MMAA104000; Timing Requirements for the Submission of a Site Assessment Plan (SAP) or General Activities Plan (GAP) for a Renewable Energy Project on the Outer Continental Shelf (OCS), 21617-21626 [2014-08488]
Download as PDF
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
Executive Orders 12372 and 13132
This rulemaking will not have
substantial direct effects on the States,
on the relationship between the national
government and the States, or on the
distribution of power and
responsibilities among the various
levels of government. Therefore, in
accordance with Executive Order 13132,
the Department has determined that this
rulemaking does not have sufficient
federalism implications to require
consultations or warrant the preparation
of a federalism summary impact
statement. The regulations
implementing Executive Order 12372
regarding intergovernmental
consultation on Federal programs and
activities do not apply to this
rulemaking.
Executive Orders 12866 and 13563
Executive Orders 12866 and 13563
direct agencies to assess costs and
benefits of available regulatory
alternatives and, if regulation is
necessary, to select regulatory
approaches that maximize net benefits
(including potential economic,
environmental, public health and safety
effects, distributed impacts, and equity).
These executive orders stress the
importance of quantifying both costs
and benefits, of reducing costs, of
harmonizing rules, and of promoting
flexibility. This rule has been
designated a ‘‘significant regulatory
action,’’ although not economically
significant, under section 3(f) of
Executive Order 12866. Accordingly,
this rule has been reviewed by the
Office of Management and Budget
(OMB).
Executive Order 12988
The Department of State reviewed this
rulemaking in light of Executive Order
12988 to eliminate ambiguity, minimize
litigation, establish clear legal
standards, and reduce burden.
wreier-aviles on DSK5TPTVN1PROD with RULES
Executive Order 13175
The Department of State determined
that this rulemaking will not have tribal
implications, will not impose
substantial direct compliance costs on
Indian tribal governments, and will not
preempt tribal law. Accordingly, the
requirements of Executive Order 13175
do not apply to this rulemaking.
Paperwork Reduction Act
This rule does not impose any new
reporting or recordkeeping requirements
subject to the Paperwork Reduction Act,
44 U.S.C. Chapter 35.
List of Subjects in 22 CFR Part 126
Arms and munitions, Exports.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
For the reasons set forth above, Title
22, Chapter I, Subchapter M, part 126 is
amended as follows:
PART 126—GENERAL POLICIES AND
PROVISIONS
1. The authority citation for part 126
continues to read as follows:
■
Authority: Secs. 2, 38, 40, 42, and 71, Pub.
L. 90–629, 90 Stat. 744 (22 U.S.C. 2752, 2778,
2780, 2791, and 2797); 22 U.S.C. 2651a; 22
U.S.C. 287c; E.O. 12918, 59 FR 28205; 3 CFR,
1994 Comp., p. 899; Sec. 1225, Pub. L. 108–
375; Sec. 7089, Pub. L. 111–117; Pub. L. 111–
266; Sections 7045 and 7046, Pub. L. 112–74;
E.O. 13637, 78 FR 16129.
21617
reform, as approved in advance by the
Committee of the Security Council
concerning the Central African
Republic; or
(6) Other sales or supply of arms and
related materiel, or provision of
assistance or personnel, as approved in
advance by the Committee of the
Security Council concerning the Central
African Republic.
*
*
*
*
*
Rose E. Gottemoeller,
Under Secretary, Arms Control and
International Security, Department of State.
[FR Doc. 2014–08781 Filed 4–16–14; 8:45 am]
■
2. Section 126.1(u) is added to read as
follows:
BILLING CODE 4710–25–P
§ 126.1 Prohibited exports, imports, and
sales to or from certain countries.
DEPARTMENT OF THE TREASURY
*
Internal Revenue Service
*
*
*
*
(u) Central African Republic. It is the
policy of the United States to deny
licenses or other approvals for exports
or imports of defense articles and
defense services destined for or
originating in the Central African
Republic, except that a license or other
approval may be issued, on a case-bycase basis, for:
(1) Defense articles intended solely for
the support of or use by the
International Support Mission to the
Central African Republic (MISCA); the
UN Integrated Peacebuilding Office in
the Central African Republic (BINUCA)
and its guard unit, the African Union
Regional Task Force (AU–RTF); and the
French forces and European Union
operation deployed in the Central
African Republic;
(2) Non-lethal military equipment,
and related technical assistance and
training, when intended solely for
humanitarian and protective use, as
approved in advance by the Committee
of the Security Council concerning the
Central African Republic;
(3) Personal protective gear
temporarily exported to the Central
African Republic by United Nations
personnel, representatives of the media,
and humanitarian and developmental
workers and associated personnel, for
their personal use only;
(4) Small arms and related equipment
intended solely for use in international
patrols providing security in the Sangha
River Tri-national Protected Area to
defend against poaching, smuggling of
ivory and arms, and other activities
contrary to the laws of the Central
African Republic or its international
legal obligations;
(5) Arms and related lethal military
equipment for Central African Republic
security forces, intended solely for
support of or use in security sector
PO 00000
Frm 00037
Fmt 4700
Sfmt 4700
26 CFR Part 1
Returns of Information of Brokers and
Barter Exchanges; Furnishing
Statement Required With Respect to
Certain Substitute Payments
CFR Correction
In Title 26 of the Code of Federal
Regulations, Part 1 (§ 1.151 to end of
part 1), revised as of April 1, 2013, on
page 258, § 1.6045–1T is removed, and
on page 263, § 1.6045–2T is removed.
[FR Doc. 2014–08935 Filed 4–16–14; 8:45 am]
BILLING CODE 1505–01–D
DEPARTMENT OF THE INTERIOR
Bureau of Ocean Energy Management
30 CFR parts 585 and 590
[Docket ID: BOEM–2012–0077]
RIN 1010–AD77
MMAA104000; Timing Requirements
for the Submission of a Site
Assessment Plan (SAP) or General
Activities Plan (GAP) for a Renewable
Energy Project on the Outer
Continental Shelf (OCS)
Bureau of Ocean Energy
Management (BOEM), Interior.
ACTION: Final rule.
AGENCY:
This rule amends the timing
requirements for submitting a SAP or
GAP. Under the rule, all OCS renewable
energy leases and grants will have a
preliminary term of 12 months in which
a lessee or grantee must submit a SAP
or a GAP. BOEM is taking this action
because the current regulations provide
timing requirements for submission of
SUMMARY:
E:\FR\FM\17APR1.SGM
17APR1
21618
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
SAPs and GAPs that have proven to be
impractical. In addition, this rule
amends various other regulatory
provisions, such as those pertaining to
a lessee’s first rent payment.
This final rule is effective May
19, 2014.
DATES:
FOR FURTHER INFORMATION CONTACT:
Jennifer Golladay, BOEM Office of
Renewable Energy, at
Jennifer.Golladay@boem.gov or 703–
787–1688.
This rule
increases efficiency and reduces the
burden of regulations, since it extends
the timeframes for lessees and operators
to submit plans and makes it possible
for a Right of Use and Easement (RUE)
to be issued while a GAP is still
pending. BOEM published a proposed
rule soliciting comments in the Federal
Register on February 25, 2013 (78 FR
12676).
SUPPLEMENTARY INFORMATION:
wreier-aviles on DSK5TPTVN1PROD with RULES
Executive Summary
Current BOEM regulations require a
lessee to submit a SAP or a GAP, and
a grantee to submit a GAP, within six
months of lease or grant issuance in
cases where the lease or grant is issued
following completion of a competitive
bidding process. In cases where a lease
or grant is issued on a noncompetitive
basis, the regulations require the
requestor to submit a SAP or GAP
within 60 days after BOEM makes and
publishes a ‘‘Determination of No
Competitive Interest.’’ In
communications with prospective OCS
renewable energy lessees and grantees
that took place after the current
regulations were issued, BOEM learned
that these timeframes—especially the
60-day requirement—are too short, and
that most developers intend to request
departures from the regulatory
requirements pertaining to the timing of
SAP and GAP submissions. In part, this
is because site characterization activities
necessary to support the submission of
a SAP or GAP are significantly affected
and controlled by seasonal weather
conditions. This rule addresses the
difficulties associated with the current
timing requirements by lengthening the
timeframe for submission of SAPs and
GAPs to 12 months following lease/
grant issuance for both competitivelyissued and noncompetitively-issued
leases and grants.
This rule makes various
administrative corrections and
clarifications to BOEM’s renewable
energy regulations.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
Summary of Changes
30 CFR Part 585
This rule amends the timing
requirements for submitting a SAP or
GAP pursuant to the regulations
governing renewable energy and
alternate uses of existing facilities on
the OCS in 30 CFR part 585. Under the
rule, all OCS renewable energy leases
and grants would have a preliminary
term of 12 months in which the lessee
or grantee must submit a SAP or a GAP.
BOEM is proposing these changes
because the current regulations specify
timing requirements for submission of
SAPs and GAPs that have proven to be
impractical. This rule addresses the
difficulties associated with the current
timing requirements by lengthening the
timeframe for submission of SAPs and
GAPs to 12 months following lease/
grant issuance in all cases for both
competitively-issued and
noncompetitively-issued leases and
grants.
Changes Made Between Proposed and
Final Rule
In the proposed rule, BOEM proposed
to add definitions of the terms ‘‘CZMA
State’’ and ‘‘State CZMA Agency’’ to the
regulations. This was intended to enable
BOEM to clarify which regulatory
provisions apply to states with rights
and responsibilities under the Coastal
Zone Management Act, as opposed to
the states that fall under the general
definition of ‘‘Affected State’’ under the
Outer Continental Shelf Lands Act
(OCSLA). However, the definition of
‘‘Affected State’’ in BOEM’s renewable
energy regulations is different from the
definition in OCSLA, and ‘‘Affected
State’’ is not used in the regulations
describing the CZMA compliance
process (e.g., 30 CFR 585.612, 628, and
647). After receiving comments and
considering the potential changes
further, BOEM decided against adding
the new definitions, since the proposed
additions would likely have caused
confusion and redundancy rather than
clarity. The current regulations at 30
CFR part 585 include a definition of
‘‘affected state’’ that fully addresses the
needs of BOEM’s renewable energy
program. Therefore, BOEM will
continue to use the term ‘‘affected state’’
in the following sections: 30 CFR
585.102, 585.112, 585.203, 585.211,
585.231, 585.238, 585.306, and 585.902
to implement this decision.
In addition to the changes to the
proposed rule which are discussed in
the section ‘‘Response to Comments
Matrix and Other Preamble Text,’’ the
following clarifying edits and/or
PO 00000
Frm 00038
Fmt 4700
Sfmt 4700
technical corrections have been made to
the current regulations:
• 30 CFR 585.112—BOEM made
minor changes that expand the
definition of ‘‘you and your’’ to include
designated agents of all entities listed,
and corrected a minor grammatical error
in this definition.
• 30 CFR 585.203—BOEM made a
small grammatical edit to the last
sentence.
• 30 CFR 585.211—BOEM made a
small grammatical edit and a small
wording change to the first sentence in
(c).
• 30 CFR 585.224—BOEM edited this
provision to ensure consistency with 30
CFR 585.503 regarding a lessee’s first
rent payment, and made a small
grammatical edit.
• 30 CFR 585.231—BOEM made
small changes and some grammatical
edits in (d), (e), and (f), and changed the
number of months of rent owed in (g)(2).
• 30 CFR 585.235—BOEM made
small wording changes in (a)(1), (a)(3),
and (a)(4), clarified the language about
the start of the operations term in the
event a SAP/Construction and
Operations Plan (COP) is submitted in
(a)(3), and moved text from the second
to third column in (a)(4).
• 30 CFR 585.236—BOEM
reformatted the table slightly.
• 30 CFR 585.303—BOEM edited (a)
to make a small grammatical change and
mirror the title of the provision in the
regulatory text, and added clarifying
language in (b).
• 30 CFR 585.500, 503, and 505—
BOEM coordinated with the Department
of the Interior’s Office of Natural
Resources Revenue (ONRR) and
determined that certain citations to the
ONRR regulations in the proposed rule
were incorrect. Accordingly, sections
500(a) & (b), 503 (a)(1) and 505(b) were
revised. In addition, edits were made to
ensure consistency with requirements in
other regulatory provisions and to
effectively communicate to lessees how
to make first-year rent payments. BOEM
also made a small grammatical edit in
30 CFR 585.500.
• 30 CFR 585.611—BOEM edited this
provision to align the language with
BOEM’s standard for determining if
previous environmental analyses
adequately cover the proposed activities
for environmental review purposes by,
for example, replacing ‘‘substantially
inconsistent’’ with ‘‘significantly
different.’’ Additionally, BOEM made
small grammatical edits and eliminated
the passive voice.
