Environmental Impact Statements; Notice of Availability, 75919 [2013-29770]
Download as PDF
ehiers on DSK2VPTVN1PROD with NOTICES
Federal Register / Vol. 78, No. 240 / Friday, December 13, 2013 / Notices
Mitigation Measures
In the Final Hanford Comprehensive
Land-Use Plan Environmental Impact
Statement (Hanford Comprehensive
Land-Use Plan EIS (DOE/EIS–0222,
September 1, 1999) DOE identified
specific mitigation measures, policies,
and management controls that direct
land use at Hanford. DOE committed to
these mitigation measures, as
documented in the Hanford
Comprehensive Land-Use Plan EIS ROD
(64 FR 61615 November 12, 1999),
which were reaffirmed in the
Supplement Analysis, Hanford
Comprehensive Land-Use Plan EIS
(EIS–0222–SA–02, June 2, 2008) and in
the amended ROD (73 FR 55824,
September 26, 2008). These mitigation
measures will continue to be
implemented, as applicable, for the tank
waste retrieval and treatment activities
discussed in the TC&WM EIS. The
TC&WM EIS did not identify any
mitigation measures for the short-term
resource areas that are needed in
addition to those in the Supplement
Analysis, Hanford Comprehensive Land
Use Plan EIS and its amended ROD.
DOE has continued to evaluate
potential mitigation measures for the
contaminated soil at Hanford for several
years. Most recently, DOE published the
Long-Range Deep Vadose Zone Program
Plan in October 2010. This program
plan summarizes the current state of
knowledge regarding deep vadose zone
remediation challenges beneath the
Central Plateau at Hanford and DOE’s
approach to solving these challenges.
The challenges to implementing deep
vadose zone remediation are the result
of contaminant depth and spread; the
presence of multiple contaminants and
comingled waste chemistries; physical,
chemical, and biological fate and
transport mechanisms; uncertain
contaminant behavior; limited
availability and effectiveness of cleanup
remedies; and the unknown efficacy of
remediation performance over the
periods and spatial scales needed for
making decisions.
Nevertheless, all practicable means to
avoid or minimize environmental harm
for the decisions identified have been
adopted. DOE will prepare and
implement a Mitigation Action Plan to
address long-term impact areas. Longterm mitigation measures related to SST
closure will be refined and presented in
the TC&WM EIS Mitigation Action Plan,
which will be posted on the Hanford
and DOE NEPA Web sites identified in
ADDRESSES. DOE will periodically
revisit and update the Mitigation Action
Plan as appropriate prior to initiating
actions pursuant to this ROD.
VerDate Mar<15>2010
13:32 Dec 12, 2013
Jkt 232001
Issued in Washington, DC, on December 6,
2013.
David Huizenga,
Senior Advisor for Environmental
Management.
[FR Doc. 2013–29734 Filed 12–12–13; 8:45 am]
BILLING CODE 6450–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9012–5]
Environmental Impact Statements;
Notice of Availability
Responsible Agency: Office of Federal
Activities, General Information (202)
564–7146 or https://www.epa.gov/
compliance/nepa/.
Weekly receipt of Environmental Impact
Statements filed 12/02/2013 through
12/06/2013 pursuant to 40 CFR
1506.9.
Notice
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
www.epa.gov/compliance/nepa/
eisdata.html.
EIS No. 20130356, Final EIS, FRA, MS,
Tupelo Railroad Relocation Planning
and Environmental Study, Review
Period Ends: 01/13/2014, Contact:
John Winkle 202–493–6067
EIS No. 20130357, Final EIS, FHWA,
VA, Interstate 66 Corridor Tier 1 Final
Environmental Impact Statement and
Tier 1 Record of Decision, Contact:
John Simkins 804–775–3347. Under
MAP–21 section 1319, FHWA has
issued a single FEIS and ROD.
Therefore, the 30-day wait/review
period under NEPA does not apply to
this action
EIS No. 20130358, Final EIS, FHWA,
VA, Interstate 64 Peninsula, from
Interstate 95 in the City of Richmond
to Interstate 664, Review Period Ends:
01/27/2014, Contact: John Simkins
804–775–3320
EIS No. 20130359, Final EIS, AFS, CA,
Kelsey Peak Timber Sale and
Fuelbreak Project, Review Period
Ends: 01/27/2014, Contact: Jeff Jones
707–441–3553
EIS No. 20130360, Final EIS, USFS, AZ,
Rosemont Copper Project, Proposed
Mining Operation, Review Period
Ends: 01/29/2014, Contact: Mindy
Vogel 520–388–8300
EIS No. 20130361, Draft Supplement,
USACE, MN, NorthMet Mining
Project and Land Exchange, Comment
Period Ends: 03/13/2014, Contact:
PO 00000
Frm 00010
Fmt 4703
Sfmt 4703
75919
Douglas Bruner 651–290–5378. The
U.S. Army Corps of Engineers and the
U.S. Department of Agriculture’s
Forest Service are joint lead agencies
for the above project.
EIS No. 20130362, Final EIS, USFS, MT,
Montana Snowbowl Expansion,
Review Period Ends: 01/21/2014,
Contact: Tami Paulsen 406–329–3731
EIS No. 20130363, Draft EIS, DOI, 00,
PROGRAMMATIC—Deepwater
Horizon Oil Spill Natural Resources
Damage Assessment, Phase III Early
Restoration Plan, Comment Period
Ends: 02/04/2014, Contact: Nanciann
Regalado 678–296–6805
EIS No. 20130364, Final EIS, USFS, OR,
Tollgate Fuels Reduction, Review
Period Ends: 01/13/2014, Contact:
Kimpton Cooper 509–522–6009
EIS No. 20130365, Draft EIS, NMFS, CA,
Bay Delta Conservation Plan,
Comment Period Ends: 04/14/2014,
Contact: Ryan Wulff 916–930–3733
The U.S. Department of the Interior’s
Bureau of Reclamation and Fish and
Wildlife Service, the U.S. Department of
Commerce’s National Marine Fisheries
Service are joint lead agencies for the
above project.
