow additional
natural gas from the Appalachian production area to be transported to
markets in the Midwest. This would be accomplished by modifying 23
existing aboveground facilities along Texas Eastern's system. These
facilities include:
In Greene County, Pennsylvania, modifications at the
Waynesburg Compressor Station would include new sample lines at the
70009 meter and regulator (M&R) station and 70037 M&R station, a new
gas chromatograph/electronic gas measurement (GC/EGM) building, removal
of a deanalyzer building, and a new GC sample line at the Waynesburg
Suction; new GC/EGM buildings at the 70020 and 73152 M&R station, and
gas turbine modifications at the existing Holbrook Compressor Station;
in Monroe County, Ohio, a new GC and Remote Terminal Units
(RTU) at the 70983 and 70471 M&R Stations, and a new launcher/receiver
and filter separator at the Berne Compressor Station;
in Noble County, Ohio, a new launcher/receiver at the
Summerfield Compressor Station, and new receiver on Somerset Line 65;
in Perry County, Ohio, new launcher/receiver at the
Coserset Compressor Station;
in Fairfield County, Ohio, a new GC building at the 73715
and 70077 M&R Stations;
in Pickaway County, Ohio, a new crossover and receiver at
the Five Points Line 1, and gas turbine modifications at the Five
Points Compressor Station;
in Fayette County, Ohio, new receiver at the Lebanon
Discharge Line 1 and new GC at the 70081 M&R Station;
in Clinton County, Ohio, a new GC at the 73105 M&R
Station;
in Warren County, Ohio, gas turbine modifications at the
Lebanon Compressor Station, a new GC building at 70041 M&R Station,
reversal modifications at the 72945 M&R Station, a new GC/RTU building
at 72908 M&R Station, and a new GC at 71353 M&R Station;
[[Page 25860]]
in Darke County, Ohio, new RTU building at the 72902 M&R
Station, and reverse compressor modifications at the Glen Karn
Compressor Station; and
in Grant County, Indiana, a new delivery meter station,
and reverse compressor modifications at the Gas City Compressor
Station.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
With the exception of the proposed 20-inch-diameter crossover
pipeline located at the Five Points Line 1 in Pickaway County, Ohio,
all of the proposed activities associated with the Project would take
place within Texas Eastern's existing right-of-way. About 4.8 acres
would be disturbed during construction at all the modified facilities
combined within the existing right-of-way. The crossover at the Five
Points Line 1 would disturb an additional 0.07 acre outside of the
existing right-of-way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. The NEPA also requires
us \2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed Project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
reliability; and
public safety.
We will also evaluate reasonable alternatives to the proposed
Project or portions of the Project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendation
to the Commission. To ensure your comments are considered, please
carefully follow the instructions in the Public Participation section
of this notice.
With this notice, we are asking agencies with jurisdiction and/or
special expertise with respect to environmental issues to formally
cooperate with us in the preparation of the EA. Agencies that would
like to request cooperating agency status should follow the
instructions for filing comments provided under the Public
Participation section of this notice.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the Project's potential effects on
historic properties.\3\ We will define the Project-specific Area of
Potential Effects (APE) in consultation with the SHPOs as the project
develops. On natural gas projects, the APE at a minimum encompasses all
areas subject to ground disturbance (examples include construction
right-of-way, contractor/pipe storage yards, compressor stations, and
access roads). Our EA for this Project will document our findings on
the impacts on historic properties and summarize the status on
consultations under section 106.
---------------------------------------------------------------------------
\3\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send in your comments
so that they will be received in Washington, DC on or before May 29,
2014.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the Project docket number (CP14-104-000) with your
submission. The Commission encourages electronic filing of comments and
has expert eFiling staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's Web site at www.ferc.gov
under the link to Documents and Filings. An eComment is an easy method
for interested persons to submit brief, text-only comments on a
project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at www.ferc.gov
under the link to Documents and Filings. With eFiling you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making. A comment on a particular project is considered a ``Comment
on a Filing;'' or
(3) You may file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; interested Indian tribes;
other interested parties; and local libraries and newspapers. This list
also includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes
[[Page 25861]]
within certain distances of aboveground facilities, and anyone who
submits comments on the Project. We will update the environmental
mailing list as the analysis proceeds to ensure that we send the
information related to this environmental review to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the compact
disc version or would like to remove your name from the mailing list,
please return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits, in the Docket Number field (i.e.,
CP14-104). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: April 29, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-10316 Filed 5-5-14; 8:45 am]