Houston Pipe Line Company, LP; Notice of Intent to Prepare an Environmental Assessment for the Proposed 24-Inch Border Crossing Project and Request for Comments on Environmental Issues, 78350-78352 [2013-30783]
Download as PDF
emcdonald on DSK67QTVN1PROD with NOTICES
78350
Federal Register / Vol. 78, No. 248 / Thursday, December 26, 2013 / Notices
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR Part 380 (Order No.
486, 52 FR 47897), the Office of Energy
Projects has reviewed the application
for an original license for the
Pomperaug Hydro Project, to be located
on the Pomperaug River, in the town of
Woodbury, Litchfield County,
Connecticut, and has prepared a draft
Environmental Assessment (EA).
The draft EA contains the staff’s
analysis of the potential environmental
impacts of the project and concludes
that licensing the project, with
appropriate environmental protective
measures, would not constitute a major
federal action that would significantly
affect the quality of the human
environment.
A copy of the draft EA is on file with
the Commission and is available for
public inspection. The draft EA may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. You may also register
online at https://www.ferc.gov/docsfiling/esubscription.asp to be notified
via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Any comments should be filed within
30 days from the date of this notice.
Comments may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments.
For assistance, please contact FERC
Online Support. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail
comments to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. The first page of
any filing should include docket
number P–12790–002.
For further information, contact Steve
Kartalia at (202) 502–6131 or
Stephen.Kartalia@ferc.gov.
VerDate Mar<15>2010
18:06 Dec 24, 2013
Jkt 232001
Dated: December 19, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–30834 Filed 12–24–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–13–000]
Houston Pipe Line Company, LP;
Notice of Intent to Prepare an
Environmental Assessment for the
Proposed 24-Inch Border Crossing
Project and Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the 24-Inch Border Crossing Project
(Project) involving construction and
operation of border crossing facilities at
the international border between
Mexico and the United States in Hidalgo
County, Texas by Houston Pipe Line
Company, LP (HPL). The Commission
will use this EA in its decision-making
process to determine whether the
Project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on January 17,
2014.
You may submit comments in written
form or verbally. Further details on how
to submit written comments are in the
Public Participation section of this
notice.
This notice is being sent to the
Commission’s current environmental
mailing list for the Project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the Project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
HPL provided landowners with a fact
sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically-asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
Summary of the Proposed Project
HPL proposes to construct a new
border crossing at the international
boundary between the United States and
Mexico in Hidalgo County, Texas. The
Project would consist of approximately
703 feet of 24-inch-diameter natural gas
pipeline, directionally drilled
underneath the Rio Grande River in
Hidalgo County, Texas. The new
pipeline would have a design capacity
of approximately 140 million cubic feet
per day (Mmcf/d) and a maximum
allowable operating pressure of 1,300
pounds per square inch gauge designed
to transport natural gas to a new
delivery interconnect with HPL’s nonjurisdictional intrastate pipeline and to
a new interconnection with the Pemex
Pipeline at the United States-Mexico
border.
The general location of the Project is
shown in Appendix 1.
Land Requirements for Construction
Construction of the planned facilities
would require ground disturbance of
approximately 4.1 acres of land for
temporary workspace. Following
construction, HPL would maintain 0.81
acre for operation of the Project and the
remaining 3.3 acres would be
revegetated.
In its application, HPL indicates that
it would also construct pipeline
facilities that are not under the
jurisdiction of the FERC. Although
FERC doesn’t have the regulatory
authority to modify or deny the
construction of these facilities, we will
disclose available information regarding
the construction impacts in our EA.
These facilities would include
approximately 23 miles of 24-inch1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
E:\FR\FM\26DEN1.SGM
26DEN1
Federal Register / Vol. 78, No. 248 / Thursday, December 26, 2013 / Notices
emcdonald on DSK67QTVN1PROD with NOTICES
diameter intrastate pipeline, to
interconnect with the existing Edinburg
Lateral Pipeline in Hidalgo County,
Texas.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
planned Project under these general
headings:
• geology and soils;
• water resources and fisheries;
• vegetation, wildlife, and
endangered and threatened species;
• land use and cumulative impacts;
• cultural resources;
• air quality and noise; and
• public safety.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section
below.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues related to this
Project to formally cooperate with us in
the preparation of the EA.3
2 ‘‘We,’’
‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
3 The Council on Environmental Quality
regulations addressing cooperating agency
VerDate Mar<15>2010
18:06 Dec 24, 2013
Jkt 232001
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
Texas Historical Commission (THC),
and to solicit their views and those of
other government agencies, interested
Indian tribes, and the public on the
Project’s potential effects on historic
properties.4 We will define the Projectspecific Area of Potential Effects in
consultation with the State Historic
Preservation Officer as the Project
develops. On natural gas facility
projects, the Area of Potential Effects at
a minimum encompasses all areas
subject to ground disturbance (examples
include construction right-of-way,
contractor/pipe storage yards, meter
stations, and access roads). Our EA for
this Project will document our findings
on the impacts on historic properties
and summarize the status of
consultations under section 106.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the Project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before January 17,
2013.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. In all
instances, please reference the Project
docket number (CP14–13–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
78351
(1) You can file your comments
electronically using the eComment
feature located on the Commission’s
Web site (www.ferc.gov) under the link
to Documents and Filings. This is an
easy method for interested persons to
submit brief, text-only comments on a
project;
(2) You can file your comments
electronically using the eFiling feature
located on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the Project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned Project.
If we publish and distribute the EA,
copies of the completed EA will be sent
to the environmental mailing list for
public review and comment. If you
would prefer to receive a paper copy of
the document instead of the CD version
or would like to remove your name from
the mailing list, please return the
attached Information Request
(Appendix 2).