EIS No. 20130366, Draft EIS, USACE,
LA, PROGRAMMATIC—Southwest
Coastal Louisiana Project, Comment
Period Ends: 01/27/2014, Contact:
Nathan Dayan 504–862–2530
Dated: December 10, 2013.
Cliff Rader,
Director, NEPA Compliance Division, Office
of Federal Activities.
[FR Doc. 2013–29770 Filed 12–12–13; 8:45 am]
BILLING CODE 6560–50–P
FEDERAL DEPOSIT INSURANCE
CORPORATION
Sunshine Act Meetings
Pursuant to the provisions of the
‘‘Government in the Sunshine Act’’ (5
U.S.C. 552b), notice is hereby given that
the Federal Deposit Insurance
Corporation’s Board of Directors met in
open session at 10:00 a.m. on Tuesday,
December 10, 2013, to consider the
following matters:
Discussion Agenda: Memorandum
and resolution re: The Resolution of
Systemically Important Financial
Institutions: The Single Point of Entry
Strategy.
In calling the meeting, the Board
determined, on motion of Vice
Chairman Thomas M. Hoenig, seconded
by Director Jeremiah O. Norton
(Appointive), concurred in by Director
Thomas J. Curry (Comptroller of the
Currency), Director Richard Cordray
E:\FR\FM\13DEN1.SGM
13DEN1
Agencies
[Federal Register Volume 78, Number 240 (Friday, December 13, 2013)]
[Notices]
[Page 75919]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-29770]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[ER-FRL-9012-5]
Environmental Impact Statements; Notice of Availability
Responsible Agency: Office of Federal Activities, General
Information (202) 564-7146 or https://www.epa.gov/compliance/nepa/.
Weekly receipt of Environmental Impact Statements filed 12/02/2013
through 12/06/2013 pursuant to 40 CFR 1506.9.
Notice
Section 309(a) of the Clean Air Act requires that EPA make public
its comments on EISs issued by other Federal agencies. EPA's comment
letters on EISs are available at: https://www.epa.gov/compliance/nepa/eisdata.html.
EIS No. 20130356, Final EIS, FRA, MS, Tupelo Railroad Relocation
Planning and Environmental Study, Review Period Ends: 01/13/2014,
Contact: John Winkle 202-493-6067
EIS No. 20130357, Final EIS, FHWA, VA, Interstate 66 Corridor Tier 1
Final Environmental Impact Statement and Tier 1 Record of Decision,
Contact: John Simkins 804-775-3347. Under MAP-21 section 1319, FHWA has
issued a single FEIS and ROD. Therefore, the 30-day wait/review period
under NEPA does not apply to this action
EIS No. 20130358, Final EIS, FHWA, VA, Interstate 64 Peninsula, from
Interstate 95 in the City of Richmond to Interstate 664, Review Period
Ends: 01/27/2014, Contact: John Simkins 804-775-3320
EIS No. 20130359, Final EIS, AFS, CA, Kelsey Peak Timber Sale and
Fuelbreak Project, Review Period Ends: 01/27/2014, Contact: Jeff Jones
707-441-3553
EIS No. 20130360, Final EIS, USFS, AZ, Rosemont Copper Project,
Proposed Mining Operation, Review Period Ends: 01/29/2014, Contact:
Mindy Vogel 520-388-8300
EIS No. 20130361, Draft Supplement, USACE, MN, NorthMet Mining Project
and Land Exchange, Comment Period Ends: 03/13/2014, Contact: Douglas
Bruner 651-290-5378. The U.S. Army Corps of Engineers and the U.S.
Department of Agriculture's Forest Service are joint lead agencies for
the above project.
EIS No. 20130362, Final EIS, USFS, MT, Montana Snowbowl Expansion,
Review Period Ends: 01/21/2014, Contact: Tami Paulsen 406-329-3731
EIS No. 20130363, Draft EIS, DOI, 00, PROGRAMMATIC--Deepwater Horizon
Oil Spill Natural Resources Damage Assessment, Phase III Early
Restoration Plan, Comment Period Ends: 02/04/2014, Contact: Nanciann
Regalado 678-296-6805
EIS No. 20130364, Final EIS, USFS, OR, Tollgate Fuels Reduction, Review
Period Ends: 01/13/2014, Contact: Kimpton Cooper 509-522-6009
EIS No. 20130365, Draft EIS, NMFS, CA, Bay Delta Conservation Plan,
Comment Period Ends: 04/14/2014, Contact: Ryan Wulff 916-930-3733
The U.S. Department of the Interior's Bureau of Reclamation and
Fish and Wildlife Service, the U.S. Department of Commerce's National
Marine Fisheries Service are joint lead agencies for the above project.
EIS No. 20130366, Draft EIS, USACE, LA, PROGRAMMATIC--Southwest Coastal
Louisiana Project, Comment Period Ends: 01/27/2014, Contact: Nathan
Dayan 504-862-2530
Dated: December 10, 2013.
Cliff Rader,
Director, NEPA Compliance Division, Office of Federal Activities.
[FR Doc. 2013-29770 Filed 12-12-13; 8:45 am]