Notice of Issuance of Final Air Permits for Statoil Gulf Services, LLC, Florida Power & Light-Port Everglades Next Generation Clean Energy Center, and Tampa Electric Company., 14506-14507 [2014-05737]
Download as PDF
14506
Federal Register / Vol. 79, No. 50 / Friday, March 14, 2014 / Notices
with 40 CFR 52.21 to issue a final PSD
permit to PPLLC for the PPEC.
Following completion of the remand
proceedings, pursuant to 40 CFR
124.19(l)(2), EPA Region 9 issued a final
permit decision to PPLLC for the PPEC
on February 28, 2014. All conditions of
the PPEC PSD permit, Permit No. SD
11–01, issued February 28, 2014,
become final and effective on April 7,
2014.
Dated: March 7, 2014.
Deborah Jordan,
Director, Air Division, Region IX.
[FR Doc. 2014–05740 Filed 3–13–14; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9013–9]
Environmental Impact Statements;
Notice Of Availability
sroberts on DSK5SPTVN1PROD with NOTICES
Responsible Agency: Office of Federal
Activities, General Information (202)
564–7146 or https://www.epa.gov/
compliance/nepa/.
Weekly receipt of Environmental Impact
Statements
Filed 03/03/2014 Through 03/07/2014
Pursuant to 40 CFR 1506.9.
Notice:
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
www.epa.gov/compliance/nepa/
eisdata.html.
EIS No. 20140062, Final EIS, NPS, CA,
Tuolumne Wild and Scenic River
Final Comprehensive Management
Plan, Review Period Ends: 04/14/
2014, Contact: Kathleen Morse 209–
379–1110.
EIS No. 20140063, Draft EIS, BLM, NM,
San Juan Basin Energy Connect
Project, Comment Period Ends: 04/28/
2014, Contact: Marcy Romero 505–
564–7600.
EIS No. 20140064, Draft Supplement,
USFS, MT, Beaverhead-Deerlodge
National Forest Land and Resource
Management Plan to Comply with a
District of Montana Court Order
(Temporary Roads), Comment Period
Ends: 06/12/2014, Contact: Jan Bowey
406–842–5432.
EIS No. 20140065, Draft EIS, USFS, OR,
Proposed Revised Land Management
Plans for the Malheur, Umatilla, and
Wallowa-Whitman National Forests,
Comment Period Ends: 06/16/2014,
Contact: Sabrina Stadler 541–523–
1264.
VerDate Mar<15>2010
19:18 Mar 13, 2014
Jkt 232001
EIS No. 20140066, Final EIS, BLM, NV,
Arturo Mine Project, Review Period
Ends:04/14/2014, Contact: John
Daniel 775–753–0277.
EIS No. 20140067, Final EIS, USFS, ND,
North Billings County Range
Allotment Management Plan
Revision, Review Period Ends: 04/28/
2014, Contact: Nickole Dahl 701–227–
7830.
EIS No. 20140068, Draft Supplement,
USFS, UT, Leasing and Underground
Mining of the Greens Hollow Federal
Coal Lease Tract UTU–102, Comment
Period Ends: 04/28/2014, Contact:
Marianne Orton 435–896–1090.
EIS No. 20140069, Draft EIS, USFS, MT,
Divide Travel Plan, Helena National
Forest, Comment Period Ends: 04/28/
2014, Contact: Heather DeGeest 406–
449–5201.
EIS No. 20140070, Final EIS, NASA, CA,
Proposed Demolition and
Environmental Cleanup Activities at
Santa Susana Field Laboratory,
Review Period Ends: 04/14/2014,
Contact: Allen Elliott 256–544–0662.
EIS No. 20140071, Draft EIS, NRCS, UT,
Green River Diversion Rehabilitation
Project, Comment Period Ends: 04/30/
2014, Contact: Bronson Smart 801–
524–4559.
EIS No. 20140072, Final EIS, NPS, NC,
Fort Raleigh National Historic Site,
General Management Plan, Review
Period Ends: 04/14/2014, Contact:
David Libman 404–507–5701.
ACTION:
Notice of final action.
This notice is to announce
that on October 28, 2013, the EPA
issued final Outer Continental Shelf
(OCS) air quality permit numbered
OCS–EPA–R4012 for Statoil Gulf
Services, LLC (Statoil); and on
November 25, 2013 and December 18,
2013, the EPA issued final Prevention of
Significant Deterioration (PSD) air
quality permits numbered PSD–EPA–
R4010 and PSD–EPA–R4014 for the
Florida Power & Light (FPL)—Port
Everglades Next Generation Clean
Energy Center (PEEC) and Tampa
Electric Company (TECO), respectively.
