Entergy Operations, Inc.; Combined License Application for Grand Gulf Unit 3; Exemption From the Requirements To Revise a Combined License Application To Comply With Enhancements to Emergency Preparedness Rule, 75381-75383 [2013-29560]
Download as PDF
Federal Register / Vol. 78, No. 238 / Wednesday, December 11, 2013 / Notices
(1) Involve a significant increase in
the probability or consequences of an
accident previously evaluated; or
(2) Create the possibility of a new or
different kind of accident from any
accident previously evaluated; or
(3) Involve a significant reduction in
a margin of safety.
(ii) There is no significant change in
the types or significant increase in the
amounts of any effluents that may be
released offsite;
The proposed action involves only a
schedule change which is
administrative in nature, and does not
involve any changes to be made in the
types or significant increase in the
amounts of effluents that may be
released offsite.
(iii) There is no significant increase in
individual or cumulative public or
occupational radiation exposure;
Since the proposed action involves
only a schedule change which is
administrative in nature, it does not
contribute to any significant increase in
occupational or public radiation
exposure.
(iv) There is no significant
construction impact;
The proposed action involves only a
schedule change which is
administrative in nature; the application
review is suspended until further
notice, and there is no consideration of
any construction at this time, and hence
the proposed action does not involve
any construction impact.
(v) There is no significant increase in
the potential for or consequences from
radiological accidents; and
The proposed action involves only a
schedule change which is
administrative in nature, and does not
impact the probability or consequences
of accidents.
(vi) The requirements from which an
exemption is sought involve:
(B) Reporting requirements:
The exemption request involves
submitting an updated FSAR by EOI
and
(G) Scheduling requirements
The proposed exemption relates to the
schedule for submitting FSAR updates
to the NRC.
emcdonald on DSK67QTVN1PROD with NOTICES
4.0
Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a)(1) and (2), the exemption is
authorized by law, will not present an
undue risk to the public health and
safety, and is consistent with the
common defense and security. Also
special circumstances are present.
Therefore, the Commission hereby
grants EOI a one-time exemption from
the requirements of 10 CFR
VerDate Mar<15>2010
17:00 Dec 10, 2013
Jkt 232001
75381
Nuclear Regulatory
Commission.
ACTION: Exemption.
for Docket ID NRC–2008–0233. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individuals listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced in this document
(if that document is available in
ADAMS) is provided the first time that
the document is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: John
Klos, Office of New Reactors, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–5136; email: John.Klos@
nrc.gov.
SUPPLEMENTARY INFORMATION: The
following sections include the text of
the exemption in its entirety as issued
to EOI.
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to a September
30, 2013 request from Entergy
Operations, Inc. (EOI) which requested
an exemption from addressing
enhancements to the Emergency
Preparedness (EP) rules in their
Combined License (COL) application.
The NRC staff reviewed this request and
determined that it is appropriate to
grant the exemption but stipulated that
the revised application must be
submitted prior to, or coincident with,
requesting the NRC to resume its review
of the COL application, or by December
31, 2014, whichever comes first.
ADDRESSES: Please refer to Docket ID
NRC–2008–0233 when contacting the
NRC about the availability of
information regarding this document.
You may access publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
1.0 Background
On February 27, 2008, EOI submitted
to the NRC a COL application for one
Economic Simplified Boiling-Water
Reactor to be constructed and operated
at the Grand Gulf Nuclear Station
(GGNS) site in Claiborne County,
Mississippi. The NRC accepted for
docketing the Grand Gulf Nuclear
Station Unit 3 (GGNS3) COL application
on April 17, 2008, (Agencywide
Documents Access and Management
System (ADAMS) Accession No.
ML081050460, Docket No. 52–024). On
January 9, 2009, EOI requested that the
NRC temporarily suspend review of the
application and the NRC granted EOI’s
request (ADAMS Accession No.
ML090080523) while the application
remained docketed. On September 30,
2013 (ADAMS Accession No.
ML13275A065), EOI requested an
exemption from the requirements of 10
CFR Part 50, Appendix E, Section I.5, as
referenced by 10 CFR 52.79(a)(21), to
submit an update by December 31, 2013,
50.71(e)(3)(iii) pertaining to the GGNS3
COL application to allow submittal of
the next FSAR update prior to, or
coincident with any request to the NRC
to resume the review, and in any event,
no later than December 31, 2014.
Pursuant to 10 CFR 51.22, the
Commission has determined that the
exemption request meets the applicable
categorical exclusion criteria set forth in
10 CFR 51.22(c)(25), and the granting of
this exemption will not have a
significant effect on the quality of the
human environment.
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 4th day
of December 2013.
For the Nuclear Regulatory Commission.
Ronaldo Jenkins,
Chief, Licensing Branch 3, Division of New
Reactor Licensing, Office of New Reactors.
