25628
Federal Register / Vol. 79, No. 86 / Monday, May 5, 2014 / Notices
backfitting, inasmuch as the SRP is
internal guidance to NRC staff.
The SRP provides internal guidance
to the NRC staff on how to review an
application for NRC regulatory approval
in the form of licensing. Changes in
internal staff guidance are not matters
for which either nuclear power plant
applicants or licensees are protected
under either the Backfit Rule or the
issue finality provisions of 10 CFR part
52.
2. The NRC staff has no intention to
impose the SRP positions on existing
licensees either now or in the future.
The NRC staff does not intend to
impose or apply the positions described
in the draft SRP to existing licenses and
regulatory approvals. Hence, the
issuance of a final SRP—even if
considered guidance within the purview
of the issue finality provisions in 10
CFR part 52—would not need to be
evaluated as if it were a backfit or as
being inconsistent with issue finality
provisions. If, in the future, the NRC
staff seeks to impose a position in the
SRP on holders of already issued
licenses in a manner that does not
provide issue finality as described in the
applicable issue finality provision, then
the staff must make the showing as set
forth in the Backfit Rule or address the
criteria for avoiding issue finality as
described in the applicable issue finality
provision.
3. Backfitting and issue finality do
not—with limited exceptions not
applicable here—protect current or
future applicants.
Applicants and potential applicants
are not, with certain exceptions,
protected by either the Backfit Rule or
any issue finality provisions under 10
CFR part 52. Neither the Backfit Rule
nor the issue finality provisions under
10 CFR part 52—with certain
exclusions—were intended to apply to
every NRC action that substantially
changes the expectations of current and
future applicants. The exceptions to the
general principle are applicable
whenever an applicant references a 10
CFR part 52 license (e.g., an early site
permit) and/or NRC regulatory approval
(e.g., a design certification rule) with
specified issue finality provisions. The
NRC staff does not, at this time, intend
to impose the positions represented in
the draft SRP in a manner that is
inconsistent with any issue finality
provisions. If, in the future, the staff
seeks to impose a position in the draft
SRP in a manner that does not provide
issue finality as described in the
applicable issue finality provision, then
the staff must address the criteria for
avoiding issue finality as described in
the applicable issue finality provision.
VerDate Mar<15>2010
17:56 May 02, 2014
Jkt 232001
Dated at Rockville, Maryland, this 22nd
day of April 2014.
For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, Policy Branch, Division of Advanced
Reactors and Rulemaking, Office of New
Reactors.
[FR Doc. 2014–10245 Filed 5–2–14; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2014–0099]
Proposed Revision 0 to Fitness-forDuty—Construction
Nuclear Regulatory
Commission.
ACTION: Standard review plan-draft new
section; request for comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is soliciting public
comment on draft NUREG–0800,
‘‘Standard Review Plan for the Review
of Safety Analysis Reports for Nuclear
Power Plants: LWR Edition,’’ Section
13.7.2, ‘‘Fitness for Duty—
Construction.’’ The NRC seeks
comments on the proposed new section
of the Standard Review Plan (SRP),
concerning implementation of a Fitnessfor-Duty (FFD) program during
construction. The current SRP does not
contain guidance on the review of an
applicant’s proposed construction FFD
program.
SUMMARY:
Comments must be filed no later
than July 7, 2014. Comments received
after this date will be considered, if it
is practical to do so, but the
Commission is able to ensure
consideration only for comments
received on or before this date.
ADDRESSES: You may submit comments
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0099. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Chief, Rules, Announcements, and
Directives Branch (RADB), Office of
Administration, Mail Stop: 3WFN–06–
44M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
DATES:
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
For additional direction on accessing
information and submitting comments,
see ‘‘Accessing Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Wesley W. Held, Office of New
Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone at 301–415–1583 or
email at Wesley.Held@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Accessing Information and
Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC–2014–
0099 when contacting the NRC about
the availability of information regarding
this document. You may access
publicly-available information related to
this action by the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2014–0099.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS Accession number for the
proposed new section of the SRP,
Section 13.7.2, ‘‘Fitness for Duty—
Construction,’’ is available in ADAMS
under accession no. ML113270035.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2014–
0099 in the subject line of your
comment submission, in order to ensure
that the NRC is able to make your
comment submission available to the
public in this docket.
