Consolidated Edison Company of New York, Inc.; Notice of Filing, 15992-15993 [2014-06347]
Download as PDF
15992
Federal Register / Vol. 79, No. 56 / Monday, March 24, 2014 / Notices
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
WREIER-AVILES on DSK5TPTVN1PROD with NOTICES
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before April 14,
2014.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number (CP14–83–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Mar<15>2010
14:29 Mar 21, 2014
Jkt 232001
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You can file your comments
electronically using the eFiling feature
on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
federal, state, and local government
representatives and agencies; elected
officials; environmental and public
interest groups; Native American Tribes;
other interested parties; and local
libraries and newspapers. This list also
includes all affected landowners (as
defined in the Commission’s
regulations) who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within certain
distances of aboveground facilities, and
anyone who submits comments on the
project. We will update the
environmental mailing list as the
analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
PO 00000
Frm 00060
Fmt 4703
Sfmt 4703
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP14–83–000). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: March 14, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–06313 Filed 3–21–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. TX14–1–000]
Consolidated Edison Company of New
York, Inc.; Notice of Filing
Take notice that on March 18, 2014,
pursuant to sections 202(b) and 210 of
the Federal Power Act, 16 U.S.C. 824a
(b) and 824i and Rule 207 of the Federal
Energy Regulatory Commission’s Rules
of Practice and Procedure 18 CFR
385.207, Consolidated Edison Company
of New York, Inc. (Con Edison) filed an
E:\FR\FM\24MRN1.SGM
24MRN1
Federal Register / Vol. 79, No. 56 / Monday, March 24, 2014 / Notices
application for an order directing Cogen
Technologies Linden Venture, L.P. to
modify the physical connection that
currently exists between its
transmission facilities and those of Con
Edison.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible online at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on April 17, 2014.
Dated: March 18, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–06347 Filed 3–21–14; 8:45 am]
BILLING CODE 6717–01–P
WREIER-AVILES on DSK5TPTVN1PROD with NOTICES
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–99–000]
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization
Take notice that on March 6, 2014,
Columbia Gas Transmission, LLC,
VerDate Mar<15>2010
14:29 Mar 21, 2014
Jkt 232001
(Columbia), 5151 San Felipe, Suite
2500, Houston, Texas 77056, filed in
Docket No. CP14–99–000, a prior notice
request pursuant to sections 157.205,
157.208 and 157.216(b) of the
Commission’s Regulations under the
Natural Gas Act (NGA) as amended,
requesting authorization to abandon and
construct certain natural gas facilities.
Columbia proposes to replace 3.4 miles
of 8-inch diameter of the bare steel Line
1655, located north of the
interconnection with Line 1804 with
new 12-inch diameter coated steel
pipeline and appurtenant facilities all
located in Adams County, Pennsylvania
(Line 1655 Project). Columbia states that
the Line 1655 Project will provide an
additional 15,700 dekatherms per day of
firm transportation service to UGI
Utilities, Inc. Columbia asserts that
replacing Line 1655 will significantly
improve the reliability and safety of this
pipeline. Columbia estimates the total
cost of the Line 1655 Project to be
approximately $17.6 million, all as more
fully set forth in the application which
is on file with the Commission and open
to public inspection. The filing may also
be viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions concerning this
application may be directed to Frederic
J. George, Senior Counsel, Columbia Gas
Transmission, LLC, PO Box 1273,
Charleston, West Virginia 25325–1273,
by telephone at (304) 357–2359 or by
facsimile at (304) 357–3206.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA. Pursuant to section 157.9 of
the Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
PO 00000
Frm 00061
Fmt 4703
Sfmt 4703
15993
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
Dated: March 18, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–06345 Filed 3–21–14; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OAR–2010–0258; FRL 9908–56–
OEI]
Information Collection Request
Submitted to OMB for Review and
Approval; Comment Request;
Alternative Affirmative Defense
Requirements for Ultra-Low Sulfur
Diesel (Renewal)
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
E:\FR\FM\24MRN1.SGM
24MRN1
Agencies
[Federal Register Volume 79, Number 56 (Monday, March 24, 2014)]
[Notices]
[Pages 15992-15993]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-06347]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. TX14-1-000]
Consolidated Edison Company of New York, Inc.; Notice of Filing
Take notice that on March 18, 2014, pursuant to sections 202(b) and
210 of the Federal Power Act, 16 U.S.C. 824a (b) and 824i and Rule 207
of the Federal Energy Regulatory Commission's Rules of Practice and
Procedure 18 CFR 385.207, Consolidated Edison Company of New York, Inc.
(Con Edison) filed an
[[Page 15993]]
application for an order directing Cogen Technologies Linden Venture,
L.P. to modify the physical connection that currently exists between
its transmission facilities and those of Con Edison.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date. On or
before the comment date, it is not necessary to serve motions to
intervene or protests on persons other than the Applicant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible online at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on April 17, 2014.
Dated: March 18, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-06347 Filed 3-21-14; 8:45 am]
BILLING CODE 6717-01-P