[FR Doc. 2013–29562 Filed 12–10–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 52–024; NRC–2008–0233]
Entergy Operations, Inc.; Combined
License Application for Grand Gulf
Unit 3; Exemption From the
Requirements To Revise a Combined
License Application To Comply With
Enhancements to Emergency
Preparedness Rule
AGENCY:
SUMMARY:
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
E:\FR\FM\11DEN1.SGM
11DEN1
75382
Federal Register / Vol. 78, No. 238 / Wednesday, December 11, 2013 / Notices
to the COL application, addressing the
enhancements to Emergency
Preparedness (EP) rules by December
31, 2013.
emcdonald on DSK67QTVN1PROD with NOTICES
2.0
Request/Action
Title 10 of the Code of Federal
Regulations (10 CFR) Part 50, Appendix
E, Section I.5 requires that an applicant
for a COL under Subpart C of 10 CFR
Part 52 whose application was docketed
prior to December 23, 2011, must revise
their COL application to comply with
the EP rules published in the Federal
Register (76 FR 72560) on November 23,
2011. 10 CFR Part 50, Appendix E,
Section I.5 gives those COL applicants
close to receiving their COL the option
to defer addressing the changes to the
EP rules, however a license amendment
request must be submitted no later than
December 31, 2013. An applicant that
does not receive a COL before December
31, 2013, shall revise its COL
application to comply with these
changes no later than December 31,
2013.
Because EOI will not hold a COL prior
to December 31, 2013, it is therefore,
required to revise its application to be
compliant with the new EP rules by
December 31, 2013. By letter dated
January 9, 2009, EOI requested that the
NRC suspend review of the GGNS3 COL
application. The NRC granted EOI’s
request for suspension of all review
activities while the application
remained docketed (ADAMS Accession
No. ML090080523). In a letter dated,
September 30, 2013 (ADAMS Accession
No. ML13275A065), EOI requested an
exemption from the requirements of 10
CFR Part 50, Appendix E, Section I.5
until the time that EOI requests
reactivation of the GGNS3 COL
application review. Prior to, or
coincident with this reactivation
request, EOI commits to submit an
upgrade of the GGNS3 COL application
addressing the enhancements to
Emergency Preparedness Regulations.
EOI’s requested exemption is seen as
an open-ended, one-time schedule
change from the requirements of 10 CFR
Part 50, Appendix E, Section I.5.
Therefore the NRC included an imposed
December 31, 2014 deadline as part of
its review of the exemption request. The
exemption would allow EOI to comply
with the new EP rule at a later date, but
still in advance of NRC’s reinstating its
review of the application and in any
event, by December 31, 2014. The
current schedule to comply with the
new EP rule by December 31, 2013,
could not be changed, absent the
exemption.
VerDate Mar<15>2010
17:00 Dec 10, 2013
Jkt 232001
3.0
Discussion
Pursuant to 10 CFR 50.12, the
Commission may, upon application by
any interested person or upon its own
initiative, grant exemptions from the
requirements of 10 CFR Part 50,
including 10 CFR Part 50, Appendix E,
Section I.5, when: (1) The exemption(s)
are authorized by law, will not present
an undue risk to public health or safety,
and are consistent with the common
defense and security; and (2) special
circumstances are present. As relevant
to the requested exemption, special
circumstances exist if: ‘‘application of
the regulation in the particular
circumstances would not serve the
underlying purpose of the rule or is not
necessary to achieve the underlying
purpose of the rule’’ (10 CFR
50.12(a)(2)(ii)).
The purpose of 10 CFR Part 50
Appendix E, Section I.5 was to ensure
that applicants and new COL holders
updated their COL application or
Combined License to allow the NRC to
review them efficiently and effectively,
and to bring the applicants or licensees
into compliance prior to COL approval
and receipt of license, or operate the
facility. The target of Section I.5 of the
rule were those applications that were
in the process of being actively
reviewed by the NRC staff when the rule
came into effect on November 23, 2011.
Because EOI requested the NRC to
suspend its review of the GGNS3 COL
application, compelling EOI to revise its
COL application in order to meet the
December 31, 2013 compliance deadline
would only bring on unnecessary
burden and hardship for the applicant
to meet the compliance date. So long as
it is recognized that the COL application
must be updated to comply with the
enhancements to the EP rules, prior to
the NRC approving EOI’s COL
application, it makes no difference if
they revise the COL application now,
when they request the review be
restarted, or December 31, 2014. For this
reason the application of Appendix E,
Section I.5 can be deemed unnecessary,
and therefore special circumstances are
present.
Authorized by Law
The exemption is a one-time schedule
exemption from the requirements of 10
CFR Part 50, Appendix E, Section I.5.
The exemption would allow EOI to
revise its COL application and comply
with the new EP rules on or before
December 31, 2014, in lieu of December
31, 2013, the date required by 10 CFR
Part 50, Appendix E, Section I.5. As
stated above, 10 CFR 50.12 allows the
NRC to grant exemptions from the
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
requirements of 10 CFR Part 50. The
NRC staff has determined that granting
EOI the requested one-time exemption
from the requirements of 10 CFR Part
50, Appendix E, Section I.5 will be only
temporary, and will not result in a
violation of the Atomic Energy Act of
1954, as amended, or the NRC’s
regulations. Therefore, the exemption is
authorized by law.