• 30 CFR 585.612—In this section,
and in all other sections where the term
‘‘State CZM agency’’ was used, BOEM
replaced this term with a new reference
E:\FR\FM\17APR1.SGM
17APR1
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
to ‘‘applicable State CZMA agency or
agencies,’’ consistent with the approach
used in new text included in 30 CFR
585.306 and 231. BOEM also changed
the wording in the first row of the table.
• 30 CFR 585.627—BOEM edited (a)
to eliminate the references to
competitive and noncompetitive leasing
and make small grammatical changes,
and corrected statutory and regulatory
references in (b).
• 30 CFR 585.628—BOEM edited (c)
to: (1) Provide consistent terminology
(‘‘applicable State CZMA agency or
agencies’’) and, (2) clarify that the
developer is responsible for providing
this set of information to the applicable
State CZMA agency or agencies in the
event that the COP is submitted to
BOEM prior to lease issuance, pursuant
to 15 CFR part 930, subpart D.
• 30 CFR 585.646—BOEM made
small changes to (a) of this provision to
ensure that the text mirrors the language
in 30 CFR 585.611 and to eliminate the
passive voice. BOEM edited (b) to align
the language with BOEM’s standard for
determining if previous environmental
analyses adequately cover the proposed
activities for environmental review
purposes by, for example, replacing
‘‘substantially inconsistent’’ with
‘‘significantly different,’’ to remove an
unnecessary reference to CZMA, to
make small grammatical changes, and to
eliminate the passive voice.
• 30 CFR 585.647—BOEM changed
some of the wording to align with the
new text included in 30 CFR 585.306
and 231, (‘‘applicable State CZMA
agency or agencies’’), to fix an incorrect
regulatory citation, and to change the
wording in the first row of the table.
Finally, BOEM made certain other
changes to the regulatory text included
in the proposed rule based on comments
received, as described below in the
Response to Comments Matrix.
Legal Authority
The authority for this rulemaking is
the broad rulemaking provision of the
OCSLA, as set forth in 43 U.S.C.
1334(a), that authorizes the Secretary of
the Interior to prescribe and amend such
rules and regulations as may be
necessary to administer a leasing
program, or necessary and proper in
order to provide for the prevention of
waste and conservation of natural
resources of the OCS.
Section 8(p)(8) of OCSLA (43 U.S.C.
1337(p)(8)) provides authority for the
portion of this rulemaking dealing with
the production, transportation, or
21619
transmission of energy from sources
other than oil and gas, and alternate
uses of the OCS, which authorizes the
Secretary to issue any necessary
regulations to carry out subsection 8(p)
of OCSLA.
Response to Comments Matrix and
Other Preamble Text
BOEM published a proposed rule
entitled, ‘‘Timing Requirements for the
Submission of a Site Assessment Plan
(SAP) or a General Activities Plan (GAP)
for a Renewable Energy Project on the
Outer Continental Shelf (OCS)’’ in the
Federal Register on February 25, 2013,
with a 30-day request for comments
period.
BOEM received nine comment letters
from interested stakeholders, and
carefully considered them prior to
finalizing the rulemaking. Generally,
commenters were supportive of
extending the timing requirements for
developers to submit SAPs and GAPs.
Some comments suggested edits to the
text of the rulemaking, requested
clarifications as to the applicability of
the rulemaking, and/or raised questions
about the necessity of the rulemaking.
Responses to those comments are
contained in the table below.
Comment received
BOEM response
BOEM should revise the definition of the term ‘‘CZMA State’’ by cross
referencing the National Oceanic and Atmospheric Administration’s
Office of Ocean and Coastal Resource Management’s Federal consistency rules.
BOEM should not require that a developer submitting an unsolicited request for a lease or grant include in the request a consistency certification and associated necessary data and information pursuant to
CZMA regulations at 15 CFR part 930 subpart D.
BOEM has decided against adding the new term ‘‘CZMA State’’ in this
rulemaking.
wreier-aviles on DSK5TPTVN1PROD with RULES
The proposed rule should address cable-related easements early at the
lease sale or SAP or GAP stage, rather than later as part of a COP.
BOEM should edit 30 CFR 585.102 to bring it into conformity with 30
CFR 585.203, such that the first sentence of 30 CFR 585.102(e)
uses ‘‘and’’ instead of ‘‘or.’’
The new proposed 30 CFR 585.612(b) should refer to 15 CFR part 930
instead of 15 CFR part 93.
To avoid confusion, BOEM should clarify that BOEM regulations (see
30 CFR 585.231 and 585.306) regarding the applicable CZMA consistency review process do not apply to pending lease applications
for which BOEM has issued a determination of no competitive interest prior to this rule’s effective date.
Please provide more detail on the number of SAPs and GAPs that
have been filed, the bureau’s use of this information, the actions
taken against any companies that have filed plans late, and any requests to change these filing deadlines.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
PO 00000
Frm 00039
Fmt 4700
BOEM has made this requested change and accordingly will not add
this requirement to 30 CFR 585.230 or 585.305. These developers
are now required to submit a consistency certification and the associated necessary data and information under CZMA only after BOEM
has determined that there is no competitive interest in the proposed
project.
BOEM did not make this requested change. The agency believes that
it would be premature to consider and analyze cable locations until
commercial wind lessees have conducted necessary surveys and
lessees are able to consider the layout of their commercial projects
when making siting decisions about transmission cables.
BOEM made this requested change.
BOEM made this requested change.
BOEM will address any such confusion with the appropriate parties on
a project-by-project basis.
At the time that this proposed rulemaking was published, BOEM had
only received one such plan. However, after receiving (1) informal
feedback on these timing requirements from industry and (2) requests to depart from these timing requirements pursuant to 30 CFR
585.103, BOEM came to the conclusion that the existing timing requirements were impractical. The comments received in response to
the proposed rulemaking were generally supportive of extending the
required timelines for plan submission.
Sfmt 4700
E:\FR\FM\17APR1.SGM
17APR1
21620
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
Procedural Matters
wreier-aviles on DSK5TPTVN1PROD with RULES
Regulatory Planning and Review
(Executive Orders 12866 and 13563)
Executive Order 12866 provides that
the Office of Information and Regulatory
Affairs (OIRA) will review all significant
rules. The Office of Information and
Regulatory Affairs has determined that
this rule is not significant.
Executive Order 13563 reaffirms the
principles of E.O. 12866 while calling
for improvements in the nation’s
regulatory system to promote
predictability, to reduce uncertainty,
and to use the best, most innovative,
and least burdensome tools for
achieving regulatory ends. The
executive order directs agencies to
consider regulatory approaches that
reduce burdens and maintain flexibility
and freedom of choice for the public
where these approaches are relevant,
feasible, and consistent with regulatory
objectives. E.O. 13563 emphasizes
further that regulations must be based
on the best available science and that
the rulemaking process must allow for
public participation and an open
exchange of ideas. BOEM has developed
this rule in a manner consistent with
these requirements.
This rule is not a significant rule as
determined by the Office of
Management and Budget (OMB) and is
not subject to review under E.O. 12866.
For the most part, this rule makes
administrative corrections and
clarifications to the existing regulations.
Other changes consist of the
reorganization of selected renewable
energy regulations.
Because this rule makes only minor
alterations and changes to requirements
for leasing, compliance, or enforcement
from those set forth in existing
regulations, no costs are estimated for
this rulemaking.
(1) This rule will not have an annual
effect of $100 million or more on the
economy. It would not adversely affect
in a material way the economy,
productivity, competition, jobs, the
environment, public health or safety, or
State, local, or tribal governments or
communities.
(2) This rule will not create a serious
inconsistency or otherwise interfere
with an action taken or planned by
another agency.
(3) This rule will not alter the
budgetary effects of entitlements, grants,
user fees, or loan programs or the rights
or obligations of their recipients.
(4) This rule will not raise novel legal
or policy issues arising out of legal
mandates, the President’s priorities, or
the principles set forth in E.O. 12866.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
Regulatory Flexibility Act
The Department of the Interior
certifies that this rule will not have a
significant economic effect on a
substantial number of small entities
under the Regulatory Flexibility Act (5
U.S.C. 601 et seq.). This rulemaking will
affect large and small entities through
the clarification of the existing
regulatory requirements under the
reorganized regulations of part 585.
Your comments are important. The
Small Business and Agriculture
Regulatory Enforcement Ombudsman
and ten Regional Fairness Boards were
established to receive comments from
small businesses about Federal agency
enforcement actions. The Ombudsman
will annually evaluate the enforcement
activities and rate each agency’s
responsiveness to small business. If you
wish to comment on the actions of
BOEM, call 1–888–734–3247. You may
comment to the Small Business
Administration without fear of
retaliation. Allegations of
discrimination/retaliation filed with the
Small Business Administration will be
investigated for appropriate action.
Small Business Regulatory Enforcement
Fairness Act
This rule is not a major rule under the
Small Business Regulatory Enforcement
Fairness Act (5 U.S.C. 801 et seq.). This
rule:
(a) Will not have an annual effect on
the economy of $100 million or more.
(b) Will not cause a major increase in
costs or prices for consumers,
individual industries, Federal, state, or
local government agencies, or
geographic regions.
(c) Will not have significant adverse
effects on competition, employment,
investment, productivity, innovation, or
the ability of U.S.-based enterprises to
compete with foreign-based enterprises.
The requirements apply to all entities
operating to develop renewable
resources on the OCS.
Unfunded Mandates Reform Act of 1995
This rule does not impose an
unfunded mandate on state, local, or
tribal governments, or the private sector,
of more than $100 million per year. This
rule does not have a significant or
unique effect on state, local, or tribal
governments, or the private sector. A
statement containing the information
required by the Unfunded Mandates
Reform Act (2 U.S.C. 1501 et seq.) is not
required.
Takings Implication Assessment (E.O.
12630)
Under the criteria in E.O. 12630, this
rule will not have significant takings
PO 00000
Frm 00040
Fmt 4700
Sfmt 4700
implications. This rule will not be a
governmental action capable of
interference with constitutionally
protected property rights. A Takings
Implication Assessment is not required.
Federalism (E.O. 13132)
Under the criteria in E.O. 13132, this
rule will not have federalism
implications. This rule will not
substantially affect the relationship
between the Federal and state
governments. To the extent that state
and local governments have a role in
OCS activities, this rule will not affect
that role. A Federalism Assessment is
not required.
Civil Justice Reform (E.O. 12988)
This rule complies with the
requirements of E.O. 12988.
Specifically, this rule:
(a) Meets the criteria of section 3(a)
requiring that all regulations be
reviewed to eliminate errors and
ambiguity and be written to minimize
litigation; and (b) Meets the criteria of
section 3(b)(2) requiring that all
regulations be written in clear language
and contain clear legal standards.
Consultation With Indian Tribes (E.O.
13175)
Under the criteria in E.O. 13175,
BOEM has evaluated this rule and
determined that it will have no
substantial effects on federally
recognized Indian tribes.
Paperwork Reduction Act (PRA) of 1995
This rule does not contain new
information collection requirements,
and a submission under the PRA is not
required. Therefore, an information
collection request is not being submitted
to the Office of Management and Budget
(OMB) for review and approval under
44 U.S.C. 3501 et seq. The rule refers to,
but does not change, the information
collection requirements in 30 CFR 585.
The OMB has approved the referenced
information collection under OMB
Control Number 1010–0176 (30,902
hours and $3,816,000 non-hour cost
burden).
National Environmental Policy Act of
1969
This rule does not constitute a major
Federal action significantly affecting the
quality of the human environment.
BOEM evaluated this rule under the
criteria of the National Environmental
Policy Act, 43 CFR Part 46 and 516
Departmental Manual 15. The issuance
of this rule is categorically excluded
from NEPA review because it meets the
criteria set forth in 43 CFR 46.210(i) in
that this rule is ‘‘. . . of an
E:\FR\FM\17APR1.SGM
17APR1
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
administrative, financial, legal,
technical, or procedural nature . . .’’
Furthermore, we have evaluated this
rule to determine if it involves any of
the extraordinary circumstances that
would require an environmental
assessment or an environmental impact
statement as set forth in 43 CFR 46.215.
