Lock 12 Hydro Partners; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 77116 [2013-30323]

Download as PDF 77116 Federal Register / Vol. 78, No. 245 / Friday, December 20, 2013 / Notices intent may be filed in response to this notice. o. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Dated: December 13, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–30324 Filed 12–19–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13214–003] emcdonald on DSK4SPTVN1PROD with NOTICES Lock 12 Hydro Partners; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original Major License. b. Project No.: 13214–003. c. Date filed: May 16, 2012. d. Applicant: Lock 12 Hydro Partners, LLC. e. Name of Project: Ravenna Dam Hydroelectric Project. f. Location: At the Kentucky River Authority’s Lock and Dam No. 12, on the Kentucky River, near the Town of Ravenna, Estill County Kentucky. No lands managed by the Federal government are located within the project boundary. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: David Brown Kinloch, Lock 12 Hydro Partners, 414 S. Wenzel Street, Louisville, Kentucky 40204, (502) 589–0975. i. FERC Contact: Michael Spencer at (202) 502–8365, or via email at michael.spencer@ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the VerDate Mar<15>2010 16:44 Dec 19, 2013 Jkt 232001 Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13214–003. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is now ready for environmental analysis. l. The Ravenna Project consists of: (1) An existing 240-foot-long, 17-foot-high concrete lock and dam with a 239-footlong earthen dike, adjacent to the lock; (2) an existing 345-acre reservoir having a storage capacity of 3,450-acre-feet; (3) a new 40-foot-high, 52-foot-wide trashrack; (4) a new powerhouse within the abandoned lock chamber containing four generating units for a total installed capacity of 2,640 kilowatts; and (5) a new 1,500-foot-long, 12.47 kilo-Volt transmission line. The project is estimated to generate an average of 10,673,000 kilowatt-hours annually. The existing lock and dam are owned by the Kentucky River Authority. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. All filings must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’, ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b), and 385.2010. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Public notice of the filing of the initial development application, which has already been given, established the due date for filing competing applications or notices of intent. Under the Commission’s regulations, any competing development application must be filed in response to and in compliance with public notice of the initial development application. No competing applications or notices of intent may be filed in response to this notice. o. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Dated: December 13, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–30323 Filed 12–19–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–1107–002. Applicants: Pacific Gas and Electric Company. E:\FR\FM\20DEN1.SGM 20DEN1

Agencies

[Federal Register Volume 78, Number 245 (Friday, December 20, 2013)]
[Notices]
[Page 77116]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-30323]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13214-003]


Lock 12 Hydro Partners; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: 13214-003.
    c. Date filed: May 16, 2012.
    d. Applicant: Lock 12 Hydro Partners, LLC.
    e. Name of Project: Ravenna Dam Hydroelectric Project.
    f. Location: At the Kentucky River Authority's Lock and Dam No. 12, 
on the Kentucky River, near the Town of Ravenna, Estill County 
Kentucky. No lands managed by the Federal government are located within 
the project boundary.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: David Brown Kinloch, Lock 12 Hydro Partners, 
414 S. Wenzel Street, Louisville, Kentucky 40204, (502) 589-0975.
    i. FERC Contact: Michael Spencer at (202) 502-8365, or via email at 
michael.spencer@ferc.gov.
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-13214-003.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    l. The Ravenna Project consists of: (1) An existing 240-foot-long, 
17-foot-high concrete lock and dam with a 239-foot-long earthen dike, 
adjacent to the lock; (2) an existing 345-acre reservoir having a 
storage capacity of 3,450-acre-feet; (3) a new 40-foot-high, 52-foot-
wide trashrack; (4) a new powerhouse within the abandoned lock chamber 
containing four generating units for a total installed capacity of 
2,640 kilowatts; and (5) a new 1,500-foot-long, 12.47 kilo-Volt 
transmission line. The project is estimated to generate an average of 
10,673,000 kilowatt-hours annually. The existing lock and dam are owned 
by the Kentucky River Authority.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must (1) bear in all capital letters the title 
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in accordance with 
18 CFR 4.34(b), and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Public notice of the filing of the initial development 
application, which has already been given, established the due date for 
filing competing applications or notices of intent. Under the 
Commission's regulations, any competing development application must be 
filed in response to and in compliance with public notice of the 
initial development application. No competing applications or notices 
of intent may be filed in response to this notice.
    o. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

    Dated: December 13, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-30323 Filed 12-19-13; 8:45 am]