Combined Notice of Filings #1, 18900-18901 [2014-07538]
Download as PDF
18900
Federal Register / Vol. 79, No. 65 / Friday, April 4, 2014 / Notices
The proposed Montgomery Locks and
Dam Hydroelectric Project would be
located at RM 31.7 and consist of the
following new facilities: (1) A 340-footlong, 205-foot-wide intake channel
containing a 150-foot-long, 90-foot-high,
205-foot-wide intake structure with 5inch bar spacing trashracks; (2) a 315foot-long, 105-foot-high, 205-foot-wide
reinforced concrete powerhouse on the
north bank of the river; (3) three turbinegenerator units with a combined
capacity of 42 MW; (4) a 280-foot-long,
210-foot-wide tailrace; (5) a 50-foot-long
by 60-foot-wide substation; (6) a 392foot-long, 69-kV, overhead transmission
line to connect the project substation to
an existing distribution line; and (7)
appurtenant facilities. The average
annual generation would be 194,370
MWh.
Free Flow Power proposes to operate
all three projects in a ‘‘run-of-river’’
mode using flows made available by the
Corps. The proposed projects would not
change existing flow releases or water
surface elevations upstream or
downstream of the proposed projects.
o. Location of the Applications: A
copy of each application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll-free at 1–866–208–3676,
or for TTY, (202) 502–8659. Copies are
also available for inspection and
reproduction at the address in item h
above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate.
mstockstill on DSK4VPTVN1PROD with NOTICES
Milestone
Issue Notice of Acceptance
Issue Scoping Document 1
for Comments.
Hold Scoping Meeting .......
Comments Due on
Scoping Document 1.
Issue Scoping Document 2
Issue Notice of Ready for
Environmental Analysis.
Commission Issues EA .....
VerDate Mar<15>2010
Date
April 2014.
May 2014.
June 2014.
July 2014.
August 2014.
August 2014.
February 2015.
17:37 Apr 03, 2014
Jkt 232001
Dated: March 27, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–07499 Filed 4–3–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2847–001;
ER10–2818–001; ER10–2806–001; ER10–
1948–003.
Applicants: TransAlta Centralia
Generation LLC, TransAlta Energy
Marketing Corporation, TransAlta
Energy Marketing (U.S.) Inc., FPL
Energy Wyoming, LLC.
Description: Supplement to December
31, 2013 Triennial Market Power
Analysis in Northwest Region and
Notice of Change in Status of the
Transalta MBR Entities.
Filed Date: 3/27/14.
Accession Number: 20140327–5192.
Comments Due: 5 p.m. ET 4/17/14.
Docket Numbers: ER14–1001–001.
Applicants: Southern California
Edison Company.
Description: Revised LGIA and Distrib
Service Agmt with Coram California
Development, L.P. to be effective 12/15/
2013.
Filed Date: 3/28/14.
Accession Number: 20140328–5005.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14–1343–001.
Applicants: Bargain Energy, LLC.
Description: Bargain Energy MBR
Supplement—Clone to be effective 4/1/
2014.
Filed Date: 3/28/14.
Accession Number: 20140328–5000.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER13–1487–002.
Applicants: Quantum Auburndale
Power, LP.
Description: Quantum Auburndale
Power, LP Revised Electric Tariff Filing
to be effective 3/29/2014.
Filed Date: 3/28/14.
Accession Number: 20140328–5071.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER13–1487–003;
ER13–1489–002; ER13–1488–001.
Applicants: Quantum Auburndale
Power, LP, Quantum Lake Power, LP,
Quantum Pasco Power, LP.
Description: Notification of NonMaterial Change in Status of the
Quantum Entities.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
Filed Date: 3/26/14.
Accession Number: 20140326–5183.
Comments Due: 5 p.m. ET 4/16/14.
Docket Numbers: ER13–1489–003.
Applicants: Quantum Lake Power, LP.
Description: Notification of NonMaterial Change in Status of Quantum
Lake Power, LP.
Filed Date: 3/26/14.
Accession Number: 20140326–5184.
Comments Due: 5 p.m. ET 4/16/14.
Docket Numbers: ER14–1603–000.
Applicants: CCES LLC.
Description: CCES Notice of
Cancellation—Clone to be effective 3/
28/2014.
Filed Date: 3/27/14.
Accession Number: 20140327–5174.
Comments Due: 5 p.m. ET 4/17/14.
Docket Numbers: ER14–1604–000.