We concluded that this rule does not
meet any of the criteria for extraordinary
circumstances as set forth in 516
Departmental Manual 2 (Appendix 2).
Data Quality Act
In developing this rule, we did not
conduct or use a study, experiment, or
survey requiring peer review under the
Data Quality Act (Pub. L. 106–554, app.
C sec. 515, 114 Stat. 2763, 2763A–153–
154).
Effects of the Nation’s Energy Supply
(E.O. 13211)
Clarity of This Regulation
We are required by E.O. 12866, E.O.
12988, and by the Presidential
Memorandum of June 1, 1998, to write
all rules in plain language. This means
that each rule we publish must:
(a) Be logically organized;
(b) Use the active voice to address
readers directly;
(c) Use clear language rather than
jargon;
(d) Be divided into short sections and
sentences; and
(e) Use lists and tables wherever such
lists or tables would be helpful.
If you feel that we have not met these
requirements, send your comments to
Mr. Loren Thompson, Regulatory
Liaison Officer, Office of Policy,
Regulations and Analysis, Bureau of
Ocean Energy Management, U.S.
Department of the Interior, 1849 C St.
NW., Washington, DC 20240 or to
Loren.Thompson@boem.gov.
List of Subjects
wreier-aviles on DSK5TPTVN1PROD with RULES
30 CFR Part 585
Assessment plans, Coastal zone,
Continental shelf, Electric power,
Energy, Environmental impact
statements, Environmental protection,
Incorporation by reference, Offshore
energy, Marine resources, Natural
resources, Planning, Public lands,
Public lands—rights-of-way, Renewable
energy, Reporting and recordkeeping
requirements, Revenue sharing, Solar
energy, Wind energy.
14:50 Apr 16, 2014
Jkt 232001
Dated: April 7, 2014.
Tommy P. Beaudreau,
Principal Deputy Assistant Secretary, Land
and Minerals Management.
For the reason stated in the preamble,
the Bureau of Ocean Energy
Management amends 30 CFR chapter V
as follows:
PART 585—RENEWABLE ENERGY
AND ALTERNATE USES OF EXISTING
FACILITIES ON THE OUTER
CONTINENTAL SHELF
1. The authority citation for part 585
continues to read as follows:
■
Authority: 43 U.S.C. 1331 et seq.; 43
U.S.C. 1337.
2. Amend § 585.102 by revising
paragraph (e) to read as follows:
■
This rule is not a significant energy
action under the definition in E.O.
13211. A Statement of Energy Effects is
not required.
VerDate Mar<15>2010
30 CFR Part 590
Administrative practice and
procedure, Appeals, Payments.
§ 585.102 What are BOEM’s
responsibilities under this part?
*
*
*
*
*
(e) BOEM will provide for
coordination and consultation with the
Governor of any State, the executive of
any local government, and the executive
of any Indian Tribe that may be affected
by a lease, easement, or ROW under this
subsection. BOEM may invite any
affected State Governor, representative
of an affected Indian Tribe, and affected
local government executive to join in
establishing a task force or other joint
planning or coordination agreement in
carrying out our responsibilities under
this part.
■ 3. Amend § 585.112 by revising the
definition of ‘‘You and your’’ to read as
follows:
§ 585.112
Definitions.
*
*
*
*
*
You and your means an applicant,
lessee, the operator, or designated
operator, ROW grant holder, RUE grant
holder, or Alternate Use RUE grant
holder under this part, or the designated
agent of any of these, or the possessive
of each, depending on the context. The
terms You and your also include
contractors and subcontractors of the
entities specified in the preceding
sentence.
*
*
*
*
*
■ 4. Revise § 585.203 to read as follows:
§ 585.203 With whom will BOEM consult
before issuance of a lease?
For leases issued under this part,
through either the competitive or
noncompetitive process, BOEM, prior to
issuing the lease, will coordinate and
consult with relevant Federal agencies
PO 00000
Frm 00041
Fmt 4700
Sfmt 4700
21621
(including, in particular, those agencies
involved in planning activities that are
undertaken to avoid or minimize
conflicts among users and maximize the
economic and ecological benefits of the
OCS, including multifaceted spatial
planning efforts), the Governor of any
affected State, the executive of any
affected local government, and any
affected Indian Tribe, as directed by
subsections 8(p)(4) and (7) of the OCS
Lands Act or other relevant Federal
laws. Federal statutes that require
BOEM to consult with interested parties
or Federal agencies or to respond to
findings of those agencies, including the
Endangered Species Act (ESA) and the
Magnuson-Stevens Fishery
Conservation and Management Act
(MSA). BOEM also engages in
consultation with state and tribal
historic preservation officers pursuant
to the National Historic Preservation Act
(NHPA).
■ 5. Amend § 585.211 by revising
paragraph (c) to read as follows:
§ 585.211 What is the process for the
competitive issuance of leases?
*
*
*
*
*
(c) Proposed Sale Notice. BOEM will
publish the Proposed Sale Notice in the
Federal Register and send it to the
Governor of any affected State, any
Indian Tribe that might be affected, and
the executive of any local government
that might be affected. The comment
period following issuance of a Proposed
Sale Notice will be 60 days.
*
*
*
*
*
■ 6. Amend § 585.212 by revising
paragraph (a) to read as follows:
§ 585.212 What is the process BOEM will
follow if there is reason to believe that
competitors have withdrawn before the
Final Sale Notice is issued?
*
*
*
*
*
(a) If, after reviewing comments in
response to the notice of Request for
Interest, BOEM determines that there is
no competitive interest in the lease area,
and one party wishes to acquire a lease,
we will discontinue the competitive
process and will proceed with the
noncompetitive process set forth in
§ 585.231(d) through (i) following
receipt of the acquisition fee specified
in § 585.502(a).
*
*
*
*
*
■ 7. Amend § 585.224 by revising
paragraph (b) to read as follows:
§ 585.224
my bid?
What happens if BOEM accepts
*
*
*
*
*
(b) Within 45 days after you receive
the lease copies, you must pay the first
E:\FR\FM\17APR1.SGM
17APR1
21622
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
12-months’ rent as required in
§ 585.503.
*
*
*
*
*
■ 8. Amend § 585.231 by revising
paragraphs (d), (e), (f), and (g)(2) to read
as follows:
§ 585.231 How will BOEM process my
unsolicited request for a noncompetitive
lease?
*
*
*
*
*
(d) If BOEM determines that there is
no competitive interest in a lease, we
will publish in the Federal Register a
notice of Determination of No
Competitive Interest. After BOEM
publishes this notice, you will be
responsible for submitting any required
consistency certification and necessary
data and information pursuant to 15
CFR part 930, subpart D to the
applicable State CZMA agency or
agencies and BOEM.
(e) BOEM will coordinate and consult
with affected Federal agencies, State,
and local governments, and affected
Indian tribes in the review of
noncompetitive lease requests.
(f) After completing the review of
your lease request, BOEM may offer you
a noncompetitive lease.
(g) * * *
(2) Within 45 days after you receive
the lease copies, you must pay the first
12-months’ rent, as required in
§ 585.503.
*
*
*
*
*
9. Amend § 585.235 by revising
paragraph (a) to read as follows:
■
§ 585.235 If I have a commercial lease,
how long will my lease remain in effect?
(a) For commercial leases, the lease
terms and applicable automatic
extensions are as shown in the
following table:
Lease term
Automatic extensions
Requirements
(1) Each commercial lease will have a
preliminary term of 12 months, within
which the lessee must submit: (i) a
SAP; or (ii) a combined SAP and
Construction and Operations Plan
(COP). The preliminary term begins
on the effective date of the lease.
(2) A commercial lease will have a site
assessment term of five years to conduct site assessment activities and to
submit a COP, if a SAP/COP has not
been submitted. Your site assessment
term begins when BOEM approves
your SAP or SAP/COP.
(3) A commercial lease will have an operations term of 25 years, unless a
longer term is negotiated by the parties. A request for lease renewal must
be submitted two years before the
end of the operations term. If you submit a COP, your operations term begins on the date that BOEM approves
the COP. If you submit a SAP/COP,
your operations term begins on the
earliest of the following dates: five
years after BOEM approves the SAP/
COP; when fabrication begins; or,
when installation commences.
(4) A commercial lease may have additional time added to the operations
term through a lease renewal. The
term of the lease renewal will not exceed the original term of the lease,
unless a longer term is negotiated by
the parties. The lease renewal term
begins upon expiration of the original
operations term.
If BOEM receives a SAP that satisfies the requirements of
§§ 585.605 through 585.613 or a SAP/COP that satisfies
the requirements of §§ 585.605 through 585.613 and
§§ 585.620 through 585.629, the preliminary term will be
extended for the time necessary for us to conduct technical and environmental reviews of the SAP or SAP/COP.
The SAP must meet the requirements
of §§ 585.605 through 585.613. The
SAP/COP must meet the requirements of §§ 585.605 through 585.613
and §§ 585.620 through 585.629.
If we receive a COP that satisfies the requirements of
§§ 585.620 through 585.629, the site assessment term
will be automatically extended for the period of time necessary for us to conduct technical and environmental reviews of the COP.
The COP must meet the requirements
of §§ 585.620 through 585.629 of this
part.
...........................................................................................
The lease renewal request must meet
the requirements in §§ 585.425
through 585.429.
...........................................................................................
NOTE: BOEM may also order or grant
a suspension of the operations term,
as provided in §§ 585.415 through
585.421 thereby effectively extending
the term of the lease.
*
*
*
*
*
10. Amend § 585.236 by revising
paragraph (a) to read as follows:
■
§ 585.236 If I have a limited lease, how
long will my lease remain in effect?
(a) For limited leases, the lease terms
are as shown in the following table:
wreier-aviles on DSK5TPTVN1PROD with RULES
Lease term
Extension or suspension
Requirements
(1) Each limited lease has a preliminary
term of 12 months to submit a GAP.
The preliminary term begins on the effective date of the lease.
If we receive a GAP that satisfies the requirements of
§§ 585.640 through 585.648 of this part, the preliminary
term will be automatically extended for the period of time
necessary for us to conduct a technical and environmental review of the plans.
The GAP must meet the requirements
of §§ 585.640 through 585.648.
PO 00000
17APR1
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
Frm 00042
Fmt 4700
Sfmt 4700
E:\FR\FM\17APR1.SGM
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
Lease term
Extension or suspension
(2) Each limited lease has an operations
term of five years for conducting site
assessment, technology testing, or
other activities. The operations term
begins on the date that we approve
your GAP.
We may order or grant a suspension of the operations term
as provided in §§ 585.415 through 585.421.
*
*
*
*
*
11. Revise § 585.303 to read as
follows:
14. Amend § 585.500 by revising
paragraphs (a) and (b) to read as follows:
■
■
§ 585.303 How long will my ROW grant or
RUE grant remain in effect?
(a) Each ROW or RUE grant will have
a preliminary term of 12 months from
the date of issuance of the ROW or RUE
grant within which to submit a GAP.
The preliminary term begins on the
effective date of the grant. You must
submit a GAP no later than the end of
the preliminary term for your grant to
remain in effect. However, you may
submit a GAP prior to the issuance of
your ROW or RUE grant.
(b) Except as described in paragraph
(a) of this section, your ROW grant or
RUE grant will remain in effect for as
long as the associated activities are
properly maintained and used for the
purpose for which the grant was made,
unless otherwise expressly stated in the
grant.
■ 12. Amend § 585.306 by revising
paragraph (b) and by removing
paragraph (c).
The revision reads as follows:
§ 585.306 What action will BOEM take on
my request?
*
*
*
*
*
(b) If BOEM determines that there is
no competitive interest in a ROW grant
or RUE grant, we will publish a notice
in the Federal Register of such
determination. After BOEM publishes
this notice, you will be responsible for
submitting any required consistency
certification and necessary data and
information pursuant to 15 CFR part
930, subpart D to the applicable State
CZMA agency or agencies and BOEM.
We will establish terms and conditions
for the grant in consultation with you.
■ 13. Amend § 585.309 by revising the
introductory text to read as follows:
§ 585.309 When will BOEM issue a
noncompetitive ROW grant or RUE grant?
wreier-aviles on DSK5TPTVN1PROD with RULES
21623
After completing the review of your
grant request, BOEM may offer you a
noncompetitive grant.
*
*
*
*
*
§ 585.500 How do I make payments under
this part?
