Download as PDF 21756 Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP14–131–000] TKELLEY on DSK3SPTVN1PROD with NOTICES WBI Energy Transmission, Inc.; Notice of Request Under Blanket Authorization Take notice that on April 1, 2014, WBI Energy Transmission, Inc. (WBI Energy), 1250 West Century Avenue, Bismarck, North Dakota 58501, filed a prior notice application pursuant to sections 157.205 and 157.211 of the Federal Energy Regulatory Commission’s (Commission) regulations under the Natural Gas Act (NGA), and WBI Energy’s blanket certificate issued in Docket No. CP82–487–000, for authorization to construct and operate delivery point facilities in Stark County, North Dakota. Specifically, WBI Energy seeks authority to construct, own and operate a new meter station that will provide up to 9.744 million cubic feet (MMcf) per day of natural gas service to Dakota Prairie Refining, LLC. Additionally, WBI Energy proposes to relocate the existing Dickson West town border station (Dickson West TBS) and purchase approximately 6,300 feet of existing steel natural gas pipeline from Montana-Dakota (DPR Lateral), all as more fully set forth in the application, which is open to the public for inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application should be directed to Keith A. Tiggelaar, Director of Regulatory Affairs, WBI Energy Transmission, Inc., 1250 West Century Avenue, Bismarck, North Dakota 58503, or (701)-530–1560 or by email keith.tiggelaar@ wbienergy.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a VerDate Mar<15>2010 17:28 Apr 16, 2014 Jkt 232001 protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 Dated: April 11, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–08752 Filed 4–16–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP14–130–000] Equitrans, L.P.; Notice of Request Under Blanket Authorization Take notice that on April 1, 2014, Equitrans, L.P., (Equitrans), 625 Liberty Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222, filed in Docket No. CP14–130–000, a prior notice request pursuant to sections 157.205, 157.208, and 157.210 of the Commission’s regulations under the Natural Gas Act for authorization to construct its proposed H–305 Project located in Greene County, Pennsylvania. Equitrans proposes to install its new H–305 pipeline, which consist of approximately 3.4 miles of 24-inch diameter pipe, extending from Equitrans’ interconnect with EQT Gathering LLC’s Jupiter Compressor Station to Equitrans’ existing Braden Run Interconnect. This project will help expand the Mainline System by up to 50,000 Dth per day, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the Web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this Application should be directed to Paul W. Diehl, Senior Counsel—Midstream, EQT Corporation, 625 Liberty Avenue, Suite 1700, Pittsburgh, PA 15222, or by calling (412) 395–5540, or by email pdiehl@eqt.com. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the NGA (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be E:\FR\FM\17APN1.SGM 17APN1

Agencies

[Federal Register Volume 79, Number 74 (Thursday, April 17, 2014)]
[Notices]
[Page 21756]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-08752]



[[Page 21756]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP14-131-000]


WBI Energy Transmission, Inc.; Notice of Request Under Blanket 
Authorization

    Take notice that on April 1, 2014, WBI Energy Transmission, Inc. 
(WBI Energy), 1250 West Century Avenue, Bismarck, North Dakota 58501, 
filed a prior notice application pursuant to sections 157.205 and 
157.211 of the Federal Energy Regulatory Commission's (Commission) 
regulations under the Natural Gas Act (NGA), and WBI Energy's blanket 
certificate issued in Docket No. CP82-487-000, for authorization to 
construct and operate delivery point facilities in Stark County, North 
Dakota. Specifically, WBI Energy seeks authority to construct, own and 
operate a new meter station that will provide up to 9.744 million cubic 
feet (MMcf) per day of natural gas service to Dakota Prairie Refining, 
LLC. Additionally, WBI Energy proposes to relocate the existing Dickson 
West town border station (Dickson West TBS) and purchase approximately 
6,300 feet of existing steel natural gas pipeline from Montana-Dakota 
(DPR Lateral), all as more fully set forth in the application, which is 
open to the public for inspection. The filing may also be viewed on the 
web at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding this application should be directed to 
Keith A. Tiggelaar, Director of Regulatory Affairs, WBI Energy 
Transmission, Inc., 1250 West Century Avenue, Bismarck, North Dakota 
58503, or (701)-530-1560 or by email keith.tiggelaar@wbienergy.com.
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenter's will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenter's will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.

    Dated: April 11, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-08752 Filed 4-16-14; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.