El Dorado Irrigation District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions to Intervene, 21235-21236 [2014-08400]
Download as PDF
Federal Register / Vol. 79, No. 72 / Tuesday, April 15, 2014 / Notices
elibrary.asp. Enter the docket number
(P–14576) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: April 8, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08408 Filed 4–14–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CD14–16–000]
El Dorado Irrigation District; Notice of
Preliminary Determination of a
Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions to Intervene
On March 25, 2014, El Dorado
Irrigation District filed a notice of intent
to construct a qualifying conduit
hydropower facility, pursuant to section
30 of the Federal Power Act, as
amended by section 4 of the
Hydropower Regulatory Efficiency Act
of 2013 (HREA). The proposed Tank 3
In-conduit Hydroelectric Project would
have an installed capacity of 600
kilowatts (kW) and would utilize an
existing 30-diameter water supply
pipeline. The project would be located
near the Town of Camino, El Dorado
County, California.
Applicant Contact: Cindy
Megerdigan, El Dorado Irrigation
District, 2890 Mosquito Road,
Placerville, CA 95667 Phone No. (530)
642–4056.
FERC Contact: Robert Bell, Phone No.
(202) 502–6062, email: robert.bell@
ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) A proposed
20-foot-long, 24-inch diameter pipeline
21235
that branches off the 30-inch diameter
main water supply pipe, which carries
water in succession to; (2) three
proposed 20-foot-long, 16-inch diameter
pipes along which are; (3) three
generating units, with a total installed
capacity of 600 kW; (4) a proposed 20foot-long, 24-inch-diameter discharge
pipe that receives water from the three
16-inch diameter pipes; (5) a proposed
20-foot-long, 24-inch diameter bypass
pipe to be used when the plant is shut
down; and (6) appurtenant facilities.
The proposed project would have an
estimated annual generating capacity of
2,900 megawatt-hours.
A qualifying conduit hydropower
facility is one that is determined or
deemed to meet all of the criteria shown
in the table below.
TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
Statutory provision
Description
Satisfies
(Y/N)
FPA 30(a)(3)(A), as amended by HREA ..
The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or
similar manmade water conveyance that is operated for the distribution of water
for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.
The facility is constructed, operated, or maintained for the generation of electric
power and uses for such generation only the hydroelectric potential of a non-federally owned conduit.
The facility has an installed capacity that does not exceed 5 megawatts ..................
Y
FPA 30(a)(3)(C)(i), as amended by HREA
mstockstill on DSK4VPTVN1PROD with NOTICES
FPA 30(a)(3)(C)(ii), as amended
HREA.
FPA 30(a)(3)(C)(iii), as amended
HREA.
by
by
On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.
Preliminary Determination: Based
upon the above criteria, Commission
staff preliminarily determines that the
proposal satisfies the requirements for a
qualifying conduit hydropower facility,
which is not required to be licensed or
exempted from licensing.
Comments and Motions to Intervene:
Deadline for filing comments contesting
whether the facility meets the qualifying
criteria is 45 days from the issuance
date of this notice.
Deadline for filing motions to
intervene is 30 days from the issuance
date of this notice.
Anyone may submit comments or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210 and
385.214. Any motions to intervene must
be received on or before the specified
deadline date for the particular
proceeding.
Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the ‘‘COMMENTS
VerDate Mar<15>2010
18:06 Apr 14, 2014
Jkt 232001
CONTESTING QUALIFICATION FOR A
CONDUIT HYDROPOWER FACILITY’’
or ‘‘MOTION TO INTERVENE,’’ as
applicable; (2) state in the heading the
name of the applicant and the project
number of the application to which the
filing responds; (3) state the name,
address, and telephone number of the
person filing; and (4) otherwise comply
with the requirements of sections
385.2001 through 385.2005 of the
Commission’s regulations.1 All
comments contesting Commission staff’s
preliminary determination that the
facility meets the qualifying criteria
must set forth their evidentiary basis.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and comments using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
1 18
PO 00000
CFR 385.2001–2005 (2013).
Frm 00033
Fmt 4703
Sfmt 4703
Y
Y
Y
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov,(866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
A copy of all other filings in reference
to this application must be accompanied
by proof of service on all persons listed
in the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Locations of Notice of Intent: Copies
of the notice of intent can be obtained
directly from the applicant or such
copies can be viewed and reproduced at
the Commission in its Public Reference
Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may
also be viewed on the web at https://
E:\FR\FM\15APN1.SGM
15APN1
21236
Federal Register / Vol. 79, No. 72 / Tuesday, April 15, 2014 / Notices
www.ferc.gov/docs-filing/elibrary.asp
using the ‘‘eLibrary’’ link. Enter the
docket number (e.g., CD14–16–000) in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or email
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659.