ADDRESSES: The final permits, the EPA’s
response to public comments for these
permits, and supporting information are
available at https://www.epa.gov/
region4/air/permits/index.htm. Copies
of the final permits and the EPA’s
response to comments are also available
for review at the EPA Regional Office
and upon request in writing. The EPA
requests that you contact the person
listed in the FOR FURTHER INFORMATION
CONTACT section to schedule your
inspection. The Regional Office’s
official hours of business are Monday
through Friday, 8:30 a.m. to 4:30 p.m.
excluding Federal holidays.
FOR FURTHER INFORMATION CONTACT:
Please contact Ms. Heather Ceron, Air
Permits Section Chief, Air Planning
Branch, Air, Pesticides and Toxics
Amended Notices
Management Division, Region 4, U.S.
Environmental Protection Agency, 61
EIS No. 20140054, Revised Draft EIS,
Forsyth Street SW., Atlanta, Georgia
USFS, CA, Harris Vegetation
Management Project, Comment Period 30303–8960. The telephone number is
(404) 562–9185. Ms. Ceron can also be
Ends: 04/21/2014, Contact: Emelia H.
reached via electronic mail at
Barnum 530–926–4511 ext. 1600.
ceron.heather@epa.gov.
Revision to FR Notice Published 03/
SUPPLEMENTARY INFORMATION: On August
07/2014; Correcting Comment Period
9, 2013, EPA Region 4 requested public
from 4/25/2014 to 4/21/2014.
comments on a preliminary
Dated: March 11, 2014.
determination to issue an OCS air
Dawn Roberts,
permit for Statoil. During the public
Management Analyst, Office of Federal
comment period, which ended on
Activities.
September 9, 2013, the EPA received no
[FR Doc. 2014–05674 Filed 3–13–14; 8:45 am]
comments.
BILLING CODE 6560–50–P
On May 31, 2013, EPA Region 4
requested public comments on a
preliminary determination to issue a
ENVIRONMENTAL PROTECTION
PSD air quality permit for the FPL PEEC
AGENCY
project. A total of 26 comments from 3
[EPA–R04–OAR–2013–0577; EPA–R04–
commenters, including 1 request for a
OAR–2013–0431; and EPA–R04–OAR–2013– public hearing, were received (via email
0648; FRL–9907–98–Region–4]
and letter) during the public comment
period, which closed on July 2, 2013.
Notice of Issuance of Final Air Permits
On September 24, 2013, EPA Region
for Statoil Gulf Services, LLC, Florida
4 requested public comments on a
Power & Light—Port Everglades Next
preliminary determination to issue a
Generation Clean Energy Center, and
PSD air quality permit for the TECO
Tampa Electric Company.
project. A total of 25 comments from
two commenters were received (via
AGENCY: Environmental Protection
email) during the public comment
Agency (EPA).
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
SUMMARY:
E:\FR\FM\14MRN1.SGM
14MRN1
Federal Register / Vol. 79, No. 50 / Friday, March 14, 2014 / Notices
sroberts on DSK5SPTVN1PROD with NOTICES
period, which closed on October 25,
2013.
The EPA reviewed each comment
received and prepared a Response to
Comments document for the two
projects. After consideration of the
expressed view of all interested persons,
the pertinent federal statutes and
regulations, the applications and
supplemental information submitted by
the applicants, and additional material
relevant to the applications and
contained in the Administrative
Records, the EPA made final
determinations in accordance with title
40 CFR part 52 and part 55 (for Statoil)
to issue final air permits.
Under 40 CFR 124.19(f)(2), notice of
any final Agency action regarding a PSD
permit must be published in the Federal
Register. Section 307(b)(1) of the CAA
provides for review of final Agency
action that is locally or regionally
applicable in the United States Court of
Appeals for the appropriate circuit.
Such a petition for review of final
Agency action must be filed within 60
days from the date of notice of such
action in the Federal Register. For
purposes of judicial review under the
CAA, final Agency action occurs when
a final PSD permit is issued or denied
by the EPA and Agency review
procedures are exhausted, per 40 CFR
124.19(f)(1).
Any person who filed comments on
the draft permits was provided the
opportunity to petition the
Environmental Appeals Board by the
end of November 26, 2013 for the Statoil
permit, by the end of December 26, 2013
for the PEEC permit, or by the end of
January 17, 2014 for the TECO permit.
No petitions were submitted for any of
these permits. Therefore, the Statoil
permit became effective on November
27, 2013. The PEEC permit became
effective on December 27, 2013. This
date was changed from December 25,
2013, as stated on the final permit, to
correct for the effective date coinciding
with a federal holiday. The TECO
permit became effective on January 18,
2014.