(a) For acquisition fees or the initial
12-months’ rent paid for the preliminary
term of your lease, you must make your
electronic payments through the Fees
for Services page on the BOEM Web site
at https://www.boem.gov, and you must
include one copy of the Pay.gov
confirmation receipt page with your
unsolicited request.
(b) For all other required rent
payments and for operating fee
payments, you must make your
payments as required in 30 CFR
1218.51.
*
*
*
*
*
15. Amend § 585.503 by revising
paragraph (a)(1) to read as follows:
■
§ 585.503 What are the rent and operating
fee requirements for a commercial lease?
(a) * * *
(1) You must pay ONRR the initial 12months’ rent 45 days after you receive
the lease copies from BOEM in
accordance with the requirements
provided in § 585.500(a).
*
*
*
*
*
16. Amend § 585.505 by revising
paragraph (b) to read as follows:
■
§ 585.505 What are the rent and operating
fee requirements for a limited lease?
*
*
*
*
*
(b) You must pay ONRR the initial 12months’ rent 45 days after you receive
the lease copies from BOEM in
accordance with the requirements
provided in § 585.500(a).
*
*
*
*
*
17. Amend § 585.601 by:
a. Revising the introductory text and
paragraph (a);
■ b. Removing paragraph (b);
■ c. Re-designating paragraphs (c) and
(d) as paragraphs (b) and (c).
The revisions read as follows:
■
■
Requirements
§ 585.601 When am I required to submit
my plans to BOEM?
You must submit your plans as
follows:
(a) You may submit your SAP or GAP
prior to lease or grant issuance, but must
submit your SAP or your GAP no later
than 12 months from the date of lease
or grant issuance.
*
*
*
*
*
18. Revise § 585.611 to read as
follows:
■
§ 585.611 What information and
certifications must I submit with my SAP to
assist BOEM in complying with NEPA and
other relevant laws?
You must submit, with your SAP,
detailed information to assist BOEM in
complying with NEPA and other
relevant laws as appropriate.
(a) A SAP submitted for an area in
which BOEM has not previously
reviewed site assessment activities
under NEPA or other applicable Federal
laws, must describe those resources,
conditions, and activities listed in the
following table that could be affected by
your proposed activities or that could
affect the activities proposed in your
SAP.
(b) For a SAP submitted for an area in
which BOEM has previously considered
site assessment activities under
applicable Federal law (e.g., a NEPA
analysis and CZMA consistency
determination for site assessment
activities), BOEM will review the SAP
to determine if its impacts are consistent
with those previously considered. If the
anticipated effects of your proposed
SAP activities are significantly different
than those previously anticipated, we
may determine that additional NEPA
and other relevant Federal reviews are
required. In that case, BOEM will notify
you of such determination, and you
must submit a SAP that describes those
resources, conditions, and activities
listed in the following table that could
be affected by your proposed activities
or that could affect the activities
proposed in your SAP, including:
Type of information:
Including:
(1) Hazard information ....................
(2) Water quality .............................
Meteorology, oceanography, sediment transport, geology, and shallow geological or manmade hazards.
Turbidity and total suspended solids from construction.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
PO 00000
Frm 00043
Fmt 4700
Sfmt 4700
E:\FR\FM\17APR1.SGM
17APR1
21624
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
Type of information:
Including:
(3) Biological resources ..................
Benthic communities, marine mammals, sea turtles, coastal and marine birds, fish and shellfish, plankton,
sea grasses, and other plant life.
As required by the Endangered Species Act (ESA) of 1973 (16 U.S.C. 1531 et seq.).
(4) Threatened or endangered species.
(5) Sensitive biological resources or
habitats.
(6) Archaeological resources ..........
(7) Social and economic conditions
(8) Coastal and marine uses ..........
(9) Consistency Certification ...........
(10) Other resources, conditions,
and activities.
Essential fish habitat, refuges, preserves, special management areas identified in coastal management
programs, sanctuaries, rookeries, hard bottom habitat, chemosynthetic communities, calving grounds,
barrier islands, beaches, dunes, and wetlands.
As required by the NHPA (16 U.S.C. 470 et seq.), as amended.
Employment, existing offshore and coastal infrastructure (including major sources of supplies, services, energy, and water), land use, subsistence resources and harvest practices, recreation, recreational and
commercial fishing (including typical fishing seasons, location, and type), minority and lower income
groups, coastal zone management programs, and viewshed.
Military activities, vessel traffic, and energy and nonenergy mineral exploration or development.
If required by CZMA, as appropriate: (i) 15 CFR part 930, subpart D, if the SAP is submitted prior to lease
issuance; (ii) 15 CFR part 930, subpart E, if the SAP is submitted after lease issuance.
As identified by BOEM.
§ 585.612 How will my SAP be processed
for Federal consistency under theCoastal
Zone Management Act?
19. Revise § 585.612 to read as
follows:
■
Your SAP will be processed based on
whether it is submitted before or after
your lease is issued:
If your SAP is submitted:
Consistency review of your SAP will be handled as follows:
(a) Before lease issuance ...............
You will furnish a copy of your SAP, consistency certification, and necessary data and information pursuant to 15 CFR part 930, subpart D, to the applicable State CZMA agency or agencies and BOEM at the
same time.
You will submit a copy of your SAP, consistency certification, and necessary data and information pursuant
to 15 CFR part 930, subpart E to BOEM. BOEM will forward to the applicable State CZMA agency or
agencies one paper copy and one electronic copy of your SAP, consistency certification, and necessary
data and information required under 15 CFR part 930, subpart E, after BOEM has determined that all information requirements for the SAP are met.
(b) After lease issuance ..................
20. Amend § 585.627 by revising
paragraphs (a) and (b) to read as follows:
■
§ 585.627 What information and
certifications must I submit with my COP to
assist the BOEM in complying with NEPA
and other relevant laws?
(a) You must submit with your COP
detailed information to assist BOEM in
complying with NEPA and other
relevant laws. Your COP must describe
those resources, conditions, and
activities listed in the following table
that could be affected by your proposed
activities, or that could affect the
activities proposed in your COP,
including:
Type of information:
Including:
(1) Hazard information ....................
(2) Water quality .............................
(3) Biological resources ..................
Meteorology, oceanography, sediment transport, geology, and shallow geological or manmade hazards.
Turbidity and total suspended solids from construction.
Benthic communities, marine mammals, sea turtles, coastal and marine birds, fish and shellfish, plankton,
seagrasses, and plant life.
As defined by the ESA (16 U.S.C. 1531 et seq.).
(4) Threatened or endangered species.
(5) Sensitive biological resources or
habitats.
wreier-aviles on DSK5TPTVN1PROD with RULES
(6) Archaeological resources ..........
(7) Social and economic resources
(8) Coastal and marine uses ..........
(9) Consistency Certification ...........
(10) Other resources, conditions,
and activities.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Essential fish habitat, refuges, preserves, special management areas identified in coastal management
programs, sanctuaries, rookeries, hard bottom habitat, chemosynthetic communities, calving grounds,
barrier islands, beaches, dunes, and wetlands.
As required by the NHPA (16 U.S.C. 470 et seq.), as amended.
Employment, existing offshore and coastal infrastructure (including major sources of supplies, services, energy, and water), land use, subsistence resources and harvest practices, recreation, recreational and
commercial fishing (including typical fishing seasons, location, and type), minority and lower income
groups, coastal zone management programs, and viewshed.
Military activities, vessel traffic, and energy and nonenergy mineral exploration or development.
As required by the CZMA regulations:
(i) 15 CFR part 930, subpart D, if your COP is submitted before lease issuance.
(ii) 15 CFR part 930, subpart E, if your COP is submitted after lease issuance.
As identified by BOEM.
Jkt 232001
PO 00000
Frm 00044
Fmt 4700
Sfmt 4700
E:\FR\FM\17APR1.SGM
17APR1
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
(b) You must submit one paper copy
and one electronic copy of your
consistency certification. Your
consistency certification must include:
(1) One copy of your consistency
certification under either subsection
307(c)(3)(B) of the CZMA (16 U.S.C.
1456(c)(3)(B)) and 15 CFR 930.76 or
subsection 307(c)(3)(A) of the CZMA (16
U.S.C. 1456(c)(3)(A)) and 15 CFR
930.57, stating that the proposed
activities described in detail in your
plans comply with the State(s) approved
coastal management program(s) and will
be conducted in a manner that is
consistent with such program(s); and
(2) ‘‘Necessary data and information,’’
as required by 15 CFR 930.58.
*
*
*
*
*
■ 21. Amend § 585.628 by revising
paragraph (c) to read as follows:
§ 585.628
COP?
How will BOEM process my
*
*
*
*
*
(c) If your COP is submitted after lease
issuance, BOEM will forward one copy
of your COP, consistency certification,
and associated data and information
under the CZMA to the applicable State
CZMA agency or agencies after all
information requirements for the COP
are met.
*
*
*
*
*
■ 22. Amend § 585.640 by revising
paragraph (b) to read as follows:
§ 585.640
(GAP)?
What is a General Activities Plan
*
*
*
*
*
(b) You must receive BOEM approval
of your GAP before you can begin any
of the approved activities on your lease
or grant. You must submit your GAP no
later than 12 months from the date of
the lease or grant issuance.
■ 23. Revise § 585.646 to read as
follows:
§ 585.646 What information and
certifications must I submit with my GAP to
assist BOEM in complying with NEPA and
other relevant laws?
You must submit, with your GAP,
detailed information to assist BOEM in
complying with NEPA and other
relevant laws as appropriate.
(a) A GAP submitted for an area in
which BOEM has not reviewed GAP
21625
activities under NEPA or other
applicable Federal laws must describe
those resources, conditions, and
activities listed in the following table
that could be affected by your proposed
activities or that could affect the
activities proposed in your GAP.
(b) For a GAP submitted for an area
in which BOEM has considered GAP
activities under applicable Federal law
(e.g., a NEPA analysis and CZMA
consistency determination for the GAP
activities), BOEM will review the GAP
to determine if its impacts are consistent
with those previously considered. If the
anticipated effects of your proposed
GAP activities are significantly different
than those previously anticipated, we
may determine that additional NEPA
and other relevant Federal reviews are
required. In that case, BOEM will notify
you of such determination, and you
must submit a GAP that describes those
resources, conditions, and activities
listed in the following table that could
be affected by your proposed activities
or that could affect the activities
proposed in your GAP, including:
Type of information:
Including:
(1) Hazard information ....................
(2) Water quality .............................
(3) Biological resources ..................
Meteorology, oceanography, sediment transport, geology, and shallow geological or manmade hazards.
Turbidity and total suspended solids from construction.
Benthic communities, marine mammals, sea turtles, coastal and marine birds, fish and shellfish, plankton,
sea grasses, and other plant life.
As required by the ESA (16 U.S.C. 1531 et seq.).
(4) Threatened or endangered species.
(5) Sensitive biological resources or
habitats.
(6) Archaeological resources ..........
(7) Social and economic conditions
(8) Coastal and marine uses ..........
(9) Consistency Certification ...........
(10) Other resources, conditions,
and activities.
Essential fish habitat, refuges, preserves, special management areas identified in coastal management
programs, sanctuaries, rookeries, hard bottom habitat, chemosynthetic communities, calving grounds,
barrier islands, beaches, dunes, and wetlands.
As required by NHPA (16 U.S.C. 470 et seq.), as amended.
Employment, existing offshore and coastal infrastructure (including major sources of supplies, services, energy, and water), land use, subsistence resources and harvest practices, recreation, recreational and
commercial fishing (including typical fishing seasons, location, and type), minority and lower income
groups, coastal zone management programs, and viewshed.
Military activities, vessel traffic, and energy and non-energy mineral exploration or development.
If required by CZMA, as appropriate: (A) 15 CFR part 930, subpart D, if the GAP is submitted prior to
lease or grant issuance; (B) 15 CFR part 930, subpart E, if the GAP is submitted after lease or grant
issuance.
As required by BOEM.
§ 585.647 How will my GAP be processed
for Federal consistency under the Coastal
Zone Management Act?
24. Revise § 585.647 to read as
follows:
■
Your GAP will be processed based on
whether it is submitted before or after
your lease or grant is issued:
wreier-aviles on DSK5TPTVN1PROD with RULES
If your GAP is submitted:
Consistency review of your GAP will be handled as follows:
(a) Before lease or grant issuance
You will furnish a copy of your GAP, consistency certification, and necessary data and information pursuant to 15 CFR part 930, subpart D, to the applicable State CZMA agency or agencies and BOEM at the
same time.