Applicants: Southern California
Edison Company.
Description: 2014 TACBAA Update to
be effective 6/1/2014.
Filed Date: 3/28/14.
Accession Number: 20140328–5002.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14–1605–000.
Applicants: Nevada Power Company.
Description: Notice of Termination of
Dynamic Scheduling Agreement of
Nevada Power Company.
Filed Date: 3/27/14.
Accession Number: 20140327–5190.
Comments Due: 5 p.m. ET 4/17/14.
Docket Numbers: ER14–1606–000.
Applicants: Cosima Energy, LLC.
Description: Cosima Energy MBR
Tariff Filing to be effective 5/1/2014.
Filed Date: 3/28/14.
Accession Number: 20140328–5098.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14–1607–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Queue W1–072A_AT5;
Original SA No. 3796 & Cancellation of
SA No. 3380 to be effective 2/26/2014.
Filed Date: 3/28/14.
Accession Number: 20140328–5145.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14–1608–000.
Applicants: Public Service Electric
and Gas Company, PJM Interconnection,
L.L.C.
Description: PSE&G submits revisions
to OATTAtt H–10A re BLC Project to be
effective 5/28/2014.
Filed Date: 3/28/14.
Accession Number: 20140328–5168.
Comments Due: 5 p.m. ET 4/18/14.
Take notice that the Commission
received the following public utility
holding company filings:
Docket Numbers: PH14–8–000.
Applicants: Sycamore Gas, Inc.
Description: Sycamore Gas, Inc.
submits FERC 65–A Exemption
Notification.
E:\FR\FM\04APN1.SGM
04APN1
Federal Register / Vol. 79, No. 65 / Friday, April 4, 2014 / Notices
Filed Date: 3/27/14.
Accession Number: 20140327–5198.
Comments Due: 5 p.m. ET 4/17/14.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 28, 2014.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2014–07538 Filed 4–3–14; 8:45 am]
BILLING CODE 6717–01–P
Dated: March 28, 2014.
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
[FR Doc. 2014–07496 Filed 4–3–14; 8:45 am]
Federal Energy Regulatory
Commission
BILLING CODE 6717–01–P
[Docket No. EL13–62–000]
DEPARTMENT OF ENERGY
mstockstill on DSK4VPTVN1PROD with NOTICES
Independent Power Producers of New
York, Inc. v. New York Independent
System Operator, Inc.; Notice of
Amendment to Complaint
Take notice that on March 25, 2014,
Independent Power Producers of New
York, Inc. (IPPNY or Complainant) filed
an amendment to its May 10, 2013,
Complaint against New York
Independent System Operator, Inc.
(NYISO or Respondent).
IPPNY certifies that copies of the
complaint were served on the contacts
of NYISO as listed on the Commission’s
list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
VerDate Mar<15>2010
17:37 Apr 03, 2014
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on April 14, 2014.
Jkt 232001
Federal Energy Regulatory
Commission
[Docket No. CP14–87–000]
Southeast Supply Header, LLC; Notice
of Intent To Prepare an Environmental
Assessment for the Proposed SESH
Expansion Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the SESH Expansion Project involving
construction and operation of facilities
by Southeast Supply Header, LLC
(SESH) in Copiah County, Mississippi.
The Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues they need to
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
18901
evaluate in the EA. Please note that the
scoping period will close on April 28,
2014.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
SESH provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically-asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
Summary of the Proposed Project
SESH requests approval to construct
and operate a new compressor station,
associated connecting piping, and
appurtenant facilities in Copiah County,
Mississippi. The SESH Expansion
Project would create about 25,000
dekatherms per day (Dth/d) of new
capacity on the SESH mainline as well
as change the mainline design to reflect
a total 45,000 Dth/d increase in
capacity.
The SESH Expansion Project would
consist of the following facilities:
• New compressor facilities (the
‘‘Dentville Compressor Station’’) at the
SESH/Texas Eastern Transmission, LP
Interconnect, which include a single
8,000 horsepower natural gas-fired
reciprocating engine compressor
package;
• approximately 4,000 feet of new 20inch-diameter connecting piping and
related appurtenances from the
proposed Dentville Compressor Station
site to an existing metering and
regulating (M&R) station on the SESH
mainline at milepost 73.05 and southsouthwest of the Dentville Compressor
Station site; and
E:\FR\FM\04APN1.SGM
04APN1
Agencies
[Federal Register Volume 79, Number 65 (Friday, April 4, 2014)]
[Notices]
[Pages 18900-18901]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-07538]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings 1
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER10-2847-001; ER10-2818-001; ER10-2806-001; ER10-
1948-003.
