National Fuel Gas Supply Corporation; Notice of Intent To Prepare an Environmental Assessment for the Proposed West Side Expansion and Modernization Project and Request for Comments on Environmental Issues, 16787-16789 [2014-06540]
Download as PDF
Federal Register / Vol. 79, No. 58 / Wednesday, March 26, 2014 / Notices
Docket Numbers: ER14–1530–000.
Applicants: Southwest Power Pool,
Inc.
Description: 2829 Midwest Energy,
Inc. & Westar Meter Agent Agreement to
be effective 3/1/2014.
Filed Date: 3/19/14.
Accession Number: 20140319–5069.
Comments Due: 5 p.m. ET 4/9/14.
Docket Numbers: ER14–1531–000.
Applicants: Southern California
Edison Company.
Description: SGIAs with Kingbird
Solar A, LLC and Kingbird Solar B, LLC
to be effective 3/11/2014.
Filed Date: 3/19/14.
Accession Number: 20140319–5079.
Comments Due: 5 p.m. ET 4/9/14.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 19, 2014.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2014–06688 Filed 3–25–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–70–000]
sroberts on DSK5SPTVN1PROD with NOTICES
National Fuel Gas Supply Corporation;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed West Side Expansion and
Modernization Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the West Side Expansion and
Modernization Project (Project)
involving construction and operation of
VerDate Mar<15>2010
17:43 Mar 25, 2014
Jkt 232001
facilities by National Fuel Gas Supply
Corporation (National Fuel) in
Washington, Allegheny, Beaver,
Venango, and Mercer Counties,
Pennsylvania. The Commission will use
this EA in its decision-making process
to determine whether the project is in
the public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on April 18,
2014. You may submit comments in
written form. Details on how to submit
written comments are in the Public
Participation section of this notice.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
National Fuel provided landowners
with a fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ This fact sheet addresses a
number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC Web
site (www.ferc.gov).
Summary of the Proposed Project
National Fuel proposes to construct a
new transmission line parallel to its
existing natural gas pipeline referred to
as Line N. The pipeline would replace
about 23 miles of the existing 20-inchdiameter Line N (referred to as Sections
1 and 2) which were built in 1947, with
new 24-inch pipeline located in
Washington, Allegheny and Beaver
Counties, PA. The Project also consists
of the installation of additional
compression at the Mercer Compressor
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
16787
Station (CS) (ongoing construction
under CP13–530) in Mercer County, PA
and miscellaneous piping modifications
at the Henderson CS in Venango
County, PA. The Project would provide
about 175,000 dekatherms per day of
incremental capacity. According to
National Fuel, the project would
improve the integrity and reliability of
the existing Line N system.
The West Side Expansion and
Modernization Project would consist of
the following facilities:
• Installation of approximately 23miles of 24-inch diameter pipeline;
• construction of one additional 3,550
horsepower (HP) reciprocating
compressor unit at the National Fuel
existing Mercer CS; and
• installation of miscellaneous valve
and piping modifications at the National
Fuel existing Henderson CS.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 3.0 acres of land for
the aboveground facilities, 275.7 acres
for temporary construction of the
pipeline. Following construction,
National Fuel would maintain about
139.7 acres for permanent operation of
the project’s facilities. The remaining
acreage would be restored and revert to
former uses. National Fuel proposes to
construct the new 24-inch pipeline
parallel to the existing Line N pipeline.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
E:\FR\FM\26MRN1.SGM
26MRN1
16788
Federal Register / Vol. 79, No. 58 / Wednesday, March 26, 2014 / Notices
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
and
• public safety.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record at
www.ferc.gov using the link called
‘‘eLibrary’’. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section
beginning on page 4.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
sroberts on DSK5SPTVN1PROD with NOTICES
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
VerDate Mar<15>2010
17:43 Mar 25, 2014
Jkt 232001
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before April 18,
2014.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number (CP14–70–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You can file your comments
electronically using the eFiling feature
on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP14–70). Be sure you have
E:\FR\FM\26MRN1.SGM
26MRN1
Federal Register / Vol. 79, No. 58 / Wednesday, March 26, 2014 / Notices
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: March 19, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–06540 Filed 3–25–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2808–016]
sroberts on DSK5SPTVN1PROD with NOTICES
KEI (Maine) Power Management (III)
LLC; Notice of Intent To File License
Application, Filing of Pre-Application
Document, and Approving Use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: 2808–016.
c. Date Filed: January 31, 2014.
d. Submitted By: KEI (Maine) Power
Management (III) LLC.
e. Name of Project: Lower Barker
Hydroelectric Project.
f. Location: On the Little
Androscoggin River, in Androscoggin
County, Maine. No federal lands are
occupied by the project works or located
within the project boundary.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Lewis
Loon, KEI (Maine) Power Management
(III) LLC, 37 Alfred Plourde Parkway
Suite 2, Lewiston, ME 04240.
i. FERC Contact: Ryan Hansen at (202)
502–8074; or email at ryan.hansen@
ferc.gov.
j. KEI (Maine) Power Management (III)
LLC (KEI Maine) filed its request to use
VerDate Mar<15>2010
17:43 Mar 25, 2014
Jkt 232001
the Traditional Licensing Process on
January 31, 2014. KEI Maine provided
public notice of its request on February
4 and February 11, 2014. In a letter
dated March 19, 2014, the Director of
the Division of Hydropower Licensing
approved KEI Maine’s request to use the
Traditional Licensing Process.
