Proposed Information Collection (VAAR Clauses 852-236-72, 852.236.80, 852.236-82, 852.236-83, 852.236-84, and 852.236-88) Activity: Comment Request, 3271-3272 [2014-00825]

Download as PDF emcdonald on DSK67QTVN1PROD with NOTICES Federal Register / Vol. 79, No. 12 / Friday, January 17, 2014 / Notices period, comments may be viewed online through the FDMS. FOR FURTHER INFORMATION CONTACT: Nancy J. Kessinger at (202) 632–8924 or FAX (202) 632–8925. SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104–13; 44 U.S.C. 3501–3521), Federal agencies must obtain approval from the Office of Management and Budget (OMB) for each collection of information they conduct or sponsor. This request for comment is being made pursuant to Section 3506(c)(2)(A) of the PRA. With respect to the following collection of information, VBA invites comments on: (1) Whether the proposed collection of information is necessary for the proper performance of VBA’s functions, including whether the information will have practical utility; (2) the accuracy of VBA’s estimate of the burden of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including through the use of automated collection techniques or the use of other forms of information technology. Title: Certificate of Affirmation of Enrollment Agreement— Correspondence Course VA Form 22– 1999c. OMB Control Number: 2900–0576. Type of Review: Extension without change of a currently approved collection. Abstract: Claimants enrolled in a correspondence training course complete and submit VA Form 22– 1999c to the correspondence school to affirm the enrollment agreement contract. The certifying official at the correspondence school must submit the form and the enrollment certification to VA for processing. VA uses the information to determine if the claimant signed and dated the form during the five day reflection period. In addition, the claimant must sign VA Form 22– 1999c on or after the seventh day the enrollment agreement was dated. VA will not pay educational benefits for correspondence training that was completed nor accept the affirmation agreement that was signed and dated on or before the enrollment agreement date. Affected Public: Individuals or households. Estimated Annual Burden: 18 hours. Estimated Average Burden per Respondent: 3 minutes. Frequency of Response: On occasion. Estimated Number of Respondents: 360. VerDate Mar<15>2010 17:00 Jan 16, 2014 Jkt 232001 Dated: January 13, 2014. By direction of the Secretary. Crystal Rennie, VA Clearance Officer, Department of Veterans Affairs. [FR Doc. 2014–00776 Filed 1–16–14; 8:45 am] BILLING CODE 8320–01–P DEPARTMENT OF VETERANS AFFAIRS [OMB Control No. 2900–0422] Proposed Information Collection (VAAR Clauses 852–236–72, 852.236.80, 852.236–82, 852.236–83, 852.236–84, and 852.236–88) Activity: Comment Request Office of Management, Department of Veterans Affairs. ACTION: Notice. AGENCY: The Office of Management (OM), Department of Veterans Affairs (VA), is announcing an opportunity for public comment on the proposed collection of certain information by the agency. Under the Paperwork Reduction Act (PRA) of 1995, Federal agencies are required to publish notice in the Federal Register concerning each proposed collection of information, including each extension without change of a currently approved collection, and allow 60 days for public comment in response to the notice. This notice solicits comments on information needed to administer contracts. DATES: Written comments and recommendations on the proposed collection of information should be received on or before March 18, 2014. ADDRESSES: Submit written comments on the collection of information through the Federal Docket Management System (FDMS) at www.Regulations.gov; or to Waleska Pierantoni-Monge, Office of Acquisition and Logistics (003A2A), Department of Veterans Affairs, 810 Vermont Avenue NW., Washington, DC 20420; or email: waleska.pierantonimonge@va.gov. Please refer to ‘‘OMB Control No. 2900–0422’’ in any correspondence. During the comment period, comments may be viewed online through FDMS. FOR FURTHER INFORMATION CONTACT: Waleska Pierantoni-Monge at (202) 632– 5400, Fax (202) 343–1434. SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104–13; 44 U.S.C. 3501–21), Federal agencies must obtain approval from the Office of Management and Budget (OMB) for each collection of information they conduct or sponsor. This request for comment is being made SUMMARY: PO 00000 Frm 00109 Fmt 4703 Sfmt 4703 3271 pursuant to Section 3506(c)(2)(A) of the PRA. With respect to the following collection of information, (OM) invites comments on: (1) Whether the proposed collection of information is necessary for the proper performance of (OM)’s functions, including whether the information will have practical utility; (2) the accuracy of (OM)’s estimate of the burden of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including through the use of automated collection techniques or the use of other forms of information technology. Titles a. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–72, Performance of Work by the Contractor. b. Department of Veterans Affairs Acquisition Regulation (VAAR) Alternate I to Clause 852.236–80, Subcontracts and Work Coordination. c. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–82, Payments Under FixedPrice Construction Contracts (without NAS), including Alternate 1. d. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–83, Payments Under FixedPrice Construction Contracts (with NAS), including Alternate 1. e. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–84, Schedule of Work Progress. f. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes. OMB Control Number: 2900–0422. Type of Review: Extension of a currently approved collection. Abstract: The information contained Department of Veterans Acquisition Regulation (VAAR) Clauses 852.236–72, Alternate I to 852.236–80, 852.236–82, 852.236–83, 852.236–84, and 852.236– 88 is necessary for VA to administer construction contracts, and to carry out its responsibility to construct, maintain and repair real property for the Department. a. VAAR Clause 852.236–72, Performance of Work by the Contractor, requires contractors awarded a construction contract containing Federal Acquisition Regulation (FAR) clause 52.236–1, to submit a statement designating the branch or branches of contract work to be performed by the E:\FR\FM\17JAN1.SGM 17JAN1 emcdonald on DSK67QTVN1PROD with NOTICES 3272 Federal Register / Vol. 79, No. 12 / Friday, January 17, 2014 / Notices contractor’s own forces. The VAAR clause implements the FAR clause by requiring the contractor to provide information to the contracting officer on how the contractor intends to fulfill this contractual obligation. The contracting officer uses this information to ensure that the contractor complies with the contract requirements. b. Alternate I to Clause 852.236–80, Work Coordination, require construction contractors, on contracts involving complex mechanicalelectrical work, to furnish coordination drawings showing the manner in which utility lines will fit into available spaces and relate to each other and to the existing building elements. The information is used by the contracting officer and VA engineer assigned to the project to resolve any problems relating to the installation of utilities on construction contract. c. VAAR Clause 852.236–82, Payments Under Fixed-Price Construction Contracts (without NAS), requires construction contractors to submit a schedule of costs for work to be performed under the contract. If the contract includes guarantee period services, Alternate I requires contractor to submit information on the total and itemized costs of the guarantee period services and to submit a performance plan/program. The information is needed to allow the contracting officer to determine the correct amount to pay the contractor as work progresses and to properly proportion the amount paid for guarantee period services. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), requires construction contractors to submit a schedule of costs for work to be performed under the contract. If the contract includes guarantee period services, Alternate I requires contractor to submit information on the total and itemized costs of the guarantee period services and to submit a performance plan/program. The information is needed to allow the contracting officer to determine the correct amount to pay the contractor as work progresses and to properly proportion the amount paid for guarantee period services. The difference between this clause and the one above 852.236–82 is that this clause requires the contractor to use a computerized Network Analysis System (NAS) to prepare the cost estimate. e. VAAR Clause 852.236–84, Schedule of Work Progress, requires construction contractors, on contracts that do not require the use of a NAS, to submit a progress schedule. The information is used by the contracting officer to track the contractor’s progress VerDate Mar<15>2010 17:00 Jan 16, 2014 Jkt 232001 under the contract and to determine whether or not the contractor is making satisfactory progress. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes. FAR Clause 52.243– 4 authorizes the contracting officer to order changes to a construction contract but does not specifically require the contractor to submit cost proposals for those changes. VAAR Clause 852.236– 88 requires contractors to submit cost proposal for changes ordered by the contracting officer or for changes proposed by the contractor. This information is needed to allow the contracting officer and the contractor to reach a mutually acceptable agreement on how much to pay the contractor for the proposed changes to the contract. It is also used by the contracting officer to determine whether or not to authorize the proposed changes or whether or not additional or alternate cost proposals for changes are needed. Affected Public: Business or other forprofit; Individuals and households; and Not-for-profit institutions. Estimated Annual Burden a. VAAR Clause 852.236–72, Performance of Work by the Contractor—60 hours. b. VAAR Alternate I to Clause 852.236–80, Subcontracts and Work Coordination—920 hours. c. VAAR Clause 852.236–82, Payments Under Fixed-Price Construction Contracts (without NAS), including Alternate 1—1,219 hours. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), including Alternate 1—46 hours. e. VAAR Clause 852.236–84, Schedule of Work Progress—1828.5 hours. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes—729 hours. Estimated Average Burden per Respondent a. VAAR Clause 852.236–72, Performance of Work by the Contractor—1 hour. b. VAAR Alternate I to Clause 852.236–80, Subcontracts and Work Coordination—10 hours. c. VAAR Clause 852.236–82, Payments Under Fixed-Price Construction Contracts (without NAS), including Alternate 1—1 hour. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), including Alternate 1—30 minutes. e. VAAR Clause 852.236–84, Schedule of Work Progress—1 hour. PO 00000 Frm 00110 Fmt 4703 Sfmt 4703 f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes—3 hours. Frequency of Response: On occasion. Estimated Number of Respondents a. VAAR Clause 852.236–72, Performance of Work by the Contractor—60. b. VAAR Alternate I to Clause 852.236–80, Subcontracts and Work Coordination—92. c. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–82, Payments Under FixedPrice Construction Contracts (without NAS), including Alternate 1—1,219. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), including Alternate 1—92 e. VAAR Clause 852.236–84, Schedule of Work Progress—1,219. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes—243. Dated: January 14, 2014. By direction of the Secretary. Crystal Rennie, VA Clearance Officer, Department of Veterans Affairs. [FR Doc. 2014–00825 Filed 1–16–14; 8:45 am] BILLING CODE 8320–01–P DEPARTMENT OF VETERANS AFFAIRS [OMB Control No. 2900–0556] Proposed Information Collection (Living Will and Durable Power of Attorney for Health Care) Activity: Comment Request Veterans Health Administration, Department of Veterans Affairs. ACTION: Notice. AGENCY: The Veterans Health Administration (VHA) is announcing an opportunity for public comment on the proposed collection of certain information by the agency. Under the Paperwork Reduction Act (PRA) of 1995, Federal agencies are required to publish notice in the Federal Register concerning each proposed collection of information, including each proposed extension of a currently approved collection, and allow 60 days for public comment in response to the notice. This notice solicits comments on information needed to identify areas for improvement in clinical training programs. SUMMARY: Written comments and recommendations on the proposed DATES: E:\FR\FM\17JAN1.SGM 17JAN1

