Algonquin Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Salem Lateral Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting, 8956-8958 [2014-03189]

Download as PDF 8956 Federal Register / Vol. 79, No. 31 / Friday, February 14, 2014 / Notices Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Salem Lateral Project involving construction and operation of facilities by Algonquin Gas Transmission, LLC (Algonquin) in Salem, Massachusetts. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. PF14–5–000] Algonquin Gas Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Salem Lateral Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting The staff of the Federal Energy Regulatory Commission (FERC or staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on March 10, 2014. You may submit comments in written form. Further details on how to submit written comments are in the Public Participation section of this notice. In lieu of or in addition to sending written comments, the Commission invites you to attend the public scoping meeting scheduled as follows: Date and time Location Thursday, March 6, 2014, 6:00 pm local time ......................................... Bentley Elementary School Cafetorium, 25 Memorial Drive, Salem, MA 01970. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this planned project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the planned facilities. Algonquin would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility on My Land? What Do I Need To Know?’’ is available for viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. mstockstill on DSK4VPTVN1PROD with NOTICES Summary of the Planned Project Algonquin plans to construct and operate 1.2 miles of new 16-inchdiameter lateral pipeline and a new metering and regulation station in Salem, Massachusetts in order to supply 115,000 dekatherms per day of natural gas to the Salem Harbor Station facility VerDate Mar<15>2010 17:47 Feb 13, 2014 Jkt 232001 for power generation.1 The general location of the project facilities is shown in appendix 1.2 Land Requirements for Construction Construction of the planned facilities would involve conventional onshore construction and use of horizontal directional drills (HDD). Onshore construction would disturb approximately 11 acres of land for the pipeline and meter station. Following construction, Algonquin would maintain about 0.5 acre for permanent operation of the meter station and approximately 4 acres for the permanent onshore easement. About 7 percent of the planned lateral route parallels an existing electric transmission right-ofway. Two HDDs would be utilized to cross Collins Cove (for approximately 0.4 mile) and Beverly Harbor (for approximately 0.2 mile), up to a tie-in location with Algonquin’s existing Hubline Pipeline. In-water work would be limited to the area immediately surrounding the new subsea tie-in within Beverly Harbor. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental 1 The Salem Harbor Station facility is being redeveloped from an existing coal burning electric generation plant to a new natural gas-fired electric generation facility by Footprint Power Salem Harbor Development, LP. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the Additional Information section at the end of this notice. PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as scoping. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the planned project under these general headings: • Geology and soils; • water resources, fisheries, and wetlands; • vegetation and wildlife; • endangered and threatened species; • cultural resources; • land use; • air quality and noise; • reliability and safety; and • cumulative environmental impacts. We will also evaluate possible alternatives to the planned project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Although no formal application has been filed, we have already initiated our NEPA review under the Commission’s pre-filing process. The purpose of the pre-filing process is to encourage early involvement of interested stakeholders 3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\14FEN1.SGM 14FEN1 Federal Register / Vol. 79, No. 31 / Friday, February 14, 2014 / Notices and to identify and resolve issues before the FERC receives an application. As part of our pre-filing review, we have begun to contact some federal and state agencies to discuss their involvement in the scoping process and the preparation of the EA. Our independent analysis of the issues will be presented in the EA. The EA will be available in the public record through the Commission’s eLibrary. Depending on the comments received during scoping, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section of this notice. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues related to this project to formally cooperate with us in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Currently, the U.S. Army Corps of Engineers has expressed its intention to participate as a cooperating agency in the preparation of the EA to satisfy its NEPA responsibilities related to this project. mstockstill on DSK4VPTVN1PROD with NOTICES Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the Massachusetts State Historic Preservation Office (SHPO), and to solicit its views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.5 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Mar<15>2010 17:47 Feb 13, 2014 Jkt 232001 disturbance (examples include construction right-of-way, contractor/ pipe storage yards, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Currently Identified Environmental Issues We have already identified several issues that we think deserve attention based on a preliminary review of the planned facilities and the environmental information provided by Algonquin. This preliminary list of issues may change based on your comments and our analysis. • impact on aquatic resources; • contaminated soils; • cumulative impacts on air quality; and • construction in residential areas. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before March 10, 2014. For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances, please reference the project docket number (PF14–5–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 8957 project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the planned project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor Once Algonquin files its application with the Commission, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Please note that the Commission will not accept requests for intervenor status at this time. You must wait until the Commission receives a formal application for the project. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web E:\FR\FM\14FEN1.SGM 14FEN1 8958 Federal Register / Vol. 79, No. 31 / Friday, February 14, 2014 / Notices site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., PF14– 5). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: February 7, 2014. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2014–03189 Filed 2–13–14; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. PF14–3–000] mstockstill on DSK4VPTVN1PROD with NOTICES Transcontinental Gas Pipe Line Company, LLC; Notice of Intent to Prepare an Environmental Assessment For the Planned Rock Springs Expansion Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Rock Springs Expansion Project (Project) involving construction and operation of facilities by Transcontinental Gas Pipeline Company, LLC (Transco) in Lancaster County, Pennsylvania and Cecil County, Maryland. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission VerDate Mar<15>2010 17:47 Feb 13, 2014 Jkt 232001 will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on March 10, 2014. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this planned project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the planned facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility on My Land? What Do I Need To Know?’’ is available for viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. • A pig launcher and valve facility at the start of the pipeline lateral, including two tie-ins; 1 • A back-pressure control regulator valve to increase operational pressure flexibility; located either (1) near the existing 30-inch Mainline ‘‘A’’ block valve at MP 1691.1 or (2) near MP 1682.8, both in Lancaster County, Pennsylvania; and • A 4,000 horsepower electric motor driven compressor station, designated as Compressor Station 196, with metering facilities at the terminus of the pipeline lateral. A pig receiver to be installed at the terminus of the pipeline lateral within the compressor station. The general location of the project facilities is shown in appendix 1.2 Summary of the Planned Project Transco is proposing to construct facilities to provide 192,000 dekatherms per day of incremental firm transportation capacity from Transco’s Market Pool Station 210 in Mercer County, New Jersey to Old Dominion Electric Cooperative’s (ODEC) proposed expansion, referred to as the Wildcat Point Generating Facility (Wildcat Plant) in Cecil County, Maryland. Construction of the Project is scheduled to begin on August 1, 2015 to meet the proposed in-service date of August 2016. The Rock Springs Expansion Project would consist of the following facilities: • Approximately 10.6 miles of new 20-inch diameter pipeline lateral from Transco’s existing Mainlines ‘‘A’’ and ‘‘B’’ near milepost (MP) 1682.8 in Lancaster County, Pennsylvania to the proposed Wildcat Plant in Cecil County, Maryland; • Piping and valve modifications to the existing Transco Compressor Station 200 in Chester County, Pennsylvania; The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as scoping. The main goal of the scoping process is to focus the analysis in the EA on the PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 Land Requirements for Construction Construction of the proposed facilities would disturb approximately 220.9 acres of land for the aboveground facilities and the pipeline lateral. Following construction, Transco would maintain approximately 55.3 acres for permanent operation of the Project’s facilities; the remaining acreage would be restored and revert to former uses. Transco is continuing to evaluate the construction and operation land requirements for the launcher and valve facility at the start of the pipeline lateral, as well as the back-pressure control regulator valve, therefore the aforementioned acreages are preliminary estimations. Approximately 34 percent of the proposed pipeline route is situated adjacent to existing utility or road rights-of-way. 1 A ‘‘pig’’ is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\14FEN1.SGM 14FEN1