Dated: February 27, 2014.
Carol L. Kemker,
Acting Director, Air, Pesticides and Toxics,
Management Division, Region 4.
[FR Doc. 2014–05737 Filed 3–13–14; 8:45 am]
BILLING CODE 6560–50–P
VerDate Mar<15>2010
19:18 Mar 13, 2014
Jkt 232001
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9907–84–Region–10]
Final Modification of the National
Pollutant Discharge Elimination
System (NPDES) General Permit (GP)
for Small Suction Dredges in Idaho,
IDG370000
Environmental Protection
Agency (EPA).
ACTION: Final notice of modification of
a general permit.
AGENCY:
When the 2013 General
Permit (GP) was issued, the language of
the GP contained a discrepancy with the
total maximum daily load (TMDL) that
was issued for Mores Creek. The
Environmental Protection Agency (EPA)
proposed to modify the permit on
December 18, 2013, and provided a 45
day comment period. EPA prepared a
Response to Comments and modified
the GP so it now includes the tributaries
of Mores, Elk or Grimes creeks in the
loading allocations of the TMDL and a
list of these tributaries in Appendix F.
DATES: The modified GP will be
effective on April 14, 2014.
ADDRESSES: Copies of the modified
general permit, Statement of Basis and
Response to Comments are available
upon request. Requests may be made to
Tracy DeGering at (208) 378–5756 or to
Cindi Godsey at (907) 271–6561.
Requests may also be electronically
mailed to: degering.tracy@epa.gov or
godsey.cindi@epa.gov.
Written requests may be submitted to
EPA, Region 10, 1200 Sixth Avenue,
Suite 900, OWW–130, Seattle, WA
98101.
FOR FURTHER INFORMATION CONTACT: The
GP, Statement of Basis and Response to
Comments along with detailed maps
and other useful information may be
found on the Region 10 Web site at:
https://yosemite.epa.gov/r10/water.nsf/
npdes+permits/idsuction-gp.
SUPPLEMENTARY INFORMATION:
Executive Order 12866: The Office of
Management and Budget has exempted
this action from the review
requirements of Executive Order 12866
pursuant to Section 6 of that order.
Regulatory Flexibility Act: Under the
Regulatory Flexibility Act (RFA), 5
U.S.C. 601 et seq., a Federal agency
must prepare an initial regulatory
flexibility analysis ‘‘for any proposed
rule’’ for which the agency ‘‘is required
by section 553 of the Administrative
Procedure Act (APA), or any other law,
to publish general notice of proposed
rulemaking.’’ The RFA exempts from
this requirement any rule that the
SUMMARY:
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
14507
issuing agency certifies ‘‘will not, if
promulgated, have a significant
economic impact on a substantial
number of small entities.’’ EPA has
concluded that NPDES general permits
are permits, not rulemakings, under the
APA and thus not subject to APA
rulemaking requirements or the RFA.
Notwithstanding that general permits
are not subject to the RFA, EPA has
determined that these general permits,
as issued, will not have a significant
economic impact on a substantial
number of small entities.
Dated: March 5, 2014.
Daniel D. Opalski,
Director, Office of Water & Watersheds,
Region 10, U.S. Environmental Protection
Agency.
[FR Doc. 2014–05724 Filed 3–13–14; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9907–95–Region–4; CERCLA–04–
2013–3763]
LWD, Inc. Superfund Site; Calverty
City, Marshall County, Kentucky;
Notice of Settlement
Environmental Protection
Agency (EPA).
AGENCY:
ACTION:
Notice of Settlement.
Under 122(h) of the
Comprehensive Environmental
Response, Compensation and Liability
Act (CERCLA), the United States
Environmental Protection Agency (EPA)
has entered into a settlement with the
approximately fifty (50) parties
concerning the LWD, Inc. Superfund
Site located in Calvert City, Marshall
County, Kentucky. The settlement
addresses remaining costs from a fundlead Removal Action taken by the EPA
at the Site.
SUMMARY:
The Agency will consider public
comments on the settlement until April
14, 2014. The Agency will consider all
comments received and may modify or
withdraw its consent to the settlement
if comments received disclose facts or
considerations which indicate that the
amended settlement is inappropriate,
improper, or inadequate.
DATES:
Copies of the settlement are
available from the Agency by contacting
Ms. Paula V. Painter, Environmental
Protection Specialist using the contact
information provided in this notice.
