Commission Information Collection Activities, (FERC-725E, FERC-583, FERC-512, and FERC-588); Consolidated Comment Request; Extension, 19888-19891 [2014-08038]
Download as PDF
19888
Federal Register / Vol. 79, No. 69 / Thursday, April 10, 2014 / Notices
cable shall be connected to the freezer
prior to testing. The freezer must be
plugged in in during testing, but shall be
placed in the ‘‘off’’ position on the
control panel. The refrigerator portion of
the control panel shall then be used to
set the appropriate temperatures for the
refrigerator test as required by Section 3.
Test Control Settings and perform the
remainder of the test as prescribed by
this Appendix.
(4) Representations. Liebherr may
make representations about the energy
use of its refrigerator-freezer products
for compliance, marketing, or other
purposes only to the extent that such
products have been tested in accordance
with the provisions outlined above and
such representations fairly disclose the
results of such testing.
DOE notes that Liebherr has not
petitioned for a test procedure waiver
nor requested an interim waiver for its
accompanying freezer models. Thus, the
freezer models shall be tested according
to the applicable test procedure in
appendix B to subpart B of 10 CFR part
430 without modification.
(5) This waiver shall remain in effect
consistent with the provisions of 10 CFR
430.27(m).
(6) This waiver is issued on the
condition that the statements,
representations, and documentary
materials provided by the petitioner are
valid and accurate. DOE may revoke or
modify this waiver at any time if it
determines the factual basis underlying
the petition for waiver is incorrect, or
the results from the alternate test
procedure are unrepresentative of the
basic models’ true energy consumption
characteristics.
(7) This waiver applies only to those
basic models set out in Liebherr’s
September 27, 2013, petition for waiver.
The granting of this waiver does not
release the petitioner from the
certification requirements set forth at 10
CFR part 429.
sroberts on DSK5SPTVN1PROD with NOTICES
Issued in Washington, DC, on April 4,
2014.
Kathleen B. Hogan
Deputy Assistant Secretary for Energy
Efficiency, Energy Efficiency and Renewable
Energy.
[FR Doc. 2014–08076 Filed 4–9–14; 8:45 am]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC14–10–000]
Commission Information Collection
Activities, (FERC–725E, FERC–583,
FERC–512, and FERC–588);
Consolidated Comment Request;
Extension
Federal Energy Regulatory
Commission, DOE.
ACTION: Notice of information
collections and request for comments.
AGENCY:
In compliance with the
requirements of the Paperwork
Reduction Act of 1995, 44 USC
3506(c)(2)(A), the Federal Energy
Regulatory Commission (Commission or
FERC) is soliciting public comment on
the requirements and burden 1 of the
information collections described
below. Please note that this is the first
time FERC has issued a consolidated
notice involving otherwise unrelated
information collections.
DATES: Comments on the collections of
information are due June 9, 2014.
ADDRESSES: You may submit comments
(identified by Docket No. IC14–10–000)
by either of the following methods:
• eFiling at Commission’s Web site:
https://www.ferc.gov/docs-filing/
efiling.asp
• Mail/Hand Delivery/Courier:
Federal Energy Regulatory Commission,
Secretary of the Commission, 888 First
Street NE., Washington, DC 20426.
Please reference the specific
collection number and/or title in your
comments.
Instructions: All submissions must be
formatted and filed in accordance with
submission guidelines at: https://
www.ferc.gov/help/submissionguide.asp. For user assistance contact
FERC Online Support by email at
ferconlinesupport@ferc.gov, or by phone
at: (866) 208–3676 (toll-free), or (202)
502–8659 for TTY.
Docket: Users interested in receiving
automatic notification of activity in this
docket or in viewing/downloading
comments and issuances in this docket
may do so at https://www.ferc.gov/docsfiling/docs-filing.asp.
FOR FURTHER INFORMATION CONTACT:
Ellen Brown may be reached by email
at DataClearance@FERC.gov, telephone
SUMMARY:
BILLING CODE 6450–01–P
1 The Commission defines burden as the total
time, effort, or financial resources expended by
persons to generate, maintain, retain, or disclose or
provide information to or for a Federal agency. For
further explanation of what is included in the
information collection burden, reference 5 Code of
Federal Regulations 1320.3.
VerDate Mar<15>2010
18:14 Apr 09, 2014
Jkt 232001
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
at (202) 502–8663, and fax at (202) 273–
0873.
SUPPLEMENTARY INFORMATION:
Type of Request: Three-year extension
of the information collection
requirements for all collections
described below with no changes to the
current reporting requirements. Please
note that each collection is distinct from
the others contained within this notice.