Agencies

[Federal Register Volume 79, Number 12 (Friday, January 17, 2014)]
[Notices]
[Pages 3271-3272]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2014-00825]


-----------------------------------------------------------------------

DEPARTMENT OF VETERANS AFFAIRS

[OMB Control No. 2900-0422]


Proposed Information Collection (VAAR Clauses 852-236-72, 
852.236.80, 852.236-82, 852.236-83, 852.236-84, and 852.236-88) 
Activity: Comment Request

AGENCY: Office of Management, Department of Veterans Affairs.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: The Office of Management (OM), Department of Veterans Affairs 
(VA), is announcing an opportunity for public comment on the proposed 
collection of certain information by the agency. Under the Paperwork 
Reduction Act (PRA) of 1995, Federal agencies are required to publish 
notice in the Federal Register concerning each proposed collection of 
information, including each extension without change of a currently 
approved collection, and allow 60 days for public comment in response 
to the notice. This notice solicits comments on information needed to 
administer contracts.

DATES: Written comments and recommendations on the proposed collection 
of information should be received on or before March 18, 2014.

ADDRESSES: Submit written comments on the collection of information 
through the Federal Docket Management System (FDMS) at 
www.Regulations.gov; or to Waleska Pierantoni-Monge, Office of 
Acquisition and Logistics (003A2A), Department of Veterans Affairs, 810 
Vermont Avenue NW., Washington, DC 20420; or email: waleska.pierantoni-monge@va.gov. Please refer to ``OMB Control No. 2900-0422'' in any 
correspondence. During the comment period, comments may be viewed 
online through FDMS.

FOR FURTHER INFORMATION CONTACT: Waleska Pierantoni-Monge at (202) 632-
5400, Fax (202) 343-1434.

SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104-13; 44 
U.S.C. 3501-21), Federal agencies must obtain approval from the Office 
of Management and Budget (OMB) for each collection of information they 
conduct or sponsor. This request for comment is being made pursuant to 
Section 3506(c)(2)(A) of the PRA.
    With respect to the following collection of information, (OM) 
invites comments on: (1) Whether the proposed collection of information 
is necessary for the proper performance of (OM)'s functions, including 
whether the information will have practical utility; (2) the accuracy 
of (OM)'s estimate of the burden of the proposed collection of 
information; (3) ways to enhance the quality, utility, and clarity of 
the information to be collected; and (4) ways to minimize the burden of 
the collection of information on respondents, including through the use 
of automated collection techniques or the use of other forms of 
information technology.

Titles

    a. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-72, Performance of Work by the Contractor.
    b. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Alternate I to Clause 852.236-80, Subcontracts and Work Coordination.
    c. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-82, Payments Under Fixed-Price Construction Contracts 
(without NAS), including Alternate 1.
    d. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-83, Payments Under Fixed-Price Construction Contracts 
(with NAS), including Alternate 1.
    e. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-84, Schedule of Work Progress.
    f. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-88, Contract Changes, Supplements FAR Clause 52.243-4, 
Changes.
    OMB Control Number: 2900-0422.
    Type of Review: Extension of a currently approved collection.
    Abstract: The information contained Department of Veterans 
Acquisition Regulation (VAAR) Clauses 852.236-72, Alternate I to 
852.236-80, 852.236-82, 852.236-83, 852.236-84, and 852.236-88 is 
necessary for VA to administer construction contracts, and to carry out 
its responsibility to construct, maintain and repair real property for 
the Department.
    a. VAAR Clause 852.236-72, Performance of Work by the Contractor, 
requires contractors awarded a construction contract containing Federal 
Acquisition Regulation (FAR) clause 52.236-1, to submit a statement 
designating the branch or branches of contract work to be performed by 
the