Agencies

[Federal Register Volume 79, Number 31 (Friday, February 14, 2014)]
[Notices]
[Pages 8956-8958]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-03189]



[[Page 8956]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF14-5-000]


Algonquin Gas Transmission, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Planned Salem Lateral Project, Request 
for Comments on Environmental Issues, and Notice of Public Scoping 
Meeting

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Salem Lateral Project 
involving construction and operation of facilities by Algonquin Gas 
Transmission, LLC (Algonquin) in Salem, Massachusetts. The Commission 
will use this EA in its decision-making process to determine whether 
the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on March 10, 2014.
    You may submit comments in written form. Further details on how to 
submit written comments are in the Public Participation section of this 
notice. In lieu of or in addition to sending written comments, the 
Commission invites you to attend the public scoping meeting scheduled 
as follows:

------------------------------------------------------------------------
             Date and time                           Location
------------------------------------------------------------------------
Thursday, March 6, 2014, 6:00 pm local   Bentley Elementary School
 time.                                    Cafetorium, 25 Memorial Drive,
                                          Salem, MA 01970.
------------------------------------------------------------------------

    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this planned 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. Algonquin 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility on My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Summary of the Planned Project

    Algonquin plans to construct and operate 1.2 miles of new 16-inch-
diameter lateral pipeline and a new metering and regulation station in 
Salem, Massachusetts in order to supply 115,000 dekatherms per day of 
natural gas to the Salem Harbor Station facility for power 
generation.\1\ The general location of the project facilities is shown 
in appendix 1.\2\
---------------------------------------------------------------------------

    \1\ The Salem Harbor Station facility is being redeveloped from 
an existing coal burning electric generation plant to a new natural 
gas-fired electric generation facility by Footprint Power Salem 
Harbor Development, LP.
    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the Additional Information section 
at the end of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the planned facilities would involve conventional 
onshore construction and use of horizontal directional drills (HDD). 
Onshore construction would disturb approximately 11 acres of land for 
the pipeline and meter station. Following construction, Algonquin would 
maintain about 0.5 acre for permanent operation of the meter station 
and approximately 4 acres for the permanent onshore easement. About 7 
percent of the planned lateral route parallels an existing electric 
transmission right-of-way. Two HDDs would be utilized to cross Collins 
Cove (for approximately 0.4 mile) and Beverly Harbor (for approximately 
0.2 mile), up to a tie-in location with Algonquin's existing Hubline 
Pipeline. In-water work would be limited to the area immediately 
surrounding the new subsea tie-in within Beverly Harbor.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the planned project under these 
general headings:
     Geology and soils;
     water resources, fisheries, and wetlands;
     vegetation and wildlife;
     endangered and threatened species;
     cultural resources;
     land use;
     air quality and noise;
     reliability and safety; and
     cumulative environmental impacts.
    We will also evaluate possible alternatives to the planned project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders

[[Page 8957]]

and to identify and resolve issues before the FERC receives an 
application. As part of our pre-filing review, we have begun to contact 
some federal and state agencies to discuss their involvement in the 
scoping process and the preparation of the EA.
    Our independent analysis of the issues will be presented in the EA. 
The EA will be available in the public record through the Commission's 
eLibrary. Depending on the comments received during scoping, we may 
also publish and distribute the EA to the public for an allotted 
comment period. We will consider all comments on the EA before we make 
our recommendations to the Commission. To ensure we have the 
opportunity to consider and address your comments, please carefully 
follow the instructions in the Public Participation section of this 
notice.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to this project to formally cooperate with us in the 
preparation of the EA.\4\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice. Currently, the U.S. Army Corps of Engineers has expressed its 
intention to participate as a cooperating agency in the preparation of 
the EA to satisfy its NEPA responsibilities related to this project.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the Massachusetts State Historic Preservation Office (SHPO), and 
to solicit its views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, and access 
roads). Our EA for this project will document our findings on the 
impacts on historic properties and summarize the status of 
consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified several issues that we think deserve 
attention based on a preliminary review of the planned facilities and 
the environmental information provided by Algonquin. This preliminary 
list of issues may change based on your comments and our analysis.
     impact on aquatic resources;
     contaminated soils;
     cumulative impacts on air quality; and
     construction in residential areas.

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before March 
10, 2014.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (PF14-5-000) with your submission. The Commission 
encourages electronic filing of comments and has expert staff available 
to assist you at (202) 502-8258 or efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. This is an easy method for interested 
persons to submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
planned project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    Once Algonquin files its application with the Commission, you may 
want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives a formal application for the project.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web

[[Page 8958]]

site (www.ferc.gov) using the eLibrary link. Click on the eLibrary 
link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF14-
5). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: February 7, 2014.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2014-03189 Filed 2-13-14; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.