Comments: Comments are invited on:
(1) Whether the collections of
information are necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s
estimates of the burden and cost of the
collections of information, including the
validity of the methodology and
assumptions used; (3) ways to enhance
the quality, utility and clarity of the
information collections; and (4) ways to
minimize the burden of the collections
of information on those who are to
respond, including the use of automated
collection techniques or other forms of
information technology.
FERC–725E, Mandatory Reliability
Standards for the Western Electric
Coordinating Council
OMB Control No.: 1902–0246.
Abstract: The information collected
by the FERC–725E (OMB Control No.
1902–0246) is required to implement
the statutory provisions of section 215
of the Federal Power Act (FPA) (16
U.S.C. 824o). Section 215 of the FPA
buttresses the Commission’s efforts to
strengthen the reliability of the
interstate grid through the grant of new
authority by providing for a system of
mandatory Reliability Standards
developed by the Electric Reliability
Organization. Reliability Standards that
the ERO proposes to the Commission
may include Reliability Standards that
are proposed to the ERO by a Regional
Entity.2 A Regional Entity is an entity
that has been approved by the
Commission to enforce Reliability
Standards under delegated authority
from the ERO.3 On June 8, 2008 in an
adjudicatory order, the Commission
approved eight regional Reliability
Standards submitted by the ERO that
were proposed by the Western
Electricity Coordinating Council
(WECC).4
WECC is responsible for coordinating
and promoting electric system
reliability. In addition to promoting a
reliable electric power system in the
Western Interconnection, WECC
2 16
U.S.C. 824o(e)(4).
U.S.C. 824o(a)(7) and (e)(4).
4 72FR33462, June 18, 2007.
3 16
E:\FR\FM\10APN1.SGM
10APN1
19889
Federal Register / Vol. 79, No. 69 / Thursday, April 10, 2014 / Notices
supports efficient competitive power
markets, ensures open and nondiscriminatory transmission access
among members, and provides a forum
for resolving transmission access
disputes plus the coordination of
operating and planning activities of its
members.
There are eight Reliability Standards
currently applicable in the WECC
region. These standards generally
require entities to document compliance
with substantive requirements, retain
documentation, and submit reports to
WECC.
• BAL–002–WECC–2 requires
balancing authorities and reserve
sharing groups to document compliance
with the contingency reserve
requirements described in the standard.
• BAL–004–WECC–02 requires
balancing authorities to document that
time error corrections and primary
inadvertent interchange payback were
conducted according the requirements
in the standard.
• FAC–501–WECC–1 requires
transmission owners with certain
transmission paths to have a
transmission maintenance and
inspection plan and to document
maintenance and inspection activities
according to the plan.
• IRO–006–WECC–1 requires
balancing authorities and reliability
coordinators document actions taken to
mitigate unscheduled flow.
• PRC–004–WECC–1 requires
transmission owners, generator owners
and transmission operators to document
their analysis and/or mitigation due to
certain misoperations on major transfer
paths. This standard requires that
documentation be kept for six years.
• TOP–007–WECC–1 requires
transmission operators to document that
when actual flows on major transfer
paths exceed system operating limits
their schedules and actual flows are not
exceeded for longer than a specified
time.
• VAR–002–WECC–1 requires
generator operators and transmission
operators to provide quarterly reports to
the compliance monitor and have
evidence related to their synchronous
generators, synchronous condensers,
and automatic voltage regulators.
• VAR–501–WECC–1 requires
generator operators to provide quarterly
reports to the compliance monitor and
have evidence regarding operation of
their power system stabilizers.
The information generated by these
standards generally serves to ensure
entities are complying with applicable
Reliability Standards.
Type of Respondents: Balancing
authorities, reserve sharing groups,
transmission owners, reliability
coordinators, transmission operators,
generator operators.
Estimate of Annual Burden: The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–725E, MANDATORY RELIABILITY STANDARDS FOR THE WESTERN ELECTRIC COORDINATING COUNCIL
Number of
respondents 5
Average
burden/cost
per response
Total annual
burden hours
(Total annual
cost)
(1)
FERC data collection
Annual
number of
responses per
respondent
(2)
(4)
(1)*(2)*(3)
FERC–725E
Reporting:
Balancing Authorities ........................................................................
Generator Operators ........................................................................
Transmission Operators applicable to standard VAR–002 6 ............
Transmission Operators that operate qualified transfer paths 7 .......
Transmission Owners that operate qualified transfer paths 8 ..........
Reliability Coordinators .....................................................................
Reserve Sharing Group ....................................................................
1
1
4
3
3
1
1
21
10
10
40
40
1
1
714
2,280
3,440
1,080
600
1
3
Total ...........................................................................................
