Lock 14 Hydro Partners; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 77115-77116 [2013-30324]
Download as PDF
Federal Register / Vol. 78, No. 245 / Friday, December 20, 2013 / Notices
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to project works
which are the subject of the license
surrender. Agencies may obtain copies
of the application directly from the
applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: December 16, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–30320 Filed 12–19–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
emcdonald on DSK4SPTVN1PROD with NOTICES
[Project No. 13213–003]
Lock 14 Hydro Partners; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
VerDate Mar<15>2010
16:44 Dec 19, 2013
Jkt 232001
b. Project No.: 13213–003.
c. Date filed: May 16, 2012.
d. Applicant: Lock 14 Hydro Partners,
LLC.
e. Name of Project: Heidelberg Dam
Hydroelectric Project.
f. Location: At the Kentucky River
Authority’s Lock and Dam No. 14, on
the Kentucky River, near the Town of
Heidelberg, Lee County Kentucky. No
lands managed by the Federal
government are located within the
project boundary.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: David Brown
Kinloch, Lock 14 Hydro Partners, 414 S.
Wenzel Street, Louisville, Kentucky
40204, (502) 589–0975.
i. FERC Contact: Michael Spencer at
(202) 502–8365, or via email at
michael.spencer@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–13213–003.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. The Heidelberg Project consists of:
(1) An existing 248-foot-long, 17-foothigh concrete lock and dam with a 319foot-long stone piled dike adjacent to
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
77115
the lock; (2) an existing 182-acre
reservoir having a storage capacity of
1,820-acre-feet; (3) a new 40-foot-high,
52-foot-wide trashrack; (4) a new
powerhouse integral to the abandoned
lock containing four generating units for
a total installed capacity of 2,640
kilowatts; and (5) a new 1,000-foot-long,
12.47 kilo-Volt transmission line. The
project is estimated to generate an
average of 10,484,000 kilowatt-hours
annually. The existing lock and dam are
owned by the Kentucky River Authority.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
E:\FR\FM\20DEN1.SGM
20DEN1
77116
Federal Register / Vol. 78, No. 245 / Friday, December 20, 2013 / Notices
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: December 13, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–30324 Filed 12–19–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13214–003]
emcdonald on DSK4SPTVN1PROD with NOTICES
Lock 12 Hydro Partners; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: 13214–003.
c. Date filed: May 16, 2012.
d. Applicant: Lock 12 Hydro Partners,
LLC.
e. Name of Project: Ravenna Dam
Hydroelectric Project.
f. Location: At the Kentucky River
Authority’s Lock and Dam No. 12, on
the Kentucky River, near the Town of
Ravenna, Estill County Kentucky. No
lands managed by the Federal
government are located within the
project boundary.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: David Brown
Kinloch, Lock 12 Hydro Partners, 414 S.
Wenzel Street, Louisville, Kentucky
40204, (502) 589–0975.
i. FERC Contact: Michael Spencer at
(202) 502–8365, or via email at
michael.spencer@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
VerDate Mar<15>2010
16:44 Dec 19, 2013
Jkt 232001
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–13214–003.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. The Ravenna Project consists of: (1)
An existing 240-foot-long, 17-foot-high
concrete lock and dam with a 239-footlong earthen dike, adjacent to the lock;
(2) an existing 345-acre reservoir having
a storage capacity of 3,450-acre-feet; (3)
a new 40-foot-high, 52-foot-wide
trashrack; (4) a new powerhouse within
the abandoned lock chamber containing
four generating units for a total installed
capacity of 2,640 kilowatts; and (5) a
new 1,500-foot-long, 12.47 kilo-Volt
transmission line. The project is
estimated to generate an average of
10,673,000 kilowatt-hours annually. The
existing lock and dam are owned by the
Kentucky River Authority.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: December 13, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–30323 Filed 12–19–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1107–002.
Applicants: Pacific Gas and Electric
Company.
E:\FR\FM\20DEN1.SGM
20DEN1
Agencies
[Federal Register Volume 78, Number 245 (Friday, December 20, 2013)]
[Notices]
[Pages 77115-77116]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-30324]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13213-003]
Lock 14 Hydro Partners; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: 13213-003.
c. Date filed: May 16, 2012.
d. Applicant: Lock 14 Hydro Partners, LLC.
e. Name of Project: Heidelberg Dam Hydroelectric Project.
f. Location: At the Kentucky River Authority's Lock and Dam No. 14,
on the Kentucky River, near the Town of Heidelberg, Lee County
Kentucky. No lands managed by the Federal government are located within
the project boundary.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: David Brown Kinloch, Lock 14 Hydro Partners,
414 S. Wenzel Street, Louisville, Kentucky 40204, (502) 589-0975.
i. FERC Contact: Michael Spencer at (202) 502-8365, or via email at
michael.spencer@ferc.gov.
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-13213-003.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. The Heidelberg Project consists of: (1) An existing 248-foot-
long, 17-foot-high concrete lock and dam with a 319-foot-long stone
piled dike adjacent to the lock; (2) an existing 182-acre reservoir
having a storage capacity of 1,820-acre-feet; (3) a new 40-foot-high,
52-foot-wide trashrack; (4) a new powerhouse integral to the abandoned
lock containing four generating units for a total installed capacity of
2,640 kilowatts; and (5) a new 1,000-foot-long, 12.47 kilo-Volt
transmission line. The project is estimated to generate an average of
10,484,000 kilowatt-hours annually. The existing lock and dam are owned
by the Kentucky River Authority.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of
[[Page 77116]]
intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Dated: December 13, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-30324 Filed 12-19-13; 8:45 am]