The NRC cautions you not to include
identifying or contact information in
comment submissions that you do not
want to be publicly disclosed. The NRC
will post all comment submissions at
https://www.regulations.gov as well as
enter the comment submissions into
ADAMS. The NRC does not routinely
edit comment submissions to remove
identifying or contact information.
E:\FR\FM\05MYN1.SGM
05MYN1
Federal Register / Vol. 79, No. 86 / Monday, May 5, 2014 / Notices
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information that
they do not want to be publicly
disclosed in their comment
submissions. Your request should state
that the NRC does not routinely edit
comment submissions to remove such
information before making the comment
submissions available to the public or
entering the comment submissions into
ADAMS.
emcdonald on DSK67QTVN1PROD with NOTICES
II. Further Information
The NRC seeks public comment on
the proposed new section of SRP 13.7.2.
This section has been developed to
assist NRC staff with the review of
applications for certain construction
permits, early site permits, licenses,
license amendments, and combined
licenses and to inform new reactor
applicants and other affected entities of
proposed SRP guidance regarding an
acceptable method by which to evaluate
a proposed FFD program for compliance
with Part 26 of Title 10 of the Code of
Federal Regulations (10 CFR).
Following NRC staff evaluation of
public comments, the NRC intends to
finalize SRP 13.7.2, Revision 0 in
ADAMS and post on the NRC’s public
Web site within the link for NUREG–
0800. The SRP is guidance for the NRC
staff. The SRP is not a substitute for the
NRC regulations, and compliance with
the SRP is not required.
III. Backfitting and Issue Finality
Issuance of this draft SRP, if finalized,
would not constitute backfitting as
defined in 10 CFR 50.109 (the Backfit
Rule) or otherwise be inconsistent with
the issue finality provisions in 10 CFR
Part 52. The NRC’s position is based
upon the following considerations.
1. The draft SRP positions, if
finalized, would not constitute
backfitting, inasmuch as the SRP is
internal guidance to NRC staff.
The SRP provides internal guidance
to the NRC staff on how to review an
application for NRC regulatory approval
in the form of licensing. Changes in
internal staff guidance are not matters
for which either nuclear power plant
applicants or licensees are protected
under either the Backfit Rule or the
issue finality provisions of 10 CFR Part
52.
2. The NRC staff has no intention to
impose the SRP positions on existing
licensees either now or in the future.
The NRC staff does not intend to
impose or apply the positions described
in the draft SRP to existing licenses and
regulatory approvals. Hence, the
VerDate Mar<15>2010
17:56 May 02, 2014
Jkt 232001
issuance of a final SRP—even if
considered guidance within the purview
of the issue finality provisions in 10
CFR Part 52—would not need to be
evaluated as if it were a backfit or as
being inconsistent with issue finality
provisions. If, in the future, the NRC
staff seeks to impose a position in the
SRP on holders of already issued
licenses in a manner that does not
provide issue finality as described in the
applicable issue finality provision, then
the staff must make the showing as set
forth in the Backfit Rule or address the
criteria for avoiding issue finality as
described in the applicable issue finality
provision.
3. Backfitting and issue finality do
not—with limited exceptions not
applicable here—protect current or
future applicants.
Applicants and potential applicants
are not, with certain exceptions,
protected by either the Backfit Rule or
any issue finality provisions under 10
CFR Part 52. Neither the Backfit Rule
nor the issue finality provisions under
10 CFR Part 52—with certain
exclusions—were intended to apply to
every NRC action that substantially
changes the expectations of current and
future applicants. The exceptions to the
general principle are applicable
whenever an applicant references a 10
CFR Part 52 license (e.g., an early site
permit) and/or NRC regulatory approval
(e.g., a design certification rule) with
specified issue finality provisions. The
NRC staff does not, at this time, intend
to impose the positions represented in
the draft SRP in a manner that is
inconsistent with any issue finality
provisions. If, in the future, the staff
seeks to impose a position in the draft
SRP in a manner that does not provide
issue finality as described in the
applicable issue finality provision, then
the staff must address the criteria for
avoiding issue finality as described in
the applicable issue finality provision.