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
PO 00000
Frm 00045
Fmt 4700
Sfmt 4700
E:\FR\FM\17APR1.SGM
17APR1
21626
Federal Register / Vol. 79, No. 74 / Thursday, April 17, 2014 / Rules and Regulations
If your GAP is submitted:
Consistency review of your GAP will be handled as follows:
(b) After lease or grant issuance ....
You will submit a copy of your GAP, consistency certification, and necessary data and information pursuant to 15 CFR 930, subpart E to BOEM. BOEM will forward to the applicable State CZMA agency or
agencies one paper copy and one electronic copy of your GAP, consistency certification, and necessary
data and information required under 15 CFR part 930, subpart E, after BOEM has determined that all information requirements for the GAP are met.
PART 590—APPEAL PROCEDURES
25. The authority citation for part 590
is revised to read as follows:
■
Authority: 5 U.S.C. 301 et seq.; 31 U.S.C.
9701; 43 U.S.C. 1334.
26. Amend § 590.4 by revising
paragraph (b)(1) to read as follows:
■
§ 590.4
How do I file an appeal?
*
*
*
*
*
(b) * * *
(1) You must pay electronically
through the Fees for Services page on
the BOEM Web site at https://
www.boem.gov, and you must include a
copy of the Pay.gov confirmation receipt
page with your Notice of Appeal.
*
*
*
*
*
Click on Open Docket Folder on the line
associated with this deviation. You may
also visit the Docket Management
Facility in Room W12–140 on the
ground floor of the Department of
Transportation West Building, 1200
New Jersey Avenue SE., Washington,
DC 20590, between 9 a.m. and 5 p.m.,
Monday through Friday, except Federal
holidays.
[FR Doc. 2014–08488 Filed 4–16–14; 8:45 am]
If
you have questions on this temporary
deviation, call or email Eric A.
Washburn, Bridge Administrator,
Western Rivers, Coast Guard; telephone
314–269–2378, email Eric.Washburn@
uscg.mil. If you have questions on
viewing the docket, call Cheryl F.
Collins, Program Manager, Docket
Operations, telephone 202–366–9826.
BILLING CODE 4320–MR–P
SUPPLEMENTARY INFORMATION:
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket Number USCG–2014–0248]
Drawbridge Operation Regulation;
Upper Mississippi River, Rock Island,
IL
Coast Guard, DHS.
Notice of deviation from
drawbridge regulation.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the Rock Island
Railroad and Highway Drawbridge
across the Upper Mississippi River, mile
482.9, at Rock Island, Illinois. The
deviation is necessary to allow the
participants of the Quad City Marathon
to cross the bridge. This deviation
allows the bridge to be maintained in
the closed-to-navigation position for
four hours.
DATES: This deviation is effective from
7:30 a.m. to 11:30 a.m., September 28,
2014.
ADDRESSES: The docket for this
deviation, [USCG–2014–0248] is
available at https://www.regulations.gov.
Type the docket number in the
‘‘SEARCH’’ box and click ‘‘SEARCH.’’
wreier-aviles on DSK5TPTVN1PROD with RULES
SUMMARY:
VerDate Mar<15>2010
14:50 Apr 16, 2014
Jkt 232001
FOR FURTHER INFORMATION CONTACT:
The U.S.
Army Rock Island Arsenal requested a
temporary deviation for the Rock Island
Railroad and Highway Drawbridge,
across the Upper Mississippi River, mile
482.9, at Rock Island, Illinois to remain
in the closed-to-navigation position for
a four hour period from 7:30 a.m. to
11:30 a.m., September 28, 2014, while
the Quad City Marathon is held between
the cities of Davenport, IA and Rock
Island, IL.
The Rock Island Railroad and
Highway Drawbridge currently operates
in accordance with 33 CFR 117.5, which
states the general requirement that
drawbridges shall open promptly and
fully for the passage of vessels when a
request to open is given in accordance
with the subpart.
There are no alternate routes for
vessels transiting this section of the
Upper Mississippi River.
The Rock Island Railroad and
Highway Drawbridge, in the closed-tonavigation position, provides a vertical
clearance of 23.8 feet above normal
pool. Navigation on the waterway
consists primarily of commercial tows
and recreational watercraft. This
temporary deviation has been
coordinated with waterway users. No
objections were received.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the effective period of this
temporary deviation. This deviation
PO 00000
Frm 00046
Fmt 4700
Sfmt 4700
from the operating regulations is
authorized under 33 CFR 117.35.
Dated: April 4, 2014.
Eric A. Washburn,
Bridge Administrator, Western Rivers.
[FR Doc. 2014–08783 Filed 4–16–14; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2013–0926]
RIN 1625–AA09
Drawbridge Operation Regulation; New
Jersey Intracoastal Waterway (NJICW),
Barnegat Bay, Seaside Heights, NJ
Coast Guard, DHS.
Temporary final rule.
AGENCY:
ACTION:
The Coast Guard is
temporarily modifying the operating
schedule that governs the S37 Bridge, at
NJICW mile 14.1 over Barnegat Bay, at
Seaside Heights, NJ. Over the span of
two and half years, the bridge will be
closed to navigation for three fourmonth closure periods. Extensive
replacement of parts and repairs to the
bridge necessitate these closures.
DATES: This temporary final rule is
effective from 8 a.m., on December 1,
2015 to 8 p.m., March 31, 2018.
ADDRESSES: Documents mentioned in
this preamble are part of docket USCG–
2013–0926. To view documents
mentioned in this preamble as being
available in the docket, go to https://
www.regulations.gov, type the docket
number in the ‘‘SEARCH’’ box and click
‘‘SEARCH.’’ Click on Open Docket
Folder on the line associated with this
rulemaking. You may also visit the
Docket Management Facility in Room
W12–140 on the ground floor of the
Department of Transportation West
Building, 1200 New Jersey Avenue SE.,
Washington, DC 20590, between 9 a.m.
and 5 p.m., Monday through Friday,
except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
rule, call or email Mr. Jim Rousseau,
SUMMARY:
E:\FR\FM\17APR1.SGM
17APR1
Agencies
[Federal Register Volume 79, Number 74 (Thursday, April 17, 2014)]
[Rules and Regulations]
[Pages 21617-21626]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-08488]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Ocean Energy Management
30 CFR parts 585 and 590
[Docket ID: BOEM-2012-0077]
RIN 1010-AD77
MMAA104000; Timing Requirements for the Submission of a Site
Assessment Plan (SAP) or General Activities Plan (GAP) for a Renewable
Energy Project on the Outer Continental Shelf (OCS)
AGENCY: Bureau of Ocean Energy Management (BOEM), Interior.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: This rule amends the timing requirements for submitting a SAP
or GAP. Under the rule, all OCS renewable energy leases and grants will
have a preliminary term of 12 months in which a lessee or grantee must
submit a SAP or a GAP. BOEM is taking this action because the current
regulations provide timing requirements for submission of
[[Page 21618]]
SAPs and GAPs that have proven to be impractical. In addition, this
rule amends various other regulatory provisions, such as those
pertaining to a lessee's first rent payment.
DATES: This final rule is effective May 19, 2014.
FOR FURTHER INFORMATION CONTACT: Jennifer Golladay, BOEM Office of
Renewable Energy, at Jennifer.Golladay@boem.gov or 703-787-1688.
SUPPLEMENTARY INFORMATION: This rule increases efficiency and reduces
the burden of regulations, since it extends the timeframes for lessees
and operators to submit plans and makes it possible for a Right of Use
and Easement (RUE) to be issued while a GAP is still pending. BOEM
published a proposed rule soliciting comments in the Federal Register
on February 25, 2013 (78 FR 12676).
Executive Summary
Current BOEM regulations require a lessee to submit a SAP or a GAP,
and a grantee to submit a GAP, within six months of lease or grant
issuance in cases where the lease or grant is issued following
completion of a competitive bidding process. In cases where a lease or
grant is issued on a noncompetitive basis, the regulations require the
requestor to submit a SAP or GAP within 60 days after BOEM makes and
publishes a ``Determination of No Competitive Interest.'' In
communications with prospective OCS renewable energy lessees and
grantees that took place after the current regulations were issued,
BOEM learned that these timeframes--especially the 60-day requirement--
are too short, and that most developers intend to request departures
from the regulatory requirements pertaining to the timing of SAP and
GAP submissions. In part, this is because site characterization
activities necessary to support the submission of a SAP or GAP are
significantly affected and controlled by seasonal weather conditions.
This rule addresses the difficulties associated with the current timing
requirements by lengthening the timeframe for submission of SAPs and
GAPs to 12 months following lease/grant issuance for both
competitively-issued and noncompetitively-issued leases and grants.
This rule makes various administrative corrections and
clarifications to BOEM's renewable energy regulations.
Summary of Changes
30 CFR Part 585
This rule amends the timing requirements for submitting a SAP or
GAP pursuant to the regulations governing renewable energy and
alternate uses of existing facilities on the OCS in 30 CFR part 585.
Under the rule, all OCS renewable energy leases and grants would have a
preliminary term of 12 months in which the lessee or grantee must
submit a SAP or a GAP. BOEM is proposing these changes because the
current regulations specify timing requirements for submission of SAPs
and GAPs that have proven to be impractical. This rule addresses the
difficulties associated with the current timing requirements by
lengthening the timeframe for submission of SAPs and GAPs to 12 months
following lease/grant issuance in all cases for both competitively-
issued and noncompetitively-issued leases and grants.
Changes Made Between Proposed and Final Rule
In the proposed rule, BOEM proposed to add definitions of the terms
``CZMA State'' and ``State CZMA Agency'' to the regulations. This was
intended to enable BOEM to clarify which regulatory provisions apply to
states with rights and responsibilities under the Coastal Zone
Management Act, as opposed to the states that fall under the general
definition of ``Affected State'' under the Outer Continental Shelf
Lands Act (OCSLA). However, the definition of ``Affected State'' in
BOEM's renewable energy regulations is different from the definition in
OCSLA, and ``Affected State'' is not used in the regulations describing
the CZMA compliance process (e.g., 30 CFR 585.612, 628, and 647). After
receiving comments and considering the potential changes further, BOEM
decided against adding the new definitions, since the proposed
additions would likely have caused confusion and redundancy rather than
clarity. The current regulations at 30 CFR part 585 include a
definition of ``affected state'' that fully addresses the needs of
BOEM's renewable energy program. Therefore, BOEM will continue to use
the term ``affected state'' in the following sections: 30 CFR 585.102,
585.112, 585.203, 585.211, 585.231, 585.238, 585.306, and 585.902 to
implement this decision.
In addition to the changes to the proposed rule which are discussed
in the section ``Response to Comments Matrix and Other Preamble Text,''
the following clarifying edits and/or technical corrections have been
made to the current regulations:
30 CFR 585.112--BOEM made minor changes that expand the
definition of ``you and your'' to include designated agents of all
entities listed, and corrected a minor grammatical error in this
definition.
30 CFR 585.203--BOEM made a small grammatical edit to the
last sentence.
30 CFR 585.211--BOEM made a small grammatical edit and a
small wording change to the first sentence in (c).
30 CFR 585.224--BOEM edited this provision to ensure
consistency with 30 CFR 585.503 regarding a lessee's first rent
payment, and made a small grammatical edit.
30 CFR 585.231--BOEM made small changes and some
grammatical edits in (d), (e), and (f), and changed the number of
months of rent owed in (g)(2).
30 CFR 585.235--BOEM made small wording changes in (a)(1),
(a)(3), and (a)(4), clarified the language about the start of the
operations term in the event a SAP/Construction and Operations Plan
(COP) is submitted in (a)(3), and moved text from the second to third
column in (a)(4).
30 CFR 585.236--BOEM reformatted the table slightly.
30 CFR 585.303--BOEM edited (a) to make a small
grammatical change and mirror the title of the provision in the
regulatory text, and added clarifying language in (b).
30 CFR 585.500, 503, and 505--BOEM coordinated with the
Department of the Interior's Office of Natural Resources Revenue (ONRR)
and determined that certain citations to the ONRR regulations in the
proposed rule were incorrect. Accordingly, sections 500(a) & (b), 503
(a)(1) and 505(b) were revised. In addition, edits were made to ensure
consistency with requirements in other regulatory provisions and to
effectively communicate to lessees how to make first-year rent
payments. BOEM also made a small grammatical edit in 30 CFR 585.500.