Record-keeping: 9
Balancing Authorities ........................................................................
Balancing Authorities (IRO–006) 10 ..................................................
Generator Operators ........................................................................
Transmission Operator (VAR–002) ..................................................
Transmission Operator .....................................................................
Transmission Owner .........................................................................
Reliability Coordinator 11 ...................................................................
..........................
..........................
..........................
8,118
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
..........................
71
34
228
344
108
60
34
Total ...........................................................................................
sroberts on DSK5SPTVN1PROD with NOTICES
34
228
86
9
5
1
3
..........................
..........................
..........................
879
5 Number of respondents derived from the NERC
Compliance Registry as of February 25, 2014.
6 Based on estimates in Order 751, Docket No.
RM09–9–000
7 Based on burden estimates taken from the Order
in Docket No. RR07–11–000 P. 130.
8 Id.
9 Based on 10% total annual burden hours per
response.
10 Based on record keeping hours for Balancing
Authorities in Order 746 in Docket No. RM09–19–
000 implementing IRO–006–WECC–1.
VerDate Mar<15>2010
18:14 Apr 09, 2014
Jkt 232001
FERC–583, Annual Kilowatt Generating
Report (Annual Charges)
OMB Control No.: 1902–0136.
Abstract: The FERC–583 is used by
the Commission to implement the
statutory provisions of section 10(e) of
the Federal Power Act (FPA) (16 U.S.C.
803(e)), which requires the Commission
to collect annual charges from
hydropower licensees for, among other
11 Based on record keeping hours in Order 746 in
Docket No. RM09–19–000.
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
things, the cost of administering Part I
of the FPA and for the use of United
States dams. In addition, section 3401 of
the Omnibus Budget Reconciliation Act
of 1986 (OBRA) authorizes the
Commission to ‘‘assess and collect fees
and annual charges in any fiscal year in
amounts equal to all of the costs
incurred by the Commission in that
fiscal year.’’ The information is
collected annually and used to
determine the amounts of the annual
charges to be assessed licensees for
E:\FR\FM\10APN1.SGM
10APN1
19890
Federal Register / Vol. 79, No. 69 / Thursday, April 10, 2014 / Notices
reimbursable government administrative
costs and for the use of government
dams. The Commission implements
these filing requirements in the Code of
Federal Regulations (CFR) under 18 CFR
part 11.
Type of Respondent: FERC-regulated
private and public hydropower
licensees.
Estimate of Annual Burden: The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–583, ANNUAL KILOWATT GENERATING REPORT (ANNUAL CHARGES)
Number of
respondents 12
Annual
number
of responses per
respondent
Total number
of responses
Average
burden and cost
per response 13
Total annual
burden hours and
total annual cost
Cost per
respondent
($)
(1)
(2)
(1)*(2)=(3)
(4)
(3)*(4)=(5)
(5)÷(1)
517
1
517
2
$141
1,034
$72,897
$141
FERC–512, Application for Preliminary
Permit
OMB Control No.: 1902–0073.
Abstract: The Commission uses the
information collected under the
requirements of FERC–512 to
implement the statutory provisions of
sections 4(f), 5 and 7 of the Federal
Power Act (FPA).14 The purpose of
obtaining a preliminary permit is to
maintain priority of the application for
a license for a hydropower facility while
the applicant conducts surveys to
prepare maps, plans, specifications and
estimates; conducts engineering,
economic and environmental feasibility
studies; and making financial
arrangements. The conditions under
which the priority will be maintained
are set forth in each permit. During the
term of the permit, no other application
for a preliminary permit or application
for a license submitted by another party
can be accepted. The term of the permit
is three years. The information collected
under the designation FERC–512 is in
the form of a written application for a
preliminary permit which is used by
Commission staff to determine an
applicant’s qualifications to hold a
preliminary permit, review the
proposed hydro development for
feasibility and to issue a notice of the
application in order to solicit public and
agency comments. The Commission
implements these mandatory filing
requirements in the Code of Federal
Regulations (CFR) under 18 CFR 4.31–
.33, 4.81–.83.
Type of Respondents: Hydropower
facilities.
Estimate of Annual Burden: The
Commission estimates the annual public
reporting burden for the information
collectionas:
FERC–512—APPLICATION FOR PRELIMINARY PERMIT
Number of
respondents
Annual
number of
responses per
respondent
Total number
of responses
Average
burden/$ per
response 15
Total annual burden
hours (total annual
cost)
Cost per
respondent
($)
(1)
(2)
(1)*(2)=(3)
(4)
(3)*(4)=(5)
(5)÷(1)
125
1
125
37
$2,608.50
4,625
$326,062.50
$2,608.50
OMB Control No.: 1902–0144.