Dated: April 8, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08400 Filed 4–14–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–135–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
East Cheyenne Gas Storage, LLC;
Notice of Request Under Blanket
Authorization
Take notice that on April 4, 2014, East
Cheyenne Gas Storage, LLC (East
Cheyenne), 10370 Richmond Avenue,
Suite 510, Houston, Texas 77042, filed
in Docket No. CP14–135–000, a prior
notice request pursuant to sections
157.205 and 157.213 of the
Commission’s regulations under the
Natural Gas Act (NGA). East Cheyenne
seeks authorization to convert its well
WP–D003–2 in Logan County, Colorado,
currently certificated as an injection/
withdrawal well, to an observation well.
East Cheyenne proposes to perform
these activities under its blanket
certificate issued in Docket No. CP10–
34–000 [132 FERC ¶ 61,097 (2010)], all
as more fully set forth in the application
which is on file with the Commission
and open to public inspection.
The filing may be viewed on the web
at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed to James
Hoff, Vice President, Reservoir
Engineering, East Cheyenne Gas Storage,
LLC, 10370 Richmond Avenue, Suite
510, Houston, Texas 77042, or by calling
(713) 403–6467 (telephone) or (713)
403–6461 (fax) jhoff@mehllc.com.
Any person or the Commission’s Staff
may, within 60 days after the issuance
of the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
VerDate Mar<15>2010
18:06 Apr 14, 2014
Jkt 232001
of intervention and, pursuant to section
157.205 of the Commission’s
Regulations under the NGA (18 CFR
157.205) a protest to the request. If no
protest is filed within the time allowed
therefore, the proposed activity shall be
deemed to be authorized effective the
day after the time allowed for protest. If
a protest is filed and not withdrawn
within 30 days after the time allowed
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to Section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the internet in lieu
of paper. See 18 CFR 385.2001(a) (1) (iii)
and the instructions on the
Commission’s Web site (www.ferc.gov)
under the ‘‘e-Filing’’ link. Persons
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
unable to file electronically should
submit an original and 5 copies of the
protest or intervention to the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
See, 18CFR 385.2001(a) (1) (iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Dated: April 8, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08402 Filed 4–14–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–126–000]
American Midstream (Midla), LLC;
Notice of Request Under Blanket
Authorization
Take notice that on March 28, 2014,
American Midstream (Midla), LLC, 1400
16th Street, Suite 310, Denver, CO
80202–5994, filed in Docket No. CP14–
126–000, a prior notice request,
pursuant to sections 157.205 and
157.216(b)(2) of the Commission’s
Regulations under the Natural Gas Act,
and Midla’s blanket certificate issued in
Docket No. CP82–539, for authorization
to abandon two portions of its pipeline
system: The ‘‘T–32 System’’ in Ouachita
Parish, Louisiana which consists of
Midla’s T–32, T–63 and T–64 Lateral
lines; and, the ‘‘Baton Rouge System’’
which consists of the welded portions of
Midla’s T–1 and T–1 Loop lines plus its
T–55, T–61, and TH–5 Lines; one
delivery meter on a non-contiguous
pipeline (the T–62 Line); three
additional non-contiguous meter
stations; and one section of noncontiguous pipeline (the T–61 Line), all
located in East Baton Rouge Parish,
Louisiana, to its affiliate, Mid-Louisiana
Gas Transmission, LLC (MLGT). Midla
states that MLGT intends to operate the
laterals as a Hinshaw Pipeline. The
filing is available for review at the
Commission in the Public Reference
Room or may be viewed on the
Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. There is
an ‘‘eSubscription’’ link on the Web site
that enables subscribers to receive email
notification when a document is added
to a subscribed docket(s). For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
E:\FR\FM\15APN1.SGM
15APN1
Agencies
[Federal Register Volume 79, Number 72 (Tuesday, April 15, 2014)]
[Notices]
[Pages 21235-21236]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-08400]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CD14-16-000]
El Dorado Irrigation District; Notice of Preliminary
Determination of a Qualifying Conduit Hydropower Facility and
Soliciting Comments and Motions to Intervene
On March 25, 2014, El Dorado Irrigation District filed a notice of
intent to construct a qualifying conduit hydropower facility, pursuant
to section 30 of the Federal Power Act, as amended by section 4 of the
Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Tank
3 In-conduit Hydroelectric Project would have an installed capacity of
600 kilowatts (kW) and would utilize an existing 30-diameter water
supply pipeline. The project would be located near the Town of Camino,
El Dorado County, California.
