Consolidated Water Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 15986-15987 [2014-06310]

Download as PDF 15986 Federal Register / Vol. 79, No. 56 / Monday, March 24, 2014 / Notices above. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: March 14, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–06314 Filed 3–21–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY WREIER-AVILES on DSK5TPTVN1PROD with NOTICES Federal Energy Regulatory Commission [Project No. 2256–071] Consolidated Water Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: VerDate Mar<15>2010 14:29 Mar 21, 2014 Jkt 232001 a. Application Type: Change in Land Rights. b. Project No: 2256–071. c. Date Filed: January 29, 2014. d. Applicant: Consolidated Water Power Company. e. Name of Project: Wisconsin Rapids Hydroelectric Project. f. Location: Wisconsin River in Wood County, Wisconsin. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Thomas J. Witt, 610 High Street, P.O. Box 8050, Wisconsin Rapids, WI 54495–8050, (715) 422–3927. i. FERC Contact: Jon Cofrancesco at (202) 502–8951, or email: jon.cofrancesco@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: April 14, 2014. All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P–2256–071) on any comments, motions, or recommendations filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: Consolidated Water Power Company (licensee) requests Commission approval to transfer certain interests in licensee-owned lands within the project boundary to New Page Wisconsin System, Inc. (New Page) to memorialize PO 00000 Frm 00054 Fmt 4703 Sfmt 4703 historic uses of the property by a paper company, currently owned by New Page, for continued use of the property by existing paper mill facilities and operations. The application would separate and more precisely delineate the licensee’s hydropower and utility assets from New Page’s paper mill assets. The proposed change in land rights does not involve any changes in project facilities, operations, or project boundaries. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field (P–2256) to access the document. You may also register online at https://www.ferc.gov/ docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person E:\FR\FM\24MRN1.SGM 24MRN1 Federal Register / Vol. 79, No. 56 / Monday, March 24, 2014 / Notices commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: March 14, 2014. Kimberly D. Bose, Secretary. [FR Doc. 2014–06310 Filed 3–21–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [ Docket Nos. CP14–96–000; PF13–16–000] WREIER-AVILES on DSK5TPTVN1PROD with NOTICES Algonquin Gas Transmission, LLC; Notice of Application Take notice that on February 28, 2014, Algonquin Gas Transmission, LLC (Algonquin), 5400 Westheimer Court, Houston, Texas 77056, filed in the above referenced docket an application pursuant to sections 7(b) and 7(c) of the Natural Gas Act (NGA) for the proposed Algonquin Incremental Market Project (AIM Project). Specifically, Algonquin requests authorization to: (i) construct, install, operate, and maintain approximately 37.6 miles of take-up and relay, loop, and lateral pipeline facilities, and appurtenances in New York, Connecticut, and Massachusetts; (ii) modify six existing compressor stations in New York, Connecticut, and Rhode Island, resulting in the addition of 81,620 horsepower (HP) of compression; (iii) modify 24 existing metering and regulating (M&R) stations and construct three new M&R stations; (iv) abandon certain existing facilities; and (v) approval of the pro forma tariff records to establish the incremental AIM Project firm transportation rate, an incremental fuel percentage applicable to service on the AIM Project, and the initial recourse rates for service on the West Roxbury Lateral (which is part of the proposed AIM Project, but has separate rate schedules). Algonquin states that the AIM Project will provide a total of 342,000 dekatherms per day of firm transportation service. Algonquin estimates the cost of the AIM Project to be approximately $971,551,683, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The VerDate Mar<15>2010 14:29 Mar 21, 2014 Jkt 232001 filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application may be directed to Berk Donaldson, Director, Rates and Certificates, Algonquin Gas Transmission, LLC, PO Box 1642, Houston, Texas 77251–1642, by telephone at (713) 627–4488 or by facsimile at (713) 627–5947. On June 28, 2013, the Commission staff granted Algonquin’s request to utilize the Pre-Filing Process and assigned Docket No. PF13–16–000 to staff activities involved in the AIM Project. Now, as of the filing of the February 28, 2014 application, the PreFiling Process for this project has ended. From this time forward, this proceeding will be conducted in Docket No. CP14– 96–000, as noted in the caption of this Notice. Pursuant to section 157.9 of the Commission’s rules (18 CFR 157.9), within 90 days of this Notice, the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and PO 00000 Frm 00055 Fmt 4703 Sfmt 4703 15987 Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit seven copies of filings made in the proceeding with the Commission and must mail a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 7 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: April 8, 2014. E:\FR\FM\24MRN1.SGM 24MRN1

Agencies

[Federal Register Volume 79, Number 56 (Monday, March 24, 2014)]
[Notices]
[Pages 15986-15987]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-06310]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2256-071]


Consolidated Water Power Company; Notice of Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Change in Land Rights.
    b. Project No: 2256-071.
    c. Date Filed: January 29, 2014.
    d. Applicant: Consolidated Water Power Company.
    e. Name of Project: Wisconsin Rapids Hydroelectric Project.
    f. Location: Wisconsin River in Wood County, Wisconsin.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Thomas J. Witt, 610 High Street, P.O. Box 
8050, Wisconsin Rapids, WI 54495-8050, (715) 422-3927.
    i. FERC Contact: Jon Cofrancesco at (202) 502-8951, or email: 
jon.cofrancesco@ferc.gov.
    j. Deadline for filing comments, motions to intervene, and 
protests: April 14, 2014.
    All documents may be filed electronically via the Internet. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and seven copies to: Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426. 
Please include the project number (P-2256-071) on any comments, 
motions, or recommendations filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency.
    k. Description of Request: Consolidated Water Power Company 
(licensee) requests Commission approval to transfer certain interests 
in licensee-owned lands within the project boundary to New Page 
Wisconsin System, Inc. (New Page) to memorialize historic uses of the 
property by a paper company, currently owned by New Page, for continued 
use of the property by existing paper mill facilities and operations. 
The application would separate and more precisely delineate the 
licensee's hydropower and utility assets from New Page's paper mill 
assets. The proposed change in land rights does not involve any changes 
in project facilities, operations, or project boundaries.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field (P-2256) to access the document. You 
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, call 1-866-
208-3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-
8659. A copy is also available for inspection and reproduction at the 
address in item (h) above. Agencies may obtain copies of the 
application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person

[[Page 15987]]

commenting, protesting or intervening; and (4) otherwise comply with 
the requirements of 18 CFR 385.2001 through 385.2005. All comments, 
motions to intervene, or protests must set forth their evidentiary 
basis. Any filing made by an intervenor must be accompanied by proof of 
service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 385.2010.

    Dated: March 14, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-06310 Filed 3-21-14; 8:45 am]
BILLING CODE 6717-01-P