k. With this notice, we are designating
KEI Maine as the Commission’s nonfederal representative for carrying out
informal consultation pursuant to
section 7 of the Endangered Species Act
and section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act; and consultation
pursuant to section 106 of the National
Historic Preservation Act.
l. KEI Maine filed a Pre-Application
Document (PAD; including a proposed
process plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of
the Commission’s regulations.
m. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). A copy is also available for
inspection and reproduction at the
address in paragraph h.
n. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 2808.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by February 1, 2017.
o. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: March 19, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–06541 Filed 3–25–14; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
16789
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD14–8–000]
Winter 2013–2014 Operations and
Market Performance in Regional
Transmission Organizations and
Independent System Operators;
Supplemental Notice of Technical
Conference
As announced in the Notice issued on
February 21, 2014,1 the Federal Energy
Regulatory Commission (Commission)
will hold a Commissioner-led technical
conference on Tuesday, April 1, 2014,
from 9 a.m. to approximately 5 p.m. to
discuss the impacts of recent cold
weather events on the Regional
Transmission Organizations/
Independent System Operators (RTOs/
ISOs), and discuss actions taken to
respond during those occurrences. The
conference will be held at the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
This conference is free of charge and
open to the public. Commission
members will participate in the
conference. The agenda and list of
participants for this conference are
attached.
Following the conference, the
Commission will take written public
comments until May 15, 2014.
If you have not already done so, those
who plan to attend the technical
conference are strongly encouraged to
complete the registration form located
at: https://www.ferc.gov/whats-new/
registration/04-01-14-form.asp. There is
no deadline to register to attend the
conference.
The technical conference will be
transcribed. Transcripts of the technical
conference will be immediately
available for a fee from Ace-Federal
Reporters, Inc. (202–347–3700 or 1–
800–336–6646). Additionally, there will
be a free webcast of the conference. The
webcast will allow persons to listen to
the technical conference but not
participate. Anyone with Internet access
who wants to listen to the conference
can do so by navigating to the Calendar
of Events at www.ferc.gov and locating
the technical conference in the
Calendar. The technical conference will
contain a link to its webcast. The
Capitol Connection provides technical
support for the webcast and offers the
1 Winter 2013–2014 Operations and Market
Performance in Regional Transmission
Organizations and Independent System Operators;
Supplemental Notice of Technical Conference
(https://www.ferc.gov/CalendarFiles/
20140221164557-AD14-8-000TC.pdf).
E:\FR\FM\26MRN1.SGM
26MRN1
Agencies
[Federal Register Volume 79, Number 58 (Wednesday, March 26, 2014)]
[Notices]
[Pages 16787-16789]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-06540]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-70-000]
National Fuel Gas Supply Corporation; Notice of Intent To Prepare
an Environmental Assessment for the Proposed West Side Expansion and
Modernization Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the West Side Expansion and
Modernization Project (Project) involving construction and operation of
facilities by National Fuel Gas Supply Corporation (National Fuel) in
Washington, Allegheny, Beaver, Venango, and Mercer Counties,
Pennsylvania. The Commission will use this EA in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on April 18, 2014. You may submit
comments in written form. Details on how to submit written comments are
in the Public Participation section of this notice.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
National Fuel provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do
I Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
National Fuel proposes to construct a new transmission line
parallel to its existing natural gas pipeline referred to as Line N.
The pipeline would replace about 23 miles of the existing 20-inch-
diameter Line N (referred to as Sections 1 and 2) which were built in
1947, with new 24-inch pipeline located in Washington, Allegheny and
Beaver Counties, PA. The Project also consists of the installation of
additional compression at the Mercer Compressor Station (CS) (ongoing
construction under CP13-530) in Mercer County, PA and miscellaneous
piping modifications at the Henderson CS in Venango County, PA. The
Project would provide about 175,000 dekatherms per day of incremental
capacity. According to National Fuel, the project would improve the
integrity and reliability of the existing Line N system.
The West Side Expansion and Modernization Project would consist of
the following facilities:
Installation of approximately 23-miles of 24-inch diameter
pipeline;
construction of one additional 3,550 horsepower (HP)
reciprocating compressor unit at the National Fuel existing Mercer CS;
and
installation of miscellaneous valve and piping
modifications at the National Fuel existing Henderson CS.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 3.0
acres of land for the aboveground facilities, 275.7 acres for temporary
construction of the pipeline. Following construction, National Fuel
would maintain about 139.7 acres for permanent operation of the
project's facilities. The remaining acreage would be restored and
revert to former uses. National Fuel proposes to construct the new 24-
inch pipeline parallel to the existing Line N pipeline.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all
[[Page 16788]]
filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species; and
public safety.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record at www.ferc.gov using the link
called ``eLibrary''. Depending on the comments received during the
scoping process, we may also publish and distribute the EA to the
public for an allotted comment period. We will consider all comments on
the EA before making our recommendations to the Commission. To ensure
we have the opportunity to consider and address your comments, please
carefully follow the instructions in the Public Participation section
beginning on page 4.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before April
18, 2014.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP14-70-000) with your submission.
The Commission encourages electronic filing of comments and has expert
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP14-
70). Be sure you have
[[Page 16789]]
selected an appropriate date range. For assistance, please contact FERC
Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-
3676, or for TTY, contact (202) 502-8659. The eLibrary link also
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: March 19, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-06540 Filed 3-25-14; 8:45 am]
BILLING CODE 6717-01-P