KC Lake Hydro LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 21233-21234 [2014-08494]
Download as PDF
Federal Register / Vol. 79, No. 72 / Tuesday, April 15, 2014 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14572–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Siting Renewables, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On December 16, 2013, Siting
Renewables, LLC, filed an application
for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of the Hepburn Street Dam
Hydroelectric Project (Hepburn Project
or project) to be located on West Branch
of the Susquehanna River, near South
Williamsport, Lycoming County,
Pennsylvania. The Hepburn Street Dam
is owned by the state of Pennsylvania.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) The existing
reinforced concrete overflow dam, 1,200
feet long and approximately 14.5 feet
high discharging into the West Branch
of the Susquehanna River; (2) nine
channels, each with two 350- kilowatt
(kW) very low head (VLH) turbines and
generators, rated at 350 kW each, with
a maximum generating capacity of 6,300
kW, with a maximum hydraulic
capacity of 8,774 cubic feet per second
under a gross head of 14 feet, (3) nine
new heavy flotsam racks; (4) a crestmounted walkway carrying hydraulic
and electrical conduits from the VLH
turbines to a new powerhouse; (5) one
hydraulic and electrical controls
module; and (6) one 600-foot-long
12.42/7.2 kilovolt primary transmission
line. The estimated annual generation of
the Hepburn Project would be
33,100,000 kilowatthours.
Applicant Contact: Mr. Ralph J. Jones,
Siting Renewables, LLC, 1800 Rt. 34,
Suite 101, Wall, NJ 07719; phone: (855)
946–7652.
FERC Contact: Timothy Looney;
phone: (202) 502–6096.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
VerDate Mar<15>2010
18:06 Apr 14, 2014
Jkt 232001
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14572–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14572) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: April 9, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08495 Filed 4–14–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. P–14558–000]
KC Lake Hydro LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On October 4, 2013, KC Lake Hydro
LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
North Hadley Lake Warner Dam
Hydropower Project (project) to be
located at the outlet of Lake Warner, on
the Miller River, near the Town of North
Hadley, Hampshire County,
Massachusetts. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
21233
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist
of: (1) The existing 82-foot-long, 15-foothigh, concrete gravity Lake Warner dam;
(2) an existing 70-acre impoundment
with a normal maximum water surface
elevation of 128 feet above mean sea
level; (3) a new 30.6-foot-long, 10.4-footdiameter conduit structure; (4) a new
20-foot-long, 20-foot-wide powerhouse
containing a single turbine generator
unit with an installed capacity of 100.8
kilowatts; (5) a new 100-foot-long, 21kilovolt transmission line; and (6)
appurtenant facilities. The project
would have an estimated average annual
energy generation of 500 megawatthours. The dam is owned and operated
by the Kestrel Land Trust. There are no
federal lands associated with the
project.
Applicant Contact: Ms. Kelly
Sackheim, Principal, KC Lake Hydro
LLC, 5096 Cocoa Palm Way, Fair Oaks,
California 95628; phone: (301) 401–
5978.
FERC Contact: Michael Watts; phone:
(202) 502–6123; email: michael.watts@
ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14558–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14558) in the docket number field to
E:\FR\FM\15APN1.SGM
15APN1
21234
Federal Register / Vol. 79, No. 72 / Tuesday, April 15, 2014 / Notices
access the document. For assistance,
contact FERC Online Support.
Dated: April 9, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08494 Filed 4–14–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14573–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Siting Renewables, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On December 17, 2013, Siting
Renewables, LLC, filed an application
for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of the Easton Dam Hydroelectric Project
(Easton Dam Project or project) to be
located on the Lehigh River, near
Easton, Northampton County,
Pennsylvania. The Easton Dam is owned
by the state of Pennsylvania. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
the following: (1) An existing dam,
reinforced with concrete in 1967, 30 feet
high; (2) a 590-foot-long concrete
spillway discharging into the Delaware
River; (3) two channels, each with three,
500-kilowatt (kW) very low head (VLH)
turbines and generators with a
maximum generating capacity of 3000
kW, with a maximum hydraulic
capacity of 2,300 cubic feet per second
under a 30-foot gross head; (4) two new
heavy flotsam racks; (5) a crest mounted
walkway, carrying hydraulic and
electrical conduits from the VLH
turbines to a new powerhouse; (6) one
hydraulic and electrical controls
module; and (7) one 4,800-foot-long
12.42/7.2 kilovolt primary transmission
line. The estimated annual generation of
the Easton Dam Project would be
15,770,000 kilowatthours.