Applicants: TransAlta Centralia Generation LLC, TransAlta Energy
Marketing Corporation, TransAlta Energy Marketing (U.S.) Inc., FPL
Energy Wyoming, LLC.
Description: Supplement to December 31, 2013 Triennial Market Power
Analysis in Northwest Region and Notice of Change in Status of the
Transalta MBR Entities.
Filed Date: 3/27/14.
Accession Number: 20140327-5192.
Comments Due: 5 p.m. ET 4/17/14.
Docket Numbers: ER14-1001-001.
Applicants: Southern California Edison Company.
Description: Revised LGIA and Distrib Service Agmt with Coram
California Development, L.P. to be effective 12/15/2013.
Filed Date: 3/28/14.
Accession Number: 20140328-5005.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14-1343-001.
Applicants: Bargain Energy, LLC.
Description: Bargain Energy MBR Supplement--Clone to be effective
4/1/2014.
Filed Date: 3/28/14.
Accession Number: 20140328-5000.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER13-1487-002.
Applicants: Quantum Auburndale Power, LP.
Description: Quantum Auburndale Power, LP Revised Electric Tariff
Filing to be effective 3/29/2014.
Filed Date: 3/28/14.
Accession Number: 20140328-5071.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER13-1487-003; ER13-1489-002; ER13-1488-001.
Applicants: Quantum Auburndale Power, LP, Quantum Lake Power, LP,
Quantum Pasco Power, LP.
Description: Notification of Non-Material Change in Status of the
Quantum Entities.
Filed Date: 3/26/14.
Accession Number: 20140326-5183.
Comments Due: 5 p.m. ET 4/16/14.
Docket Numbers: ER13-1489-003.
Applicants: Quantum Lake Power, LP.
Description: Notification of Non-Material Change in Status of
Quantum Lake Power, LP.
Filed Date: 3/26/14.
Accession Number: 20140326-5184.
Comments Due: 5 p.m. ET 4/16/14.
Docket Numbers: ER14-1603-000.
Applicants: CCES LLC.
Description: CCES Notice of Cancellation--Clone to be effective 3/
28/2014.
Filed Date: 3/27/14.
Accession Number: 20140327-5174.
Comments Due: 5 p.m. ET 4/17/14.
Docket Numbers: ER14-1604-000.
Applicants: Southern California Edison Company.
Description: 2014 TACBAA Update to be effective 6/1/2014.
Filed Date: 3/28/14.
Accession Number: 20140328-5002.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14-1605-000.
Applicants: Nevada Power Company.
Description: Notice of Termination of Dynamic Scheduling Agreement
of Nevada Power Company.
Filed Date: 3/27/14.
Accession Number: 20140327-5190.
Comments Due: 5 p.m. ET 4/17/14.
Docket Numbers: ER14-1606-000.
Applicants: Cosima Energy, LLC.
Description: Cosima Energy MBR Tariff Filing to be effective 5/1/
2014.
Filed Date: 3/28/14.
Accession Number: 20140328-5098.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14-1607-000.
Applicants: PJM Interconnection, L.L.C.
Description: Queue W1-072A--AT5; Original SA No. 3796 &
Cancellation of SA No. 3380 to be effective 2/26/2014.
Filed Date: 3/28/14.
Accession Number: 20140328-5145.
Comments Due: 5 p.m. ET 4/18/14.
Docket Numbers: ER14-1608-000.
Applicants: Public Service Electric and Gas Company, PJM
Interconnection, L.L.C.
Description: PSE&G submits revisions to OATTAtt H-10A re BLC
Project to be effective 5/28/2014.
Filed Date: 3/28/14.
Accession Number: 20140328-5168.
Comments Due: 5 p.m. ET 4/18/14.
Take notice that the Commission received the following public
utility holding company filings:
Docket Numbers: PH14-8-000.
Applicants: Sycamore Gas, Inc.
Description: Sycamore Gas, Inc. submits FERC 65-A Exemption
Notification.
[[Page 18901]]
Filed Date: 3/27/14.
Accession Number: 20140327-5198.
Comments Due: 5 p.m. ET 4/17/14.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: March 28, 2014.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2014-07538 Filed 4-3-14; 8:45 am]
BILLING CODE 6717-01-P