Abstract: The Commission uses the
information collected under the
requirements of FERC–588 to
implement the statutory provisions of
sections 7(c) of the Natural Gas Act
(NGA) (Pub. L. 75–688) (15 U.S.C. 717–
717w) and provisions of the Natural Gas
Policy Act of 1978 (NGPA), 15 U.S.C.
3301–3432. Under the NGA, a natural
gas company must obtain Commission
approval to engage in the transportation,
sale or exchange of natural gas in
interstate commerce. However, section
7(c) exempts from certificate
requirements ‘‘temporary acts or
operations for which the issuance of a
certificate will not be required in the
public interest.’’ The NGPA also
provides for non-certificated interstate
transactions involving intrastate
pipelines and local distribution
companies.
A temporary operation, or emergency,
is defined as any situation in which an
actual or expected shortage of gas
supply would require an interstate
pipeline company, intrastate pipeline,
local distribution company, or Hinshaw
pipeline to curtail deliveries of gas or
provide less than the projected level of
service to the customer. The natural gas
companies which provide the temporary
assistance to the companies which are
having the ‘‘emergency’’ must file the
necessary information described in Part
284, Subpart I of the Commission’s
Regulations with the Commission so
that it may determine if their assisting
transaction/operation qualifies for
exemption. The assisting company may
or may not be under the Commission’s
jurisdiction and if their assisting actions
qualify for the exemption, they will not
become subject to the Commission’s
jurisdiction for such actions.
A report within forty-eight hours of
the commencement of the
transportation, sale or exchange, a
request to extend the sixty-day term of
12 Based on data from Fiscal Year 2013, there
were 517 projects, owned by 241 FERC-regulated
private and public licensees. Many of the licensees
owned multiple projects.
13 The estimates for cost per response are derived
using the following formula: Average Burden Hours
per Response * $70.50 per hour.
14 16 U.S.C. 797, 798, & 800.
15 The estimates for cost per response are derived
using the following formula: Average Burden Hours
per Response * $70.50 per hour.
sroberts on DSK5SPTVN1PROD with NOTICES
FERC–588, Emergency Natural Gas
Transportation, Sale, and Exchange
Transportation
VerDate Mar<15>2010
18:14 Apr 09, 2014
Jkt 232001
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
E:\FR\FM\10APN1.SGM
10APN1
19891
Federal Register / Vol. 79, No. 69 / Thursday, April 10, 2014 / Notices
the emergency transportation, if needed,
and a termination report are required.
The data required to be filed for the
forty-eight hour report is specified by 18
CFR 284.270.
Type of Respondents: Natural Gas
Pipelines.
Estimate of Annual Burden: The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–588—EMERGENCY NATURAL GAS TRANSPORTATION, SALE, AND EXCHANGE TRANSPORTATION
Number of
respondents
Annual
number of
responses per
respondent
Total number
of responses
Average burden/$
per response 16
Total annual burden
hours
(total annual cost)
Cost per
respondent
($)
(1)
(2)
(1)*(2)=(3)
(4)
(3)*(4)=(5)
(5)÷(1)
8
1
8
10
$705
80
$5,640
$705
Dated: April 2, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–08038 Filed 4–9–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC14–4–000]
Commission Information Collection
Activities (FERC–73); Comment
Request
Federal Energy Regulatory
Commission, DOE.
ACTION: Comment request.
AGENCY:
In compliance with the
requirements of the Paperwork
Reduction Act of 1995, the Federal
Energy Regulatory Commission
(Commission or FERC) is submitting the
information FERC–73, Oil Pipeline
Service Life Data, to the Office of
Management and Budget (OMB) for
review of the information collection
requirements. Any interested person
may file comments directly with OMB
and should address a copy of those
comments to the Commission as
explained below. In response to the
notice issued in the Federal Register (79
FR 3362, January 21, 2014) FERC
received one comment. FERC responds
to the comment below as well as in its
submittal to OMB.
DATES: Comments on the collection of
information are due by May 12, 2014.
ADDRESSES: Comments filed with OMB,
identified by the OMB Control No.
1902–0019, should be sent via email to
the Office of Information and Regulatory
Affairs: oira_submission@omb.gov.
sroberts on DSK5SPTVN1PROD with NOTICES
SUMMARY:
16 The estimates for cost per response are derived
using the following formula: Average Burden Hours
per Response * $70.50 per hour.
VerDate Mar<15>2010
18:14 Apr 09, 2014
Jkt 232001
Attention: Federal Energy Regulatory
Commission Desk Officer. The Desk
Officer may also be reached via
telephone at 202–395–4718.