30 CFR 585.611--BOEM edited this provision to align the
language with BOEM's standard for determining if previous environmental
analyses adequately cover the proposed activities for environmental
review purposes by, for example, replacing ``substantially
inconsistent'' with ``significantly different.'' Additionally, BOEM
made small grammatical edits and eliminated the passive voice.
30 CFR 585.612--In this section, and in all other sections
where the term ``State CZM agency'' was used, BOEM replaced this term
with a new reference
[[Page 21619]]
to ``applicable State CZMA agency or agencies,'' consistent with the
approach used in new text included in 30 CFR 585.306 and 231. BOEM also
changed the wording in the first row of the table.
30 CFR 585.627--BOEM edited (a) to eliminate the
references to competitive and noncompetitive leasing and make small
grammatical changes, and corrected statutory and regulatory references
in (b).
30 CFR 585.628--BOEM edited (c) to: (1) Provide consistent
terminology (``applicable State CZMA agency or agencies'') and, (2)
clarify that the developer is responsible for providing this set of
information to the applicable State CZMA agency or agencies in the
event that the COP is submitted to BOEM prior to lease issuance,
pursuant to 15 CFR part 930, subpart D.
30 CFR 585.646--BOEM made small changes to (a) of this
provision to ensure that the text mirrors the language in 30 CFR
585.611 and to eliminate the passive voice. BOEM edited (b) to align
the language with BOEM's standard for determining if previous
environmental analyses adequately cover the proposed activities for
environmental review purposes by, for example, replacing
``substantially inconsistent'' with ``significantly different,'' to
remove an unnecessary reference to CZMA, to make small grammatical
changes, and to eliminate the passive voice.
30 CFR 585.647--BOEM changed some of the wording to align
with the new text included in 30 CFR 585.306 and 231, (``applicable
State CZMA agency or agencies''), to fix an incorrect regulatory
citation, and to change the wording in the first row of the table.
Finally, BOEM made certain other changes to the regulatory text
included in the proposed rule based on comments received, as described
below in the Response to Comments Matrix.
Legal Authority
The authority for this rulemaking is the broad rulemaking provision
of the OCSLA, as set forth in 43 U.S.C. 1334(a), that authorizes the
Secretary of the Interior to prescribe and amend such rules and
regulations as may be necessary to administer a leasing program, or
necessary and proper in order to provide for the prevention of waste
and conservation of natural resources of the OCS.
Section 8(p)(8) of OCSLA (43 U.S.C. 1337(p)(8)) provides authority
for the portion of this rulemaking dealing with the production,
transportation, or transmission of energy from sources other than oil
and gas, and alternate uses of the OCS, which authorizes the Secretary
to issue any necessary regulations to carry out subsection 8(p) of
OCSLA.
Response to Comments Matrix and Other Preamble Text
BOEM published a proposed rule entitled, ``Timing Requirements for
the Submission of a Site Assessment Plan (SAP) or a General Activities
Plan (GAP) for a Renewable Energy Project on the Outer Continental
Shelf (OCS)'' in the Federal Register on February 25, 2013, with a 30-
day request for comments period.
BOEM received nine comment letters from interested stakeholders,
and carefully considered them prior to finalizing the rulemaking.
Generally, commenters were supportive of extending the timing
requirements for developers to submit SAPs and GAPs. Some comments
suggested edits to the text of the rulemaking, requested clarifications
as to the applicability of the rulemaking, and/or raised questions
about the necessity of the rulemaking. Responses to those comments are
contained in the table below.
------------------------------------------------------------------------
Comment received BOEM response
------------------------------------------------------------------------
BOEM should revise the definition of BOEM has decided against adding
the term ``CZMA State'' by cross the new term ``CZMA State'' in
referencing the National Oceanic and this rulemaking.
Atmospheric Administration's Office of
Ocean and Coastal Resource
Management's Federal consistency rules.
BOEM should not require that a BOEM has made this requested
developer submitting an unsolicited change and accordingly will
request for a lease or grant include not add this requirement to 30
in the request a consistency CFR 585.230 or 585.305. These
certification and associated necessary developers are now required to
data and information pursuant to CZMA submit a consistency
regulations at 15 CFR part 930 subpart certification and the
D. associated necessary data and
information under CZMA only
after BOEM has determined that
there is no competitive
interest in the proposed
project.
The proposed rule should address cable- BOEM did not make this
related easements early at the lease requested change. The agency
sale or SAP or GAP stage, rather than believes that it would be
later as part of a COP. premature to consider and
analyze cable locations until
commercial wind lessees have
conducted necessary surveys
and lessees are able to
consider the layout of their
commercial projects when
making siting decisions about
transmission cables.
BOEM should edit 30 CFR 585.102 to BOEM made this requested
bring it into conformity with 30 CFR change.
585.203, such that the first sentence
of 30 CFR 585.102(e) uses ``and''
instead of ``or.''
The new proposed 30 CFR 585.612(b) BOEM made this requested
should refer to 15 CFR part 930 change.
instead of 15 CFR part 93.
To avoid confusion, BOEM should clarify BOEM will address any such
that BOEM regulations (see 30 CFR confusion with the appropriate
585.231 and 585.306) regarding the parties on a project-by-
applicable CZMA consistency review project basis.
process do not apply to pending lease
applications for which BOEM has issued
a determination of no competitive
interest prior to this rule's
effective date.
Please provide more detail on the At the time that this proposed
number of SAPs and GAPs that have been rulemaking was published, BOEM
filed, the bureau's use of this had only received one such
information, the actions taken against plan. However, after receiving
any companies that have filed plans (1) informal feedback on these
late, and any requests to change these timing requirements from
filing deadlines. industry and (2) requests to
depart from these timing
requirements pursuant to 30
CFR 585.103, BOEM came to the
conclusion that the existing
timing requirements were
impractical. The comments
received in response to the
proposed rulemaking were
generally supportive of
extending the required
timelines for plan submission.
------------------------------------------------------------------------
[[Page 21620]]
Procedural Matters
Regulatory Planning and Review (Executive Orders 12866 and 13563)
Executive Order 12866 provides that the Office of Information and
Regulatory Affairs (OIRA) will review all significant rules. The Office
of Information and Regulatory Affairs has determined that this rule is
not significant.
Executive Order 13563 reaffirms the principles of E.O. 12866 while
calling for improvements in the nation's regulatory system to promote
predictability, to reduce uncertainty, and to use the best, most
innovative, and least burdensome tools for achieving regulatory ends.
The executive order directs agencies to consider regulatory approaches
that reduce burdens and maintain flexibility and freedom of choice for
the public where these approaches are relevant, feasible, and
consistent with regulatory objectives. E.O. 13563 emphasizes further
that regulations must be based on the best available science and that
the rulemaking process must allow for public participation and an open
exchange of ideas. BOEM has developed this rule in a manner consistent
with these requirements.
This rule is not a significant rule as determined by the Office of
Management and Budget (OMB) and is not subject to review under E.O.
12866. For the most part, this rule makes administrative corrections
and clarifications to the existing regulations. Other changes consist
of the reorganization of selected renewable energy regulations.
Because this rule makes only minor alterations and changes to
requirements for leasing, compliance, or enforcement from those set
forth in existing regulations, no costs are estimated for this
rulemaking.
(1) This rule will not have an annual effect of $100 million or
more on the economy. It would not adversely affect in a material way
the economy, productivity, competition, jobs, the environment, public
health or safety, or State, local, or tribal governments or
communities.
(2) This rule will not create a serious inconsistency or otherwise
interfere with an action taken or planned by another agency.
(3) This rule will not alter the budgetary effects of entitlements,
grants, user fees, or loan programs or the rights or obligations of
their recipients.
(4) This rule will not raise novel legal or policy issues arising
out of legal mandates, the President's priorities, or the principles
set forth in E.O. 12866.
Regulatory Flexibility Act
The Department of the Interior certifies that this rule will not
have a significant economic effect on a substantial number of small
entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.).
This rulemaking will affect large and small entities through the
clarification of the existing regulatory requirements under the
reorganized regulations of part 585.
Your comments are important. The Small Business and Agriculture
Regulatory Enforcement Ombudsman and ten Regional Fairness Boards were
established to receive comments from small businesses about Federal
agency enforcement actions. The Ombudsman will annually evaluate the
enforcement activities and rate each agency's responsiveness to small
business. If you wish to comment on the actions of BOEM, call 1-888-
734-3247. You may comment to the Small Business Administration without
fear of retaliation. Allegations of discrimination/retaliation filed
with the Small Business Administration will be investigated for
appropriate action.
Small Business Regulatory Enforcement Fairness Act
This rule is not a major rule under the Small Business Regulatory
Enforcement Fairness Act (5 U.S.C. 801 et seq.). This rule:
(a) Will not have an annual effect on the economy of $100 million
or more.
(b) Will not cause a major increase in costs or prices for
consumers, individual industries, Federal, state, or local government
agencies, or geographic regions.
(c) Will not have significant adverse effects on competition,
employment, investment, productivity, innovation, or the ability of
U.S.-based enterprises to compete with foreign-based enterprises. The
requirements apply to all entities operating to develop renewable
resources on the OCS.
Unfunded Mandates Reform Act of 1995
This rule does not impose an unfunded mandate on state, local, or
tribal governments, or the private sector, of more than $100 million
per year. This rule does not have a significant or unique effect on
state, local, or tribal governments, or the private sector. A statement
containing the information required by the Unfunded Mandates Reform Act
(2 U.S.C. 1501 et seq.) is not required.
Takings Implication Assessment (E.O. 12630)
Under the criteria in E.O. 12630, this rule will not have
significant takings implications. This rule will not be a governmental
action capable of interference with constitutionally protected property
rights. A Takings Implication Assessment is not required.
Federalism (E.O. 13132)
Under the criteria in E.O. 13132, this rule will not have
federalism implications. This rule will not substantially affect the
relationship between the Federal and state governments. To the extent
that state and local governments have a role in OCS activities, this
rule will not affect that role. A Federalism Assessment is not
required.
Civil Justice Reform (E.O. 12988)
This rule complies with the requirements of E.O. 12988.
Specifically, this rule:
(a) Meets the criteria of section 3(a) requiring that all
regulations be reviewed to eliminate errors and ambiguity and be
written to minimize litigation; and (b) Meets the criteria of section
3(b)(2) requiring that all regulations be written in clear language and
contain clear legal standards.
Consultation With Indian Tribes (E.O. 13175)
Under the criteria in E.O. 13175, BOEM has evaluated this rule and
determined that it will have no substantial effects on federally
recognized Indian tribes.
Paperwork Reduction Act (PRA) of 1995
This rule does not contain new information collection requirements,
and a submission under the PRA is not required. Therefore, an
information collection request is not being submitted to the Office of
Management and Budget (OMB) for review and approval under 44 U.S.C.
3501 et seq. The rule refers to, but does not change, the information
collection requirements in 30 CFR 585. The OMB has approved the
referenced information collection under OMB Control Number 1010-0176
(30,902 hours and $3,816,000 non-hour cost burden).
National Environmental Policy Act of 1969
This rule does not constitute a major Federal action significantly
affecting the quality of the human environment. BOEM evaluated this
rule under the criteria of the National Environmental Policy Act, 43
CFR Part 46 and 516 Departmental Manual 15. The issuance of this rule
is categorically excluded from NEPA review because it meets the
criteria set forth in 43 CFR 46.210(i) in that this rule is ``. . . of
an
[[Page 21621]]
administrative, financial, legal, technical, or procedural nature . .
.'' Furthermore, we have evaluated this rule to determine if it
involves any of the extraordinary circumstances that would require an
environmental assessment or an environmental impact statement as set
forth in 43 CFR 46.215. We concluded that this rule does not meet any
of the criteria for extraordinary circumstances as set forth in 516
Departmental Manual 2 (Appendix 2).
Data Quality Act
In developing this rule, we did not conduct or use a study,
experiment, or survey requiring peer review under the Data Quality Act
(Pub. L. 106-554, app. C sec. 515, 114 Stat. 2763, 2763A-153-154).
Effects of the Nation's Energy Supply (E.O. 13211)
This rule is not a significant energy action under the definition
in E.O. 13211. A Statement of Energy Effects is not required.
Clarity of This Regulation
We are required by E.O. 12866, E.O. 12988, and by the Presidential
Memorandum of June 1, 1998, to write all rules in plain language. This
means that each rule we publish must:
(a) Be logically organized;
(b) Use the active voice to address readers directly;
(c) Use clear language rather than jargon;
(d) Be divided into short sections and sentences; and
(e) Use lists and tables wherever such lists or tables would be
helpful.