Dated at Rockville, Maryland, this 22nd
day of April 2014.
For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, Policy Branch, Division of Advanced
Reactors and Rulemaking, Office of New
Reactors.
[FR Doc. 2014–10217 Filed 5–2–14; 8:45 am]
BILLING CODE 7590–01–P
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
25629
SECURITIES AND EXCHANGE
COMMISSION
Proposed Collection; Comment
Request
Upon Written Request, Copies Available
From: U.S. Securities and Exchange
Commission, Office of Investor
Education and Advocacy,
Washington, DC 20549–0213.
Extension:
Rule 15g–2, SEC File No. 270–381, OMB
Control No. 3235–0434.
Notice is hereby given that pursuant
to the Paperwork Reduction Act of 1995
(44 U.S.C. 3501 et seq.) (‘‘PRA’’), the
Securities and Exchange Commission
(‘‘Commission’’) is soliciting comments
on the collection of information
provided for in Rule 15g–2 (17 CFR
240.15g–2) under the Securities
Exchange Act of 1934 (15 U.S.C. 78a et
seq.) (‘‘Exchange Act’’). The
Commission plans to submit this
existing collection of information to the
Office of Management and Budget
(‘‘OMB’’) for extension and approval.
Rule 15g–2 (The ‘‘Penny Stock
Disclosure Rule’’) requires brokerdealers to provide their customers with
a risk disclosure document, as set forth
in Schedule 15G, prior to their first nonexempt transaction in a ‘‘penny stock.’’
As amended, the rule requires brokerdealers to obtain written
acknowledgement from the customer
that he or she has received the required
risk disclosure document. The amended
rule also requires broker-dealers to
maintain a copy of the customer’s
written acknowledgement for at least
three years following the date on which
the risk disclosure document was
provided to the customer, the first two
years in an accessible place. Rule 15g–
2 also requires a broker-dealer, upon
request of a customer, to furnish the
customer with a copy of certain
information set forth on the
Commission’s Web site.
The risk disclosure documents are for
the benefit of the customers, to assure
that they are aware of the risks of
trading in ‘‘penny stocks’’ before they
enter into a transaction. The risk
disclosure documents are maintained by
the broker-dealers and may be reviewed
during the course of an examination by
the Commission.
There are approximately 221 brokerdealers that could potentially be subject
to current Rule 15g–2. The Commission
estimates that approximately 5% of
registered broker-dealers are engaged in
penny stock transactions, and thereby
subject to the Rule (5% × approximately
4,410 registered broker-dealers = 221
broker-dealers). The Commission
E:\FR\FM\05MYN1.SGM
05MYN1
Agencies
[Federal Register Volume 79, Number 86 (Monday, May 5, 2014)]
[Notices]
[Pages 25628-25629]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-10217]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2014-0099]
Proposed Revision 0 to Fitness-for-Duty--Construction
AGENCY: Nuclear Regulatory Commission.
ACTION: Standard review plan-draft new section; request for comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is soliciting
public comment on draft NUREG-0800, ``Standard Review Plan for the
Review of Safety Analysis Reports for Nuclear Power Plants: LWR
Edition,'' Section 13.7.2, ``Fitness for Duty--Construction.'' The NRC
seeks comments on the proposed new section of the Standard Review Plan
(SRP), concerning implementation of a Fitness-for-Duty (FFD) program
during construction. The current SRP does not contain guidance on the
review of an applicant's proposed construction FFD program.
DATES: Comments must be filed no later than July 7, 2014. Comments
received after this date will be considered, if it is practical to do
so, but the Commission is able to ensure consideration only for
comments received on or before this date.