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor,’’ which is an
official party to the Commission’s
E:\FR\FM\26DEN1.SGM
26DEN1
78352
Federal Register / Vol. 78, No. 248 / Thursday, December 26, 2013 / Notices
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site at https://www.ferc.gov/help/
how-to/intervene.asp.
Additional Information
Additional information about the
Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search’’ and enter the docket
number, excluding the last three digits
in the Docket Number field (i.e., CP14–
13). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: December 18, 2013.
Kimberly D. Bose,
Secretary.
Order No. 1000 Further Regional
Compliance Filing to be effective 1/1/
2015.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on January 16, 2014.
Dated: December 19, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–30832 Filed 12–24–13; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2013–30783 Filed 12–24–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
emcdonald on DSK67QTVN1PROD with NOTICES
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket No. ER14–660–000]
Orlando Utilities Commission; Notice
of Filing
Plant-E Corp; Supplemental Notice
That Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
Take notice that on December 18,
2013, Orlando Utilities Commission
submitted its tariff filing per 35.28(e):
This is a supplemental notice in the
above-referenced proceeding, of Plant-E
Corp’s application for market-based rate
[Docket No. NJ14–4–000]
VerDate Mar<15>2010
18:06 Dec 24, 2013
Jkt 232001
PO 00000
Frm 00028
Fmt 4703
Sfmt 9990
authority, with an accompanying rate
schedule, noting that such application
includes a request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR Part 34, of
future issuances of securities and
assumptions of liability is January 7,
2014.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding(s) are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: December 18, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–30697 Filed 12–24–13; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\26DEN1.SGM
26DEN1
Agencies
[Federal Register Volume 78, Number 248 (Thursday, December 26, 2013)]
[Notices]
[Pages 78350-78352]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-30783]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-13-000]
Houston Pipe Line Company, LP; Notice of Intent to Prepare an
Environmental Assessment for the Proposed 24-Inch Border Crossing
Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the 24-Inch Border Crossing
Project (Project) involving construction and operation of border
crossing facilities at the international border between Mexico and the
United States in Hidalgo County, Texas by Houston Pipe Line Company, LP
(HPL). The Commission will use this EA in its decision-making process
to determine whether the Project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the Project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on January 17, 2014.
You may submit comments in written form or verbally. Further
details on how to submit written comments are in the Public
Participation section of this notice.
This notice is being sent to the Commission's current environmental
mailing list for the Project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
HPL provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
HPL proposes to construct a new border crossing at the
international boundary between the United States and Mexico in Hidalgo
County, Texas. The Project would consist of approximately 703 feet of
24-inch-diameter natural gas pipeline, directionally drilled underneath
the Rio Grande River in Hidalgo County, Texas. The new pipeline would
have a design capacity of approximately 140 million cubic feet per day
(Mmcf/d) and a maximum allowable operating pressure of 1,300 pounds per
square inch gauge designed to transport natural gas to a new delivery
interconnect with HPL's non-jurisdictional intrastate pipeline and to a
new interconnection with the Pemex Pipeline at the United States-Mexico
border.
The general location of the Project is shown in Appendix \1\.
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would require ground
disturbance of approximately 4.1 acres of land for temporary workspace.
Following construction, HPL would maintain 0.81 acre for operation of
the Project and the remaining 3.3 acres would be revegetated.
In its application, HPL indicates that it would also construct
pipeline facilities that are not under the jurisdiction of the FERC.
Although FERC doesn't have the regulatory authority to modify or deny
the construction of these facilities, we will disclose available
information regarding the construction impacts in our EA. These
facilities would include approximately 23 miles of 24-inch-
[[Page 78351]]
diameter intrastate pipeline, to interconnect with the existing
Edinburg Lateral Pipeline in Hidalgo County, Texas.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned Project under these
general headings:
geology and soils;
water resources and fisheries;
vegetation, wildlife, and endangered and threatened
species;
land use and cumulative impacts;
cultural resources;
air quality and noise; and
public safety.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section below.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this Project to formally cooperate with us in the
preparation of the EA.\3\
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the Texas Historical Commission (THC), and to solicit their views
and those of other government agencies, interested Indian tribes, and
the public on the Project's potential effects on historic
properties.\4\ We will define the Project-specific Area of Potential
Effects in consultation with the State Historic Preservation Officer as
the Project develops. On natural gas facility projects, the Area of
Potential Effects at a minimum encompasses all areas subject to ground
disturbance (examples include construction right-of-way, contractor/
pipe storage yards, meter stations, and access roads). Our EA for this
Project will document our findings on the impacts on historic
properties and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the Project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before
January 17, 2013.
For your convenience, there are three methods you can use to submit
your comments to the Commission. In all instances, please reference the
Project docket number (CP14-13-000) with your submission. The
Commission encourages electronic filing of comments and has expert
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature located on the Commission's Web site (www.ferc.gov) under the
link to Documents and Filings. This is an easy method for interested
persons to submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature located on the Commission's Web site (www.ferc.gov) under the
link to Documents and Filings. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the Project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned Project.
If we publish and distribute the EA, copies of the completed EA
will be sent to the environmental mailing list for public review and
comment. If you would prefer to receive a paper copy of the document
instead of the CD version or would like to remove your name from the
mailing list, please return the attached Information Request (Appendix
2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor,'' which is an official party to the
Commission's
[[Page 78352]]
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in the proceeding by filing a request to
intervene. Instructions for becoming an intervenor are in the User's
Guide under the ``e-filing'' link on the Commission's Web site at
https://www.ferc.gov/help/how-to/intervene.asp.
Additional Information
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP14-
13). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: December 18, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-30783 Filed 12-24-13; 8:45 am]