If you feel that we have not met these requirements, send your
comments to Mr. Loren Thompson, Regulatory Liaison Officer, Office of
Policy, Regulations and Analysis, Bureau of Ocean Energy Management,
U.S. Department of the Interior, 1849 C St. NW., Washington, DC 20240
or to Loren.Thompson@boem.gov.
List of Subjects
30 CFR Part 585
Assessment plans, Coastal zone, Continental shelf, Electric power,
Energy, Environmental impact statements, Environmental protection,
Incorporation by reference, Offshore energy, Marine resources, Natural
resources, Planning, Public lands, Public lands--rights-of-way,
Renewable energy, Reporting and recordkeeping requirements, Revenue
sharing, Solar energy, Wind energy.
30 CFR Part 590
Administrative practice and procedure, Appeals, Payments.
Dated: April 7, 2014.
Tommy P. Beaudreau,
Principal Deputy Assistant Secretary, Land and Minerals Management.
For the reason stated in the preamble, the Bureau of Ocean Energy
Management amends 30 CFR chapter V as follows:
PART 585--RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING
FACILITIES ON THE OUTER CONTINENTAL SHELF
0
1. The authority citation for part 585 continues to read as follows:
Authority: 43 U.S.C. 1331 et seq.; 43 U.S.C. 1337.
0
2. Amend Sec. 585.102 by revising paragraph (e) to read as follows:
Sec. 585.102 What are BOEM's responsibilities under this part?
* * * * *
(e) BOEM will provide for coordination and consultation with the
Governor of any State, the executive of any local government, and the
executive of any Indian Tribe that may be affected by a lease,
easement, or ROW under this subsection. BOEM may invite any affected
State Governor, representative of an affected Indian Tribe, and
affected local government executive to join in establishing a task
force or other joint planning or coordination agreement in carrying out
our responsibilities under this part.
0
3. Amend Sec. 585.112 by revising the definition of ``You and your''
to read as follows:
Sec. 585.112 Definitions.
* * * * *
You and your means an applicant, lessee, the operator, or
designated operator, ROW grant holder, RUE grant holder, or Alternate
Use RUE grant holder under this part, or the designated agent of any of
these, or the possessive of each, depending on the context. The terms
You and your also include contractors and subcontractors of the
entities specified in the preceding sentence.
* * * * *
0
4. Revise Sec. 585.203 to read as follows:
Sec. 585.203 With whom will BOEM consult before issuance of a lease?
For leases issued under this part, through either the competitive
or noncompetitive process, BOEM, prior to issuing the lease, will
coordinate and consult with relevant Federal agencies (including, in
particular, those agencies involved in planning activities that are
undertaken to avoid or minimize conflicts among users and maximize the
economic and ecological benefits of the OCS, including multifaceted
spatial planning efforts), the Governor of any affected State, the
executive of any affected local government, and any affected Indian
Tribe, as directed by subsections 8(p)(4) and (7) of the OCS Lands Act
or other relevant Federal laws. Federal statutes that require BOEM to
consult with interested parties or Federal agencies or to respond to
findings of those agencies, including the Endangered Species Act (ESA)
and the Magnuson-Stevens Fishery Conservation and Management Act (MSA).
BOEM also engages in consultation with state and tribal historic
preservation officers pursuant to the National Historic Preservation
Act (NHPA).
0
5. Amend Sec. 585.211 by revising paragraph (c) to read as follows:
Sec. 585.211 What is the process for the competitive issuance of
leases?
* * * * *
(c) Proposed Sale Notice. BOEM will publish the Proposed Sale
Notice in the Federal Register and send it to the Governor of any
affected State, any Indian Tribe that might be affected, and the
executive of any local government that might be affected. The comment
period following issuance of a Proposed Sale Notice will be 60 days.
* * * * *
0
6. Amend Sec. 585.212 by revising paragraph (a) to read as follows:
Sec. 585.212 What is the process BOEM will follow if there is reason
to believe that competitors have withdrawn before the Final Sale Notice
is issued?
* * * * *
(a) If, after reviewing comments in response to the notice of
Request for Interest, BOEM determines that there is no competitive
interest in the lease area, and one party wishes to acquire a lease, we
will discontinue the competitive process and will proceed with the
noncompetitive process set forth in Sec. 585.231(d) through (i)
following receipt of the acquisition fee specified in Sec. 585.502(a).
* * * * *
0
7. Amend Sec. 585.224 by revising paragraph (b) to read as follows:
Sec. 585.224 What happens if BOEM accepts my bid?
* * * * *
(b) Within 45 days after you receive the lease copies, you must pay
the first
[[Page 21622]]
12-months' rent as required in Sec. 585.503.
* * * * *
0
8. Amend Sec. 585.231 by revising paragraphs (d), (e), (f), and (g)(2)
to read as follows:
Sec. 585.231 How will BOEM process my unsolicited request for a
noncompetitive lease?
* * * * *
(d) If BOEM determines that there is no competitive interest in a
lease, we will publish in the Federal Register a notice of
Determination of No Competitive Interest. After BOEM publishes this
notice, you will be responsible for submitting any required consistency
certification and necessary data and information pursuant to 15 CFR
part 930, subpart D to the applicable State CZMA agency or agencies and
BOEM.
(e) BOEM will coordinate and consult with affected Federal
agencies, State, and local governments, and affected Indian tribes in
the review of noncompetitive lease requests.
(f) After completing the review of your lease request, BOEM may
offer you a noncompetitive lease.
(g) * * *
(2) Within 45 days after you receive the lease copies, you must pay
the first 12-months' rent, as required in Sec. 585.503.
* * * * *
0
9. Amend Sec. 585.235 by revising paragraph (a) to read as follows:
Sec. 585.235 If I have a commercial lease, how long will my lease
remain in effect?
(a) For commercial leases, the lease terms and applicable automatic
extensions are as shown in the following table:
------------------------------------------------------------------------
Automatic
Lease term extensions Requirements
------------------------------------------------------------------------
(1) Each commercial lease will If BOEM receives a The SAP must meet
have a preliminary term of 12 SAP that the requirements
months, within which the lessee satisfies the of Sec. Sec.
must submit: (i) a SAP; or (ii) requirements of 585.605 through
a combined SAP and Construction Sec. Sec. 585.613. The SAP/
and Operations Plan (COP). The 585.605 through COP must meet the
preliminary term begins on the 585.613 or a SAP/ requirements of
effective date of the lease. COP that Sec. Sec.
satisfies the 585.605 through
requirements of 585.613 and Sec.
Sec. Sec. Sec. 585.620
585.605 through through 585.629.
585.613 and Sec.
Sec. 585.620
through 585.629,
the preliminary
term will be
extended for the
time necessary
for us to conduct
technical and
environmental
reviews of the
SAP or SAP/COP.
(2) A commercial lease will have If we receive a The COP must meet
a site assessment term of five COP that the requirements
years to conduct site satisfies the of Sec. Sec.
assessment activities and to requirements of 585.620 through
submit a COP, if a SAP/COP has Sec. Sec. 585.629 of this
not been submitted. Your site 585.620 through part.
assessment term begins when 585.629, the site
BOEM approves your SAP or SAP/ assessment term
COP. will be
automatically
extended for the
period of time
necessary for us
to conduct
technical and
environmental
reviews of the
COP.
(3) A commercial lease will have .................. The lease renewal
an operations term of 25 years, request must meet
unless a longer term is the requirements
negotiated by the parties. A in Sec. Sec.
request for lease renewal must 585.425 through
be submitted two years before 585.429.
the end of the operations term.
If you submit a COP, your
operations term begins on the
date that BOEM approves the
COP. If you submit a SAP/COP,
your operations term begins on
the earliest of the following
dates: five years after BOEM
approves the SAP/COP; when
fabrication begins; or, when
installation commences.
(4) A commercial lease may have .................. NOTE: BOEM may
additional time added to the also order or
operations term through a lease grant a
renewal. The term of the lease suspension of the
renewal will not exceed the operations term,
original term of the lease, as provided in
unless a longer term is Sec. Sec.
negotiated by the parties. The 585.415 through
lease renewal term begins upon 585.421 thereby
expiration of the original effectively
operations term. extending the
term of the
lease.
------------------------------------------------------------------------
* * * * *
0
10. Amend Sec. 585.236 by revising paragraph (a) to read as follows:
Sec. 585.236 If I have a limited lease, how long will my lease remain
in effect?
(a) For limited leases, the lease terms are as shown in the
following table:
------------------------------------------------------------------------
Extension or
Lease term suspension Requirements
------------------------------------------------------------------------
(1) Each limited lease has a If we receive a The GAP must meet
preliminary term of 12 months GAP that the requirements
to submit a GAP. The satisfies the of Sec. Sec.
preliminary term begins on the requirements of 585.640 through
effective date of the lease. Sec. Sec. 585.648.
585.640 through
585.648 of this
part, the
preliminary term
will be
automatically
extended for the
period of time
necessary for us
to conduct a
technical and
environmental
review of the
plans.
[[Page 21623]]
(2) Each limited lease has an We may order or
operations term of five years grant a
for conducting site assessment, suspension of the
technology testing, or other operations term
activities. The operations term as provided in
begins on the date that we Sec. Sec.
approve your GAP. 585.415 through
585.421.
------------------------------------------------------------------------
* * * * *
0
11. Revise Sec. 585.303 to read as follows:
Sec. 585.303 How long will my ROW grant or RUE grant remain in
effect?
(a) Each ROW or RUE grant will have a preliminary term of 12 months
from the date of issuance of the ROW or RUE grant within which to
submit a GAP. The preliminary term begins on the effective date of the
grant. You must submit a GAP no later than the end of the preliminary
term for your grant to remain in effect. However, you may submit a GAP
prior to the issuance of your ROW or RUE grant.
(b) Except as described in paragraph (a) of this section, your ROW
grant or RUE grant will remain in effect for as long as the associated
activities are properly maintained and used for the purpose for which
the grant was made, unless otherwise expressly stated in the grant.
0
12. Amend Sec. 585.306 by revising paragraph (b) and by removing
paragraph (c).
The revision reads as follows:
Sec. 585.306 What action will BOEM take on my request?
* * * * *
(b) If BOEM determines that there is no competitive interest in a
ROW grant or RUE grant, we will publish a notice in the Federal
Register of such determination. After BOEM publishes this notice, you
will be responsible for submitting any required consistency
certification and necessary data and information pursuant to 15 CFR
part 930, subpart D to the applicable State CZMA agency or agencies and
BOEM. We will establish terms and conditions for the grant in
consultation with you.
0
13. Amend Sec. 585.309 by revising the introductory text to read as
follows:
Sec. 585.309 When will BOEM issue a noncompetitive ROW grant or RUE
grant?
After completing the review of your grant request, BOEM may offer
you a noncompetitive grant.
* * * * *
0
14. Amend Sec. 585.500 by revising paragraphs (a) and (b) to read as
follows:
Sec. 585.500 How do I make payments under this part?
(a) For acquisition fees or the initial 12-months' rent paid for
the preliminary term of your lease, you must make your electronic
payments through the Fees for Services page on the BOEM Web site at
https://www.boem.gov, and you must include one copy of the Pay.gov
confirmation receipt page with your unsolicited request.
(b) For all other required rent payments and for operating fee
payments, you must make your payments as required in 30 CFR 1218.51.
* * * * *
0
15. Amend Sec. 585.503 by revising paragraph (a)(1) to read as
follows:
Sec. 585.503 What are the rent and operating fee requirements for a
commercial lease?
(a) * * *
(1) You must pay ONRR the initial 12-months' rent 45 days after you
receive the lease copies from BOEM in accordance with the requirements
provided in Sec. 585.500(a).
* * * * *
0
16. Amend Sec. 585.505 by revising paragraph (b) to read as follows:
Sec. 585.505 What are the rent and operating fee requirements for a
limited lease?
* * * * *
(b) You must pay ONRR the initial 12-months' rent 45 days after you
receive the lease copies from BOEM in accordance with the requirements
provided in Sec. 585.500(a).
* * * * *
0
17. Amend Sec. 585.601 by:
0
a. Revising the introductory text and paragraph (a);
0
b. Removing paragraph (b);
0
c. Re-designating paragraphs (c) and (d) as paragraphs (b) and (c).