[[Page 3272]]

contractor's own forces. The VAAR clause implements the FAR clause by 
requiring the contractor to provide information to the contracting 
officer on how the contractor intends to fulfill this contractual 
obligation. The contracting officer uses this information to ensure 
that the contractor complies with the contract requirements.
    b. Alternate I to Clause 852.236-80, Work Coordination, require 
construction contractors, on contracts involving complex mechanical-
electrical work, to furnish coordination drawings showing the manner in 
which utility lines will fit into available spaces and relate to each 
other and to the existing building elements. The information is used by 
the contracting officer and VA engineer assigned to the project to 
resolve any problems relating to the installation of utilities on 
construction contract.
    c. VAAR Clause 852.236-82, Payments Under Fixed-Price Construction 
Contracts (without NAS), requires construction contractors to submit a 
schedule of costs for work to be performed under the contract. If the 
contract includes guarantee period services, Alternate I requires 
contractor to submit information on the total and itemized costs of the 
guarantee period services and to submit a performance plan/program. The 
information is needed to allow the contracting officer to determine the 
correct amount to pay the contractor as work progresses and to properly 
proportion the amount paid for guarantee period services.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), requires construction contractors to submit a 
schedule of costs for work to be performed under the contract. If the 
contract includes guarantee period services, Alternate I requires 
contractor to submit information on the total and itemized costs of the 
guarantee period services and to submit a performance plan/program. The 
information is needed to allow the contracting officer to determine the 
correct amount to pay the contractor as work progresses and to properly 
proportion the amount paid for guarantee period services. The 
difference between this clause and the one above 852.236-82 is that 
this clause requires the contractor to use a computerized Network 
Analysis System (NAS) to prepare the cost estimate.
    e. VAAR Clause 852.236-84, Schedule of Work Progress, requires 
construction contractors, on contracts that do not require the use of a 
NAS, to submit a progress schedule. The information is used by the 
contracting officer to track the contractor's progress under the 
contract and to determine whether or not the contractor is making 
satisfactory progress.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes. FAR Clause 52.243-4 authorizes the contracting 
officer to order changes to a construction contract but does not 
specifically require the contractor to submit cost proposals for those 
changes. VAAR Clause 852.236-88 requires contractors to submit cost 
proposal for changes ordered by the contracting officer or for changes 
proposed by the contractor. This information is needed to allow the 
contracting officer and the contractor to reach a mutually acceptable 
agreement on how much to pay the contractor for the proposed changes to 
the contract. It is also used by the contracting officer to determine 
whether or not to authorize the proposed changes or whether or not 
additional or alternate cost proposals for changes are needed.
    Affected Public: Business or other for-profit; Individuals and 
households; and Not-for-profit institutions.

Estimated Annual Burden

    a. VAAR Clause 852.236-72, Performance of Work by the Contractor--
60 hours.
    b. VAAR Alternate I to Clause 852.236-80, Subcontracts and Work 
Coordination--920 hours.
    c. VAAR Clause 852.236-82, Payments Under Fixed-Price Construction 
Contracts (without NAS), including Alternate 1--1,219 hours.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), including Alternate 1--46 hours.
    e. VAAR Clause 852.236-84, Schedule of Work Progress--1828.5 hours.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes--729 hours.

Estimated Average Burden per Respondent

    a. VAAR Clause 852.236-72, Performance of Work by the Contractor--1 
hour.
    b. VAAR Alternate I to Clause 852.236-80, Subcontracts and Work 
Coordination--10 hours.
    c. VAAR Clause 852.236-82, Payments Under Fixed-Price Construction 
Contracts (without NAS), including Alternate 1--1 hour.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), including Alternate 1--30 minutes.
    e. VAAR Clause 852.236-84, Schedule of Work Progress--1 hour.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes--3 hours.
    Frequency of Response: On occasion.

Estimated Number of Respondents

    a. VAAR Clause 852.236-72, Performance of Work by the Contractor--
60.
    b. VAAR Alternate I to Clause 852.236-80, Subcontracts and Work 
Coordination--92.
    c. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-82, Payments Under Fixed-Price Construction Contracts 
(without NAS), including Alternate 1--1,219.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), including Alternate 1--92
    e. VAAR Clause 852.236-84, Schedule of Work Progress--1,219.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes--243.

    Dated: January 14, 2014.
    By direction of the Secretary.
Crystal Rennie,
VA Clearance Officer, Department of Veterans Affairs.
[FR Doc. 2014-00825 Filed 1-16-14; 8:45 am]
BILLING CODE 8320-01-P