A copy of the comments should also
be sent to the Federal Energy Regulatory
Commission, identified by the Docket
No. IC14–4–000, by either of the
following methods:
• eFiling at Commission’s Web site:
https://www.ferc.gov/docs-filing/
efiling.asp.
• Mail/Hand Delivery/Courier:
Federal Energy Regulatory Commission,
Secretary of the Commission, 888 First
Street NE., Washington, DC 20426.
Instructions: All submissions must be
formatted and filed in accordance with
submission guidelines at: https://
www.ferc.gov/help/submissionguide.asp. For user assistance contact
FERC Online Support by email at
ferconlinesupport@ferc.gov, or by phone
at: (866) 208–3676 (toll-free), or (202)
502–8659 for TTY.
Docket: Users interested in receiving
automatic notification of activity in this
docket or in viewing/downloading
comments and issuances in this docket
may do so at https://www.ferc.gov/docsfiling/docs-filing.asp.
FOR FURTHER INFORMATION CONTACT:
Ellen Brown may be reached by email
at DataClearance@FERC.gov, by
telephone at (202) 502–8663, and by fax
at (202) 273–0873.
SUPPLEMENTARY INFORMATION:
Title: FERC–73, Oil Pipeline Service
Life Data
OMB Control No.: 1902–0019
Type of Request: Three-year extension
of the FERC–73 information collection
requirements with no changes to the
current reporting requirements.
Abstract: The Commission has
authority over interstate oil pipelines as
stated in the Interstate Commerce Act,
49 U.S.C. 6501, et. al. As part of the
information necessary for the
subsequent investigation and review of
an oil pipeline company’s proposed
depreciation rates, the pipeline
companies are required to provide
service life data as part of their data
submissions if the proposed
depreciation rates are based on the
remaining physical life calculations.
This service life data is submitted on
FERC Form No. 73, ‘‘Oil Pipeline
Service Life Data.’’ The information
collected under the requirements of
FERC Form No. 73 is used by the
Commission to implement the statutory
provisions of Sections 306 and 402 of
the Department of Energy Organization
Act, 42 U.S.C. 7155 and 7172, and
Executive Order No. 12009, 42 FR 46277
(September 13, 1977).1
The submitted data are used by the
Commission to assist in the selection of
appropriate service lives and book
depreciation rates. Book depreciation
rates are used by oil pipeline companies
to compute the depreciation portion of
their operating expense which is a
component of their cost of service
which in turn is used to determine the
transportation rate to assess customers.
FERC staff’s recommended book
depreciation rates become legally
binding when issued by Commission
order. These rates remain in effect until
a subsequent review is requested and
the outcome indicates that a
modification is justified. The
Commission implements these filings in
18 CFR parts 347 and 357.
Type of Respondents: Oil pipeline
companies.
Estimate of Annual Burden: 2 The
Commission estimates the total Public
Reporting Burden for this information
collection as:
1 For FERC Form No. 73 filing instructions and
materials, please see https://www.ferc.gov/docsfiling/forms.asp#form73.
2 The Commission defines burden as the total
time, effort, or financial resources expended by
persons to generate, maintain, retain, or disclose or
provide information to or for a Federal agency. For
further explanation of what is included in the
information collection burden, reference 5 Code of
Federal Regulations 1320.3.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
E:\FR\FM\10APN1.SGM
10APN1
Agencies
[Federal Register Volume 79, Number 69 (Thursday, April 10, 2014)]
[Notices]
[Pages 19888-19891]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-08038]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. IC14-10-000]
Commission Information Collection Activities, (FERC-725E, FERC-
583, FERC-512, and FERC-588); Consolidated Comment Request; Extension
AGENCY: Federal Energy Regulatory Commission, DOE.
ACTION: Notice of information collections and request for comments.
-----------------------------------------------------------------------
SUMMARY: In compliance with the requirements of the Paperwork Reduction
Act of 1995, 44 USC 3506(c)(2)(A), the Federal Energy Regulatory
Commission (Commission or FERC) is soliciting public comment on the
requirements and burden \1\ of the information collections described
below. Please note that this is the first time FERC has issued a
consolidated notice involving otherwise unrelated information
collections.
---------------------------------------------------------------------------
\1\ The Commission defines burden as the total time, effort, or
financial resources expended by persons to generate, maintain,
retain, or disclose or provide information to or for a Federal
agency. For further explanation of what is included in the
information collection burden, reference 5 Code of Federal
Regulations 1320.3.
---------------------------------------------------------------------------
DATES: Comments on the collections of information are due June 9, 2014.