ADDRESSES: You may submit comments by any of the following methods
(unless this document describes a different method for submitting
comments on a specific subject):
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2014-0099. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: 3WFN-06-44M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
For additional direction on accessing information and submitting
comments, see ``Accessing Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Wesley W. Held, Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone at 301-415-1583 or email at Wesley.Held@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC-2014-0099 when contacting the NRC
about the availability of information regarding this document. You may
access publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2014-0099.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS Accession number
for the proposed new section of the SRP, Section 13.7.2, ``Fitness for
Duty--Construction,'' is available in ADAMS under accession no.
ML113270035.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2014-0099 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information in comment submissions that you do not want to be publicly
disclosed. The NRC will post all comment submissions at https://www.regulations.gov as well as enter the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
[[Page 25629]]
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submissions. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Further Information
The NRC seeks public comment on the proposed new section of SRP
13.7.2. This section has been developed to assist NRC staff with the
review of applications for certain construction permits, early site
permits, licenses, license amendments, and combined licenses and to
inform new reactor applicants and other affected entities of proposed
SRP guidance regarding an acceptable method by which to evaluate a
proposed FFD program for compliance with Part 26 of Title 10 of the
Code of Federal Regulations (10 CFR).
Following NRC staff evaluation of public comments, the NRC intends
to finalize SRP 13.7.2, Revision 0 in ADAMS and post on the NRC's
public Web site within the link for NUREG-0800. The SRP is guidance for
the NRC staff. The SRP is not a substitute for the NRC regulations, and
compliance with the SRP is not required.
III. Backfitting and Issue Finality
Issuance of this draft SRP, if finalized, would not constitute
backfitting as defined in 10 CFR 50.109 (the Backfit Rule) or otherwise
be inconsistent with the issue finality provisions in 10 CFR Part 52.
The NRC's position is based upon the following considerations.
1. The draft SRP positions, if finalized, would not constitute
backfitting, inasmuch as the SRP is internal guidance to NRC staff.
The SRP provides internal guidance to the NRC staff on how to
review an application for NRC regulatory approval in the form of
licensing. Changes in internal staff guidance are not matters for which
either nuclear power plant applicants or licensees are protected under
either the Backfit Rule or the issue finality provisions of 10 CFR Part
52.
2. The NRC staff has no intention to impose the SRP positions on
existing licensees either now or in the future.
The NRC staff does not intend to impose or apply the positions
described in the draft SRP to existing licenses and regulatory
approvals. Hence, the issuance of a final SRP--even if considered
guidance within the purview of the issue finality provisions in 10 CFR
Part 52--would not need to be evaluated as if it were a backfit or as
being inconsistent with issue finality provisions. If, in the future,
the NRC staff seeks to impose a position in the SRP on holders of
already issued licenses in a manner that does not provide issue
finality as described in the applicable issue finality provision, then
the staff must make the showing as set forth in the Backfit Rule or
address the criteria for avoiding issue finality as described in the
applicable issue finality provision.
3. Backfitting and issue finality do not--with limited exceptions
not applicable here--protect current or future applicants.
Applicants and potential applicants are not, with certain
exceptions, protected by either the Backfit Rule or any issue finality
provisions under 10 CFR Part 52. Neither the Backfit Rule nor the issue
finality provisions under 10 CFR Part 52--with certain exclusions--were
intended to apply to every NRC action that substantially changes the
expectations of current and future applicants. The exceptions to the
general principle are applicable whenever an applicant references a 10
CFR Part 52 license (e.g., an early site permit) and/or NRC regulatory
approval (e.g., a design certification rule) with specified issue
finality provisions. The NRC staff does not, at this time, intend to
impose the positions represented in the draft SRP in a manner that is
inconsistent with any issue finality provisions. If, in the future, the
staff seeks to impose a position in the draft SRP in a manner that does
not provide issue finality as described in the applicable issue
finality provision, then the staff must address the criteria for
avoiding issue finality as described in the applicable issue finality
provision.
Dated at Rockville, Maryland, this 22nd day of April 2014.
For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, Policy Branch, Division of Advanced Reactors and Rulemaking,
Office of New Reactors.
[FR Doc. 2014-10217 Filed 5-2-14; 8:45 am]