The revisions read as follows:
Sec. 585.601 When am I required to submit my plans to BOEM?
You must submit your plans as follows:
(a) You may submit your SAP or GAP prior to lease or grant
issuance, but must submit your SAP or your GAP no later than 12 months
from the date of lease or grant issuance.
* * * * *
0
18. Revise Sec. 585.611 to read as follows:
Sec. 585.611 What information and certifications must I submit with
my SAP to assist BOEM in complying with NEPA and other relevant laws?
You must submit, with your SAP, detailed information to assist BOEM
in complying with NEPA and other relevant laws as appropriate.
(a) A SAP submitted for an area in which BOEM has not previously
reviewed site assessment activities under NEPA or other applicable
Federal laws, must describe those resources, conditions, and activities
listed in the following table that could be affected by your proposed
activities or that could affect the activities proposed in your SAP.
(b) For a SAP submitted for an area in which BOEM has previously
considered site assessment activities under applicable Federal law
(e.g., a NEPA analysis and CZMA consistency determination for site
assessment activities), BOEM will review the SAP to determine if its
impacts are consistent with those previously considered. If the
anticipated effects of your proposed SAP activities are significantly
different than those previously anticipated, we may determine that
additional NEPA and other relevant Federal reviews are required. In
that case, BOEM will notify you of such determination, and you must
submit a SAP that describes those resources, conditions, and activities
listed in the following table that could be affected by your proposed
activities or that could affect the activities proposed in your SAP,
including:
------------------------------------------------------------------------
Type of information: Including:
------------------------------------------------------------------------
(1) Hazard information............ Meteorology, oceanography, sediment
transport, geology, and shallow
geological or manmade hazards.
(2) Water quality................. Turbidity and total suspended solids
from construction.
[[Page 21624]]
(3) Biological resources.......... Benthic communities, marine mammals,
sea turtles, coastal and marine
birds, fish and shellfish,
plankton, sea grasses, and other
plant life.
(4) Threatened or endangered As required by the Endangered
species. Species Act (ESA) of 1973 (16
U.S.C. 1531 et seq.).
(5) Sensitive biological resources Essential fish habitat, refuges,
or habitats. preserves, special management areas
identified in coastal management
programs, sanctuaries, rookeries,
hard bottom habitat, chemosynthetic
communities, calving grounds,
barrier islands, beaches, dunes,
and wetlands.
(6) Archaeological resources...... As required by the NHPA (16 U.S.C.
470 et seq.), as amended.
(7) Social and economic conditions Employment, existing offshore and
coastal infrastructure (including
major sources of supplies,
services, energy, and water), land
use, subsistence resources and
harvest practices, recreation,
recreational and commercial fishing
(including typical fishing seasons,
location, and type), minority and
lower income groups, coastal zone
management programs, and viewshed.
(8) Coastal and marine uses....... Military activities, vessel traffic,
and energy and nonenergy mineral
exploration or development.
(9) Consistency Certification..... If required by CZMA, as appropriate:
(i) 15 CFR part 930, subpart D, if
the SAP is submitted prior to lease
issuance; (ii) 15 CFR part 930,
subpart E, if the SAP is submitted
after lease issuance.
------------------------------------------------------------------------
(10) Other resources, conditions, As identified by BOEM.
and activities.
------------------------------------------------------------------------
0
19. Revise Sec. 585.612 to read as follows:
Sec. 585.612 How will my SAP be processed for Federal consistency
under theCoastal Zone Management Act?
Your SAP will be processed based on whether it is submitted before
or after your lease is issued:
------------------------------------------------------------------------
Consistency review of your SAP will
If your SAP is submitted: be handled as follows:
------------------------------------------------------------------------
(a) Before lease issuance......... You will furnish a copy of your SAP,
consistency certification, and
necessary data and information
pursuant to 15 CFR part 930,
subpart D, to the applicable State
CZMA agency or agencies and BOEM at
the same time.
(b) After lease issuance.......... You will submit a copy of your SAP,
consistency certification, and
necessary data and information
pursuant to 15 CFR part 930,
subpart E to BOEM. BOEM will
forward to the applicable State
CZMA agency or agencies one paper
copy and one electronic copy of
your SAP, consistency
certification, and necessary data
and information required under 15
CFR part 930, subpart E, after BOEM
has determined that all information
requirements for the SAP are met.
------------------------------------------------------------------------
0
20. Amend Sec. 585.627 by revising paragraphs (a) and (b) to read as
follows:
Sec. 585.627 What information and certifications must I submit with
my COP to assist the BOEM in complying with NEPA and other relevant
laws?
(a) You must submit with your COP detailed information to assist
BOEM in complying with NEPA and other relevant laws. Your COP must
describe those resources, conditions, and activities listed in the
following table that could be affected by your proposed activities, or
that could affect the activities proposed in your COP, including:
------------------------------------------------------------------------
Type of information: Including:
------------------------------------------------------------------------
(1) Hazard information............ Meteorology, oceanography, sediment
transport, geology, and shallow
geological or manmade hazards.
(2) Water quality................. Turbidity and total suspended solids
from construction.
(3) Biological resources.......... Benthic communities, marine mammals,
sea turtles, coastal and marine
birds, fish and shellfish,
plankton, seagrasses, and plant
life.
(4) Threatened or endangered As defined by the ESA (16 U.S.C.
species. 1531 et seq.).
(5) Sensitive biological resources Essential fish habitat, refuges,
or habitats. preserves, special management areas
identified in coastal management
programs, sanctuaries, rookeries,
hard bottom habitat, chemosynthetic
communities, calving grounds,
barrier islands, beaches, dunes,
and wetlands.
(6) Archaeological resources...... As required by the NHPA (16 U.S.C.
470 et seq.), as amended.
(7) Social and economic resources. Employment, existing offshore and
coastal infrastructure (including
major sources of supplies,
services, energy, and water), land
use, subsistence resources and
harvest practices, recreation,
recreational and commercial fishing
(including typical fishing seasons,
location, and type), minority and
lower income groups, coastal zone
management programs, and viewshed.
(8) Coastal and marine uses....... Military activities, vessel traffic,
and energy and nonenergy mineral
exploration or development.
(9) Consistency Certification..... As required by the CZMA regulations:
(i) 15 CFR part 930, subpart D, if
your COP is submitted before lease
issuance.
(ii) 15 CFR part 930, subpart E, if
your COP is submitted after lease
issuance.
(10) Other resources, conditions, As identified by BOEM.
and activities.
------------------------------------------------------------------------
[[Page 21625]]
(b) You must submit one paper copy and one electronic copy of your
consistency certification. Your consistency certification must include:
(1) One copy of your consistency certification under either
subsection 307(c)(3)(B) of the CZMA (16 U.S.C. 1456(c)(3)(B)) and 15
CFR 930.76 or subsection 307(c)(3)(A) of the CZMA (16 U.S.C.
1456(c)(3)(A)) and 15 CFR 930.57, stating that the proposed activities
described in detail in your plans comply with the State(s) approved
coastal management program(s) and will be conducted in a manner that is
consistent with such program(s); and
(2) ``Necessary data and information,'' as required by 15 CFR
930.58.
* * * * *
0
21. Amend Sec. 585.628 by revising paragraph (c) to read as follows:
Sec. 585.628 How will BOEM process my COP?
* * * * *
(c) If your COP is submitted after lease issuance, BOEM will
forward one copy of your COP, consistency certification, and associated
data and information under the CZMA to the applicable State CZMA agency
or agencies after all information requirements for the COP are met.
* * * * *
0
22. Amend Sec. 585.640 by revising paragraph (b) to read as follows:
Sec. 585.640 What is a General Activities Plan (GAP)?
* * * * *
(b) You must receive BOEM approval of your GAP before you can begin
any of the approved activities on your lease or grant. You must submit
your GAP no later than 12 months from the date of the lease or grant
issuance.
0
23. Revise Sec. 585.646 to read as follows:
Sec. 585.646 What information and certifications must I submit with
my GAP to assist BOEM in complying with NEPA and other relevant laws?
You must submit, with your GAP, detailed information to assist BOEM
in complying with NEPA and other relevant laws as appropriate.
(a) A GAP submitted for an area in which BOEM has not reviewed GAP
activities under NEPA or other applicable Federal laws must describe
those resources, conditions, and activities listed in the following
table that could be affected by your proposed activities or that could
affect the activities proposed in your GAP.
(b) For a GAP submitted for an area in which BOEM has considered
GAP activities under applicable Federal law (e.g., a NEPA analysis and
CZMA consistency determination for the GAP activities), BOEM will
review the GAP to determine if its impacts are consistent with those
previously considered. If the anticipated effects of your proposed GAP
activities are significantly different than those previously
anticipated, we may determine that additional NEPA and other relevant
Federal reviews are required. In that case, BOEM will notify you of
such determination, and you must submit a GAP that describes those
resources, conditions, and activities listed in the following table
that could be affected by your proposed activities or that could affect
the activities proposed in your GAP, including:
------------------------------------------------------------------------
Type of information: Including:
------------------------------------------------------------------------
(1) Hazard information............ Meteorology, oceanography, sediment
transport, geology, and shallow
geological or manmade hazards.
(2) Water quality................. Turbidity and total suspended solids
from construction.
(3) Biological resources.......... Benthic communities, marine mammals,
sea turtles, coastal and marine
birds, fish and shellfish,
plankton, sea grasses, and other
plant life.
(4) Threatened or endangered As required by the ESA (16 U.S.C.
species. 1531 et seq.).
(5) Sensitive biological resources Essential fish habitat, refuges,
or habitats. preserves, special management areas
identified in coastal management
programs, sanctuaries, rookeries,
hard bottom habitat, chemosynthetic
communities, calving grounds,
barrier islands, beaches, dunes,
and wetlands.
(6) Archaeological resources...... As required by NHPA (16 U.S.C. 470
et seq.), as amended.
(7) Social and economic conditions Employment, existing offshore and
coastal infrastructure (including
major sources of supplies,
services, energy, and water), land
use, subsistence resources and
harvest practices, recreation,
recreational and commercial fishing
(including typical fishing seasons,
location, and type), minority and
lower income groups, coastal zone
management programs, and viewshed.
(8) Coastal and marine uses....... Military activities, vessel traffic,
and energy and non-energy mineral
exploration or development.
(9) Consistency Certification..... If required by CZMA, as appropriate:
(A) 15 CFR part 930, subpart D, if
the GAP is submitted prior to lease
or grant issuance; (B) 15 CFR part
930, subpart E, if the GAP is
submitted after lease or grant
issuance.
(10) Other resources, conditions, As required by BOEM.
and activities.
------------------------------------------------------------------------
0
24. Revise Sec. 585.647 to read as follows:
Sec. 585.647 How will my GAP be processed for Federal consistency
under the Coastal Zone Management Act?
Your GAP will be processed based on whether it is submitted before
or after your lease or grant is issued:
------------------------------------------------------------------------
Consistency review of your GAP will
If your GAP is submitted: be handled as follows:
------------------------------------------------------------------------
(a) Before lease or grant issuance You will furnish a copy of your GAP,
consistency certification, and
necessary data and information
pursuant to 15 CFR part 930,
subpart D, to the applicable State
CZMA agency or agencies and BOEM at
the same time.
[[Page 21626]]
(b) After lease or grant issuance. You will submit a copy of your GAP,
consistency certification, and
necessary data and information
pursuant to 15 CFR 930, subpart E
to BOEM. BOEM will forward to the
applicable State CZMA agency or
agencies one paper copy and one
electronic copy of your GAP,
consistency certification, and
necessary data and information
required under 15 CFR part 930,
subpart E, after BOEM has
determined that all information
requirements for the GAP are met.
------------------------------------------------------------------------
PART 590--APPEAL PROCEDURES
0
25. The authority citation for part 590 is revised to read as follows:
Authority: 5 U.S.C. 301 et seq.; 31 U.S.C. 9701; 43 U.S.C.
1334.
0
26. Amend Sec. 590.4 by revising paragraph (b)(1) to read as follows:
Sec. 590.4 How do I file an appeal?
* * * * *
(b) * * *
(1) You must pay electronically through the Fees for Services page
on the BOEM Web site at https://www.boem.gov, and you must include a
copy of the Pay.gov confirmation receipt page with your Notice of
Appeal.
* * * * *
[FR Doc. 2014-08488 Filed 4-16-14; 8:45 am]
BILLING CODE 4320-MR-P