ADDRESSES: You may submit comments (identified by Docket No. IC14-10-
000) by either of the following methods:
eFiling at Commission's Web site: https://www.ferc.gov/docs-filing/efiling.asp
Mail/Hand Delivery/Courier: Federal Energy Regulatory
Commission, Secretary of the Commission, 888 First Street NE.,
Washington, DC 20426.
Please reference the specific collection number and/or title in
your comments.
Instructions: All submissions must be formatted and filed in
accordance with submission guidelines at: https://www.ferc.gov/help/submission-guide.asp. For user assistance contact FERC Online Support
by email at ferconlinesupport@ferc.gov, or by phone at: (866) 208-3676
(toll-free), or (202) 502-8659 for TTY.
Docket: Users interested in receiving automatic notification of
activity in this docket or in viewing/downloading comments and
issuances in this docket may do so at https://www.ferc.gov/docs-filing/docs-filing.asp.
FOR FURTHER INFORMATION CONTACT: Ellen Brown may be reached by email at
DataClearance@FERC.gov, telephone at (202) 502-8663, and fax at (202)
273-0873.
SUPPLEMENTARY INFORMATION:
Type of Request: Three-year extension of the information collection
requirements for all collections described below with no changes to the
current reporting requirements. Please note that each collection is
distinct from the others contained within this notice.
Comments: Comments are invited on: (1) Whether the collections of
information are necessary for the proper performance of the functions
of the Commission, including whether the information will have
practical utility; (2) the accuracy of the agency's estimates of the
burden and cost of the collections of information, including the
validity of the methodology and assumptions used; (3) ways to enhance
the quality, utility and clarity of the information collections; and
(4) ways to minimize the burden of the collections of information on
those who are to respond, including the use of automated collection
techniques or other forms of information technology.
FERC-725E, Mandatory Reliability Standards for the Western Electric
Coordinating Council
OMB Control No.: 1902-0246.
Abstract: The information collected by the FERC-725E (OMB Control
No. 1902-0246) is required to implement the statutory provisions of
section 215 of the Federal Power Act (FPA) (16 U.S.C. 824o). Section
215 of the FPA buttresses the Commission's efforts to strengthen the
reliability of the interstate grid through the grant of new authority
by providing for a system of mandatory Reliability Standards developed
by the Electric Reliability Organization. Reliability Standards that
the ERO proposes to the Commission may include Reliability Standards
that are proposed to the ERO by a Regional Entity.\2\ A Regional Entity
is an entity that has been approved by the Commission to enforce
Reliability Standards under delegated authority from the ERO.\3\ On
June 8, 2008 in an adjudicatory order, the Commission approved eight
regional Reliability Standards submitted by the ERO that were proposed
by the Western Electricity Coordinating Council (WECC).\4\
---------------------------------------------------------------------------
\2\ 16 U.S.C. 824o(e)(4).
\3\ 16 U.S.C. 824o(a)(7) and (e)(4).
\4\ 72FR33462, June 18, 2007.
---------------------------------------------------------------------------
WECC is responsible for coordinating and promoting electric system
reliability. In addition to promoting a reliable electric power system
in the Western Interconnection, WECC
[[Page 19889]]
supports efficient competitive power markets, ensures open and non-
discriminatory transmission access among members, and provides a forum
for resolving transmission access disputes plus the coordination of
operating and planning activities of its members.
There are eight Reliability Standards currently applicable in the
WECC region. These standards generally require entities to document
compliance with substantive requirements, retain documentation, and
submit reports to WECC.
BAL-002-WECC-2 requires balancing authorities and reserve
sharing groups to document compliance with the contingency reserve
requirements described in the standard.
BAL-004-WECC-02 requires balancing authorities to document
that time error corrections and primary inadvertent interchange payback
were conducted according the requirements in the standard.
FAC-501-WECC-1 requires transmission owners with certain
transmission paths to have a transmission maintenance and inspection
plan and to document maintenance and inspection activities according to
the plan.
IRO-006-WECC-1 requires balancing authorities and
reliability coordinators document actions taken to mitigate unscheduled
flow.
PRC-004-WECC-1 requires transmission owners, generator
owners and transmission operators to document their analysis and/or
mitigation due to certain misoperations on major transfer paths. This
standard requires that documentation be kept for six years.
TOP-007-WECC-1 requires transmission operators to document
that when actual flows on major transfer paths exceed system operating
limits their schedules and actual flows are not exceeded for longer
than a specified time.
VAR-002-WECC-1 requires generator operators and
transmission operators to provide quarterly reports to the compliance
monitor and have evidence related to their synchronous generators,
synchronous condensers, and automatic voltage regulators.
