Reliability Standards for Physical Security Measures; Notice of Designation of Commission Staff as Non-Decisional, 14505 [2014-05628]
Download as PDF
Federal Register / Vol. 79, No. 50 / Friday, March 14, 2014 / Notices
electronic filing. Please file the
requested information using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first
page of any filing should include docket
number P–14345–001.
Dated: March 7, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–05627 Filed 3–13–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RD14–6–000]
Reliability Standards for Physical
Security Measures; Notice of
Designation of Commission Staff as
Non-Decisional
sroberts on DSK5SPTVN1PROD with NOTICES
With respect to an order issued by the
Commission today in the abovecaptioned docket, pursuant to 18 CFR
385.2201(c)(3) (2013), the staff
identified below from the Office of
Electric Reliability are designated as
non-decisional in deliberations by the
Commission in this docket.
Accordingly, these persons will not
serve as advisors to the Commission or
otherwise be involved in the decisional
process in this proceeding. Likewise, as
non-decisional staff, pursuant to 18 CFR
385.2201 (2013), they are prohibited
from communicating with advisory staff
concerning any deliberations in this
docket.
The staff designated as non-decisional
are:
Edward Franks
Regis Binder
David O’Connor
Mary Agnes Nimis
Justin Kelly
Andres Lopez
Dated: March 7, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–05628 Filed 3–13–14; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
19:18 Mar 13, 2014
Jkt 232001
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–R09–OAR–2011–0978; FRL–9908–07–
Region–9]
Notice of Decision To Issue Clean Air
Act PSD Permit for the Pio Pico Energy
Center
United States Environmental
Protection Agency (EPA) Region 9.
ACTION: Notice of final agency action.
AGENCY:
This notice announces that
EPA Region 9 issued a final permit
decision for a Clean Air Act Prevention
of Significant Deterioration (PSD)
permit to Pio Pico Energy Center, LLC
(PPLLC) for the construction of the Pio
Pico Energy Center (PPEC).
DATES: EPA Region 9 issued a final PSD
permit decision for the PPEC on
February 28, 2014. The PSD permit for
the PPEC will become effective on April
7, 2014. Pursuant to section 307(b)(1) of
the Clean Air Act, 42 U.S.C. 7607(b)(1),
judicial review of this final permit
decision, to the extent it is available,
may be sought by filing a petition for
review in the United States Court of
Appeals for the Ninth Circuit within 60
days of March 14, 2014.
ADDRESSES: Documents relevant to the
above-referenced permit are available
for public inspection during normal
business hours at the following address:
U.S. Environmental Protection Agency,
Region 9, 75 Hawthorne Street, San
Francisco, CA 94105–3901. To arrange
for viewing of these documents, call
Lisa Beckham at (415) 972–3811.
FOR FURTHER INFORMATION CONTACT: Lisa
Beckham, Permits Office (Air-3), U.S.
Environmental Protection Agency,
Region 9, (415) 972–3811,
beckham.lisa@epa.gov. Key portions of
the administrative record for this
decision (including the final permit, all
public comments, EPA’s responses to
the public comments, and additional
supporting information) are available
through a link at Region 9’s Web site,
www.epa.gov/region09/air/permit/r9permits-issued.html#psd, or at
www.regulations.gov (Docket ID # EPA–
R09–OAR–2011–0978). Anyone who
wishes to review the EPA
Environmental Appeals Board (EAB or
Board) decision described below or
documents in the EAB’s electronic
docket for its decision related to this
matter can obtain them at https://
www.epa.gov/eab/.
Notice of Final Action and
Supplementary Information: EPA
Region 9 issued its final permit decision
to PPLLC authorizing the construction
and operation of the PPEC, PSD Permit
No. SD 11–01, on February 28, 2014.
SUMMARY:
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
14505
EPA Region 9 initially issued a final
PSD permit decision to PPLLC for the
PPEC on November 19, 2012. Three
commenters filed petitions for review of
the Region’s November 19, 2012 PSD
permit decision for the PPEC with EPA’s
EAB. On August 2, 2013, the Board
issued a decision remanding in part and
denying review in part of the Region’s
November 19, 2012 PSD permit decision
for the PPEC. See In re Pio Pico Energy
Center PSD Permit No. SD 11–01, PSD
Appeal Nos. 12–04 through 12–06 (EAB,
Aug. 2, 2013) (Order Remanding in Part
and Denying Review in Part). The Board
remanded to Region 9 the emission
limits for particulate matter from the
combustion turbines and directed
Region 9 to prepare a revised Best
Available Control Technology (BACT)
analysis for particulate matter for the
Project’s combustion turbines in
accordance with the Board’s decision,
including a new BACT determination,
after consideration of all of the relevant
information. The Board also directed
Region 9 to reopen the public comment
period to provide the public with an
opportunity to comment on the
revisions to its particulate matter BACT
analysis. The EAB denied review of all
other issues.
In addition, the Board’s decision
stated that once Region 9 issues a final
permit decision following the public
comment period required by the
remand, the Region’s final permit
decision and the Board’s decision in
this matter would become final agency
action subject to judicial review per 40
CFR 124.19(l). The Board’s decision
further stated that the Board was not
requiring, and would not accept, an
appeal to the Board of the final permit
decision for the Project following
remand in this case.
In response to the EAB’s remand
decision, Region 9 prepared a revised
particulate matter BACT analysis and
BACT determination for the emission
limits for the Project’s combustion
turbines in accordance with the Board’s
order, and proposed revised permit
conditions for such limits. In November
of 2013, Region 9 issued a public notice
seeking public comment on this revised
analysis and these revised particulate
matter permit conditions, and on
December 17, 2013, Region 9 held a
public hearing to receive such comment.
EPA has carefully reviewed each of
the comments submitted and, after
consideration of the expressed views of
all commenters, the pertinent Federal
statutes and regulations, and additional
material relevant to the application and
contained in our Administrative Record,
EPA made a decision in accordance
E:\FR\FM\14MRN1.SGM
14MRN1
Agencies
[Federal Register Volume 79, Number 50 (Friday, March 14, 2014)]
[Notices]
[Page 14505]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-05628]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. RD14-6-000]
Reliability Standards for Physical Security Measures; Notice of
Designation of Commission Staff as Non-Decisional
With respect to an order issued by the Commission today in the
above-captioned docket, pursuant to 18 CFR 385.2201(c)(3) (2013), the
staff identified below from the Office of Electric Reliability are
designated as non-decisional in deliberations by the Commission in this
docket. Accordingly, these persons will not serve as advisors to the
Commission or otherwise be involved in the decisional process in this
proceeding. Likewise, as non-decisional staff, pursuant to 18 CFR
385.2201 (2013), they are prohibited from communicating with advisory
staff concerning any deliberations in this docket.
The staff designated as non-decisional are:
Edward Franks
Regis Binder
David O'Connor
Mary Agnes Nimis
Justin Kelly
Andres Lopez
Dated: March 7, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-05628 Filed 3-13-14; 8:45 am]