Applicant Contact: Cindy Megerdigan, El Dorado Irrigation District,
2890 Mosquito Road, Placerville, CA 95667 Phone No. (530) 642-4056.
FERC Contact: Robert Bell, Phone No. (202) 502-6062, email:
robert.bell@ferc.gov.
Qualifying Conduit Hydropower Facility Description: The proposed
project would consist of: (1) A proposed 20-foot-long, 24-inch diameter
pipeline that branches off the 30-inch diameter main water supply pipe,
which carries water in succession to; (2) three proposed 20-foot-long,
16-inch diameter pipes along which are; (3) three generating units,
with a total installed capacity of 600 kW; (4) a proposed 20-foot-long,
24-inch-diameter discharge pipe that receives water from the three 16-
inch diameter pipes; (5) a proposed 20-foot-long, 24-inch diameter
bypass pipe to be used when the plant is shut down; and (6) appurtenant
facilities. The proposed project would have an estimated annual
generating capacity of 2,900 megawatt-hours.
A qualifying conduit hydropower facility is one that is determined
or deemed to meet all of the criteria shown in the table below.
Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
Statutory provision Description Satisfies (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by The conduit the Y
HREA. facility uses is a
tunnel, canal,
pipeline, aqueduct,
flume, ditch, or
similar manmade water
conveyance that is
operated for the
distribution of water
for agricultural,
municipal, or
industrial
consumption and not
primarily for the
generation of
electricity.
FPA 30(a)(3)(C)(i), as amended The facility is Y
by HREA. constructed,
operated, or
maintained for the
generation of
electric power and
uses for such
generation only the
hydroelectric
potential of a non-
federally owned
conduit.
FPA 30(a)(3)(C)(ii), as amended The facility has an Y
by HREA. installed capacity
that does not exceed
5 megawatts.
FPA 30(a)(3)(C)(iii), as On or before August 9, Y
amended by HREA. 2013, the facility is
not licensed, or
exempted from the
licensing
requirements of Part
I of the FPA.
------------------------------------------------------------------------
Preliminary Determination: Based upon the above criteria,
Commission staff preliminarily determines that the proposal satisfies
the requirements for a qualifying conduit hydropower facility, which is
not required to be licensed or exempted from licensing.
Comments and Motions to Intervene: Deadline for filing comments
contesting whether the facility meets the qualifying criteria is 45
days from the issuance date of this notice.
Deadline for filing motions to intervene is 30 days from the
issuance date of this notice.
Anyone may submit comments or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210 and 385.214. Any motions to intervene must be received on or
before the specified deadline date for the particular proceeding.
Filing and Service of Responsive Documents: All filings must (1)
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as
applicable; (2) state in the heading the name of the applicant and the
project number of the application to which the filing responds; (3)
state the name, address, and telephone number of the person filing; and
(4) otherwise comply with the requirements of sections 385.2001 through
385.2005 of the Commission's regulations.\1\ All comments contesting
Commission staff's preliminary determination that the facility meets
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------
\1\ 18 CFR 385.2001-2005 (2013).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filing. Please file
motions to intervene and comments using the Commission's eFiling system
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov,(866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. A copy of all other filings in
reference to this application must be accompanied by proof of service
on all persons listed in the service list prepared by the Commission in
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
Locations of Notice of Intent: Copies of the notice of intent can
be obtained directly from the applicant or such copies can be viewed
and reproduced at the Commission in its Public Reference Room, Room 2A,
888 First Street NE., Washington, DC 20426. The filing may also be
viewed on the web at https://
[[Page 21236]]
www.ferc.gov/docs-filing/elibrary.asp using the ``eLibrary'' link.
Enter the docket number (e.g., CD14-16-000) in the docket number field
to access the document. For assistance, call toll-free 1-866-208-3676
or email FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659.
Dated: April 8, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-08400 Filed 4-14-14; 8:45 am]
BILLING CODE 6717-01-P