VAR-501-WECC-1 requires generator operators to provide
quarterly reports to the compliance monitor and have evidence regarding
operation of their power system stabilizers.
The information generated by these standards generally serves to
ensure entities are complying with applicable Reliability Standards.
Type of Respondents: Balancing authorities, reserve sharing groups,
transmission owners, reliability coordinators, transmission operators,
generator operators.
Estimate of Annual Burden: The Commission estimates the annual
public reporting burden for the information collection as:
FERC-725E, Mandatory Reliability Standards for the Western Electric Coordinating Council
----------------------------------------------------------------------------------------------------------------
Total annual
Number of Annual number Average burden/ burden hours
respondents \5\ of responses cost per (Total annual
per respondent response cost)
FERC data collection (1) (2) (4) (1)*(2)*(3)
----------------------------------------------------------------------------------------------------------------
FERC-725E
Reporting:
Balancing Authorities................... 34 1 21 714
Generator Operators..................... 228 1 10 2,280
Transmission Operators applicable to 86 4 10 3,440
standard VAR-002 \6\...................
Transmission Operators that operate 9 3 40 1,080
qualified transfer paths \7\...........
Transmission Owners that operate 5 3 40 600
qualified transfer paths \8\...........
Reliability Coordinators................ 1 1 1 1
Reserve Sharing Group................... 3 1 1 3
-------------------------------------------------------------------
Total............................... ............... ............... ............... 8,118
Record-keeping: \9\
Balancing Authorities................... ............... ............... ............... 71
Balancing Authorities (IRO-006) \10\.... ............... ............... ............... 34
Generator Operators..................... ............... ............... ............... 228
Transmission Operator (VAR-002)......... ............... ............... ............... 344
Transmission Operator................... ............... ............... ............... 108
Transmission Owner...................... ............... ............... ............... 60
Reliability Coordinator \11\............ ............... ............... ............... 34
-------------------------------------------------------------------
Total............................... ............... ............... ............... 879
----------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------
\5\ Number of respondents derived from the NERC Compliance
Registry as of February 25, 2014.
\6\ Based on estimates in Order 751, Docket No. RM09-9-000
\7\ Based on burden estimates taken from the Order in Docket No.
RR07-11-000 P. 130.
\8\ Id.
\9\ Based on 10% total annual burden hours per response.
\10\ Based on record keeping hours for Balancing Authorities in
Order 746 in Docket No. RM09-19-000 implementing IRO-006-WECC-1.
\11\ Based on record keeping hours in Order 746 in Docket No.
RM09-19-000.
---------------------------------------------------------------------------
FERC-583, Annual Kilowatt Generating Report (Annual Charges)
OMB Control No.: 1902-0136.
Abstract: The FERC-583 is used by the Commission to implement the
statutory provisions of section 10(e) of the Federal Power Act (FPA)
(16 U.S.C. 803(e)), which requires the Commission to collect annual
charges from hydropower licensees for, among other things, the cost of
administering Part I of the FPA and for the use of United States dams.
In addition, section 3401 of the Omnibus Budget Reconciliation Act of
1986 (OBRA) authorizes the Commission to ``assess and collect fees and
annual charges in any fiscal year in amounts equal to all of the costs
incurred by the Commission in that fiscal year.'' The information is
collected annually and used to determine the amounts of the annual
charges to be assessed licensees for
[[Page 19890]]
reimbursable government administrative costs and for the use of
government dams. The Commission implements these filing requirements in
the Code of Federal Regulations (CFR) under 18 CFR part 11.
Type of Respondent: FERC-regulated private and public hydropower
licensees.
Estimate of Annual Burden: The Commission estimates the annual
public reporting burden for the information collection as:
FERC-583, Annual Kilowatt Generating Report (Annual Charges)
----------------------------------------------------------------------------------------------------------------
Annual number Average burden Total annual
Number of of responses per Total number of and cost per burden hours and Cost per
respondents \12\ respondent responses response \13\ total annual cost respondent ($)
(1) (2) (1)*(2)=(3) (4) (3)*(4)=(5) (5)/(1)
----------------------------------------------------------------------------------------------------------------
517 1 517 2 1,034 $141
$141 $72,897
----------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------
\12\ Based on data from Fiscal Year 2013, there were 517
projects, owned by 241 FERC-regulated private and public licensees.
Many of the licensees owned multiple projects.
\13\ The estimates for cost per response are derived using the
following formula: Average Burden Hours per Response * $70.50 per
hour.
---------------------------------------------------------------------------
FERC-512, Application for Preliminary Permit
OMB Control No.: 1902-0073.
