Pacific Gas and Electric Company; Notice of Authorization for Continued Project Operation, 14023 [2014-05308]
Download as PDF
Federal Register / Vol. 79, No. 48 / Wednesday, March 12, 2014 / Notices
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on March 26, 2014.
Dated: March 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–05303 Filed 3–11–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2351–000]
tkelley on DSK3SPTVN1PROD with NOTICES
Public Service Company of Colorado;
Notice of Authorization for Continued
Project Operation
On February 27, 2012, the Public
Service Company of Colorado, licensee
for the Cabin Creek Pumped Storage
Project, filed an Application for a New
License pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The Cabin Creek
Pumped Storage Project is located on
the South Clear Creek and its tributary
Cabin Creek in Clear Creek County,
Colorado.
The license for Project No. 2351 was
issued for a period ending February 28,
2014. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
VerDate Mar<15>2010
17:51 Mar 11, 2014
Jkt 232001
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2351
is issued to the licensee for a period
effective March 1, 2014 through
February 28, 2015 or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first.
If issuance of a new license (or other
disposition) does not take place on or
before February 28, 2015, notice is
hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise. If the
project is not subject to section 15 of the
FPA, notice is hereby given that the
licensee, Public Service Company of
Colorado, is authorized to continue
operation of the Cabin Creek Pumped
Storage Project, until such time as the
Commission acts on its application for
a subsequent license.
Dated: March 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–05307 Filed 3–11–14; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2467–000]
Pacific Gas and Electric Company;
Notice of Authorization for Continued
Project Operation
On February 8, 2012, the Pacific Gas
and Electric Company, licensee for the
Merced Falls Hydroelectric Project, filed
an Application for a New License
pursuant to the Federal Power Act
PO 00000
Frm 00047
Fmt 4703
Sfmt 9990
14023
(FPA) and the Commission’s regulations
thereunder. The Merced Falls
Hydroelectric Project is located on the
Merced River on the border of Merced
and Mariposa counties, California.
The license for Project No. 2179 was
issued for a period ending February 28,
2014. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2467
is issued to the licensee for a period
effective March 1, 2014 through
February 28, 2015 or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first.
If issuance of a new license (or other
disposition) does not take place on or
before February 28, 2015, notice is
hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise. If the
project is not subject to section 15 of the
FPA, notice is hereby given that the
licensee, Pacific Gas and Electric
Company, is authorized to continue
operation of the Merced Falls
Hydroelectric Project, until such time as
the Commission acts on its application
for a subsequent license.
Dated: March 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014–05308 Filed 3–11–14; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\12MRN1.SGM
12MRN1
Agencies
[Federal Register Volume 79, Number 48 (Wednesday, March 12, 2014)]
[Notices]
[Page 14023]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-05308]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2467-000]
Pacific Gas and Electric Company; Notice of Authorization for
Continued Project Operation
On February 8, 2012, the Pacific Gas and Electric Company, licensee
for the Merced Falls Hydroelectric Project, filed an Application for a
New License pursuant to the Federal Power Act (FPA) and the
Commission's regulations thereunder. The Merced Falls Hydroelectric
Project is located on the Merced River on the border of Merced and
Mariposa counties, California.
The license for Project No. 2179 was issued for a period ending
February 28, 2014. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2467 is issued to
the licensee for a period effective March 1, 2014 through February 28,
2015 or until the issuance of a new license for the project or other
disposition under the FPA, whichever comes first.
If issuance of a new license (or other disposition) does not take
place on or before February 28, 2015, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1)
of the FPA is renewed automatically without further order or notice by
the Commission, unless the Commission orders otherwise. If the project
is not subject to section 15 of the FPA, notice is hereby given that
the licensee, Pacific Gas and Electric Company, is authorized to
continue operation of the Merced Falls Hydroelectric Project, until
such time as the Commission acts on its application for a subsequent
license.
Dated: March 5, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-05308 Filed 3-11-14; 8:45 am]