Comments may also be submitted by
referencing the Site’s name through one
of the following methods:
ADDRESSES:
E:\FR\FM\14MRN1.SGM
14MRN1
Agencies
[Federal Register Volume 79, Number 50 (Friday, March 14, 2014)]
[Notices]
[Pages 14506-14507]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-05737]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[EPA-R04-OAR-2013-0577; EPA-R04-OAR-2013-0431; and EPA-R04-OAR-2013-
0648; FRL-9907-98-Region-4]
Notice of Issuance of Final Air Permits for Statoil Gulf
Services, LLC, Florida Power & Light--Port Everglades Next Generation
Clean Energy Center, and Tampa Electric Company.
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of final action.
-----------------------------------------------------------------------
SUMMARY: This notice is to announce that on October 28, 2013, the EPA
issued final Outer Continental Shelf (OCS) air quality permit numbered
OCS-EPA-R4012 for Statoil Gulf Services, LLC (Statoil); and on November
25, 2013 and December 18, 2013, the EPA issued final Prevention of
Significant Deterioration (PSD) air quality permits numbered PSD-EPA-
R4010 and PSD-EPA-R4014 for the Florida Power & Light (FPL)--Port
Everglades Next Generation Clean Energy Center (PEEC) and Tampa
Electric Company (TECO), respectively.
ADDRESSES: The final permits, the EPA's response to public comments for
these permits, and supporting information are available at https://www.epa.gov/region4/air/permits/index.htm. Copies of the final permits
and the EPA's response to comments are also available for review at the
EPA Regional Office and upon request in writing. The EPA requests that
you contact the person listed in the FOR FURTHER INFORMATION CONTACT
section to schedule your inspection. The Regional Office's official
hours of business are Monday through Friday, 8:30 a.m. to 4:30 p.m.
excluding Federal holidays.
FOR FURTHER INFORMATION CONTACT: Please contact Ms. Heather Ceron, Air
Permits Section Chief, Air Planning Branch, Air, Pesticides and Toxics
Management Division, Region 4, U.S. Environmental Protection Agency, 61
Forsyth Street SW., Atlanta, Georgia 30303-8960. The telephone number
is (404) 562-9185. Ms. Ceron can also be reached via electronic mail at
ceron.heather@epa.gov.
SUPPLEMENTARY INFORMATION: On August 9, 2013, EPA Region 4 requested
public comments on a preliminary determination to issue an OCS air
permit for Statoil. During the public comment period, which ended on
September 9, 2013, the EPA received no comments.
On May 31, 2013, EPA Region 4 requested public comments on a
preliminary determination to issue a PSD air quality permit for the FPL
PEEC project. A total of 26 comments from 3 commenters, including 1
request for a public hearing, were received (via email and letter)
during the public comment period, which closed on July 2, 2013.
On September 24, 2013, EPA Region 4 requested public comments on a
preliminary determination to issue a PSD air quality permit for the
TECO project. A total of 25 comments from two commenters were received
(via email) during the public comment
[[Page 14507]]
period, which closed on October 25, 2013.
The EPA reviewed each comment received and prepared a Response to
Comments document for the two projects. After consideration of the
expressed view of all interested persons, the pertinent federal
statutes and regulations, the applications and supplemental information
submitted by the applicants, and additional material relevant to the
applications and contained in the Administrative Records, the EPA made
final determinations in accordance with title 40 CFR part 52 and part
55 (for Statoil) to issue final air permits.
Under 40 CFR 124.19(f)(2), notice of any final Agency action
regarding a PSD permit must be published in the Federal Register.
Section 307(b)(1) of the CAA provides for review of final Agency action
that is locally or regionally applicable in the United States Court of
Appeals for the appropriate circuit. Such a petition for review of
final Agency action must be filed within 60 days from the date of
notice of such action in the Federal Register. For purposes of judicial
review under the CAA, final Agency action occurs when a final PSD
permit is issued or denied by the EPA and Agency review procedures are
exhausted, per 40 CFR 124.19(f)(1).
Any person who filed comments on the draft permits was provided the
opportunity to petition the Environmental Appeals Board by the end of
November 26, 2013 for the Statoil permit, by the end of December 26,
2013 for the PEEC permit, or by the end of January 17, 2014 for the
TECO permit. No petitions were submitted for any of these permits.
Therefore, the Statoil permit became effective on November 27, 2013.
The PEEC permit became effective on December 27, 2013. This date was
changed from December 25, 2013, as stated on the final permit, to
correct for the effective date coinciding with a federal holiday. The
TECO permit became effective on January 18, 2014.
Dated: February 27, 2014.
Carol L. Kemker,
Acting Director, Air, Pesticides and Toxics, Management Division,
Region 4.
[FR Doc. 2014-05737 Filed 3-13-14; 8:45 am]
BILLING CODE 6560-50-P