Abstract: The Commission uses the information collected under the
requirements of FERC-512 to implement the statutory provisions of
sections 4(f), 5 and 7 of the Federal Power Act (FPA).\14\ The purpose
of obtaining a preliminary permit is to maintain priority of the
application for a license for a hydropower facility while the applicant
conducts surveys to prepare maps, plans, specifications and estimates;
conducts engineering, economic and environmental feasibility studies;
and making financial arrangements. The conditions under which the
priority will be maintained are set forth in each permit. During the
term of the permit, no other application for a preliminary permit or
application for a license submitted by another party can be accepted.
The term of the permit is three years. The information collected under
the designation FERC-512 is in the form of a written application for a
preliminary permit which is used by Commission staff to determine an
applicant's qualifications to hold a preliminary permit, review the
proposed hydro development for feasibility and to issue a notice of the
application in order to solicit public and agency comments. The
Commission implements these mandatory filing requirements in the Code
of Federal Regulations (CFR) under 18 CFR 4.31-.33, 4.81-.83.
---------------------------------------------------------------------------
\14\ 16 U.S.C. 797, 798, & 800.
---------------------------------------------------------------------------
Type of Respondents: Hydropower facilities.
Estimate of Annual Burden: The Commission estimates the annual
public reporting burden for the information collection as:
---------------------------------------------------------------------------
\15\ The estimates for cost per response are derived using the
following formula: Average Burden Hours per Response * $70.50 per
hour.
FERC-512--Application for Preliminary Permit
----------------------------------------------------------------------------------------------------------------
Total annual
Number of Annual number of Total number of Average burden/$ burden hours Cost per
respondents responses per responses per response (total annual respondent ($)
respondent \15\ cost)
(1) (2) (1)*(2)=(3) (4) (3)*(4)=(5) (5)/(1)
----------------------------------------------------------------------------------------------------------------
125 1 125 37 4,625 $2,608.50
$2,608.50 $326,062.50
----------------------------------------------------------------------------------------------------------------
FERC-588, Emergency Natural Gas Transportation, Sale, and Exchange
Transportation
OMB Control No.: 1902-0144.
Abstract: The Commission uses the information collected under the
requirements of FERC-588 to implement the statutory provisions of
sections 7(c) of the Natural Gas Act (NGA) (Pub. L. 75-688) (15 U.S.C.
717-717w) and provisions of the Natural Gas Policy Act of 1978 (NGPA),
15 U.S.C. 3301-3432. Under the NGA, a natural gas company must obtain
Commission approval to engage in the transportation, sale or exchange
of natural gas in interstate commerce. However, section 7(c) exempts
from certificate requirements ``temporary acts or operations for which
the issuance of a certificate will not be required in the public
interest.'' The NGPA also provides for non-certificated interstate
transactions involving intrastate pipelines and local distribution
companies.
A temporary operation, or emergency, is defined as any situation in
which an actual or expected shortage of gas supply would require an
interstate pipeline company, intrastate pipeline, local distribution
company, or Hinshaw pipeline to curtail deliveries of gas or provide
less than the projected level of service to the customer. The natural
gas companies which provide the temporary assistance to the companies
which are having the ``emergency'' must file the necessary information
described in Part 284, Subpart I of the Commission's Regulations with
the Commission so that it may determine if their assisting transaction/
operation qualifies for exemption. The assisting company may or may not
be under the Commission's jurisdiction and if their assisting actions
qualify for the exemption, they will not become subject to the
Commission's jurisdiction for such actions.
A report within forty-eight hours of the commencement of the
transportation, sale or exchange, a request to extend the sixty-day
term of
[[Page 19891]]
the emergency transportation, if needed, and a termination report are
required. The data required to be filed for the forty-eight hour report
is specified by 18 CFR 284.270.
Type of Respondents: Natural Gas Pipelines.
Estimate of Annual Burden: The Commission estimates the annual
public reporting burden for the information collection as:
---------------------------------------------------------------------------
\16\ The estimates for cost per response are derived using the
following formula: Average Burden Hours per Response * $70.50 per
hour.
FERC-588--Emergency Natural Gas Transportation, Sale, and Exchange Transportation
----------------------------------------------------------------------------------------------------------------
Total annual
Number of Annual number of Total number of Average burden/$ burden hours Cost per
respondents responses per responses per response \16\ (total annual respondent ($)
respondent cost)
(1) (2) (1)*(2)=(3) (4) (3)*(4)=(5) (5)/(1)
----------------------------------------------------------------------------------------------------------------
8 1 8 10 80 $705
$705 $5,640
----------------------------------------------------------------------------------------------------------------
Dated: April 2, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-08038 Filed 4-9-14; 8:45 am]