Applicant Contact: Mr. Ralph J. Jones,
Siting Renewables, LLC, 1800 Rt. 34,
Suite 101, Wall, NJ 07719; phone: (855)
946–7652.
VerDate Mar<15>2010
18:06 Apr 14, 2014
Jkt 232001
FERC Contact: Timothy Looney;
phone: (202) 502–6096.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14573–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14573) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: April 9, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08497 Filed 4–14–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14576–000]
Warm Springs Hydro LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On January 13, 2014, Warm Spring
Hydro LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Unity Dam Hydroelectric Project
(project) to be located on the Burnt
River near Unity in Baker County,
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
Illinois. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would be
located at the U. S. Bureau of
Reclamation’s Unity Dam and would
consist of the following new facilities:
(1) A bifurcation at the end of the
existing discharge pipe; (2) a 130-footlong, 4-foot-diameter steel penstock; (3)
a powerhouse containing two Francis
turbine/generator units with a combined
rated capacity of 800 kilowatts at 100
feet of design head; (4) a 500-foot-long,
12.5-kilovolt transmission line
extending from the powerhouse to an
existing transmission line (the point of
interconnection); and (5) appurtenant
facilities. The estimated annual
generation of the project would be 3,400
megawatt-hours.
Applicant Contact: Mr. Nick Josten,
GeoSense, 2742 St. Charles Avenue,
Idaho Falls, ID 83404; phone: (208) 522–
8069.
FERC Contact: Kim Nguyen; phone:
(202) 502–6105.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14576–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
E:\FR\FM\15APN1.SGM
15APN1
Agencies
[Federal Register Volume 79, Number 72 (Tuesday, April 15, 2014)]
[Notices]
[Pages 21233-21234]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-08494]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-14558-000]
KC Lake Hydro LLC; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
On October 4, 2013, KC Lake Hydro LLC filed an application for a
preliminary permit, pursuant to section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility of the North Hadley Lake
Warner Dam Hydropower Project (project) to be located at the outlet of
Lake Warner, on the Miller River, near the Town of North Hadley,
Hampshire County, Massachusetts. The sole purpose of a preliminary
permit, if issued, is to grant the permit holder priority to file a
license application during the permit term. A preliminary permit does
not authorize the permit holder to perform any land-disturbing
activities or otherwise enter upon lands or waters owned by others
without the owners' express permission.
The proposed project would consist of: (1) The existing 82-foot-
long, 15-foot-high, concrete gravity Lake Warner dam; (2) an existing
70-acre impoundment with a normal maximum water surface elevation of
128 feet above mean sea level; (3) a new 30.6-foot-long, 10.4-foot-
diameter conduit structure; (4) a new 20-foot-long, 20-foot-wide
powerhouse containing a single turbine generator unit with an installed
capacity of 100.8 kilowatts; (5) a new 100-foot-long, 21-kilovolt
transmission line; and (6) appurtenant facilities. The project would
have an estimated average annual energy generation of 500 megawatt-
hours. The dam is owned and operated by the Kestrel Land Trust. There
are no federal lands associated with the project.
Applicant Contact: Ms. Kelly Sackheim, Principal, KC Lake Hydro
LLC, 5096 Cocoa Palm Way, Fair Oaks, California 95628; phone: (301)
401-5978.
FERC Contact: Michael Watts; phone: (202) 502-6123; email:
michael.watts@ferc.gov.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-14558-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-14558) in the docket number field to
[[Page 21234]]
access the document. For assistance, contact FERC Online Support.
Dated: April 9, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-08494 Filed 4-14-14; 8:45 am]
BILLING CODE 6717-01-P