No Undue Risk to Public Health and
Safety
The underlying purpose of the
enhancements to Emergency
Preparedness found in 10 CFR Part 50,
Appendix E is to amend certain EP
requirements which are aimed at
enhancing protective measures in the
event of a radiological emergency;
address, in part, enhancements
identified after the terrorist events of
September 11, 2001; clarify regulations
to effect consistent Emergency Plan
implementation among licensees; and
modify certain requirements to be more
effective and efficient. Since plant
construction cannot proceed until the
NRC review of the application is
completed, a mandatory hearing is
completed, and a license is issued, the
exemption does not increase the
probability of postulated accidents.
Additionally, based on the nature of the
requested exemption as described
above, no new accident precursors are
created by the exemption; thus neither
the probability, nor the consequences of
postulated accidents are increased.
Therefore, there is no undue risk to
public health and safety.
Consistent With Common Defense and
Security
The requested exemption would
allow EOI to submit the revised COL
application prior to, or coincident, with
a request of the NRC to resume the
review, and in any event, on or before
December 31, 2014. This schedule
change has no relation to security
issues. Therefore, the common defense
and security is not impacted.
Special Circumstances
Special circumstances, in accordance
with 10 CFR 50.12(a)(2)(ii), are present
whenever ‘‘application of the regulation
in the particular circumstances would
not serve the underlying purpose of the
rule or is not necessary to achieve the
underlying purpose of the rule’’ (10 CFR
50.12(a)(2)(ii)). The underlying purpose
of 10 CFR Part 50, Appendix E, Section
I.5 is to ensure that applicants are in
compliance with the new EP rules in a
time that allows the NRC to effectively
review their revised COL application
prior to issuance of the license. Because
E:\FR\FM\11DEN1.SGM
11DEN1
Federal Register / Vol. 78, No. 238 / Wednesday, December 11, 2013 / Notices
emcdonald on DSK67QTVN1PROD with NOTICES
the requirement to comply with the new
EP rules was intended for active reviews
and the GGNS3 COL application review
is now suspended, the application of
this regulation in this particular
circumstance is unnecessary in order to
achieve its underlying purpose. If the
NRC were to grant this exemption, and
EOI were then required to comply by
December 31, 2014 or prior to any
request to restart their review, the
purpose of the rule would still be
achieved. Therefore, the special
circumstances required by 10 CFR
50.12(a)(2)(ii) for the granting of an
exemption from 10 CFR Part 50,
Appendix E, Section I.5 exist.
Eligibility for Categorical Exclusion
From Environmental Review:
With respect to the exemption’s
impact on the quality of the human
environment, the NRC has determined
that this specific exemption request is
eligible for categorical exclusion as
identified in 10 CFR 51.22(c)(25) and
justified by the NRC staff as follows:
(c) The following categories of actions
are categorical exclusions:
(25) Granting of an exemption from
the requirements of any regulation of
this chapter, provided that—
(i) There is no significant hazards
consideration;
The criteria for determining whether
there is no significant hazards
consideration are found in 10 CFR
50.92. The proposed action involves
only a schedule change regarding the
submission of an update to the
application for which the licensing
review has been suspended. Therefore,
there is no significant hazards
considerations because granting the
proposed exemption would not:
(1) Involve a significant increase in
the probability or consequences of an
accident previously evaluated; or
(2) Create the possibility of a new or
different kind of accident from any
accident previously evaluated; or
(3) Involve a significant reduction in
a margin of safety.
(ii) There is no significant change in
the types or significant increase in the
amounts of any effluents that may be
released offsite;
The proposed action involves only a
schedule change which is
administrative in nature, and does not
involve any changes to be made in the
types or significant increase in the
amounts of effluents that may be
released offsite.
(iii) There is no significant increase in
individual or cumulative public or
occupational radiation exposure;
Since the proposed action involves
only a schedule change which is
VerDate Mar<15>2010
17:00 Dec 10, 2013
Jkt 232001
administrative in nature, it does not
contribute to any significant increase in
occupational or public radiation
exposure.
(iv) There is no significant
construction impact;
The proposed action involves only a
schedule change which is
administrative in nature; the application
review is suspended until further
notice, and there is no consideration of
any construction at this time, and hence
the proposed action does not involve
any construction impact.
(v) There is no significant increase in
the potential for or consequences from
radiological accidents; and
The proposed action involves only a
schedule change which is
administrative in nature, and does not
impact the probability or consequences
of accidents.
(vi) The requirements from which an
exemption is sought involve:
(B) Reporting requirements;
The exemption request involves
submitting an updated COL application
by EOI and
(G) Scheduling requirements;
The proposed exemption relates to the
schedule for submitting a COL
application update to the NRC.
4.0
Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a)(1) and (2), the exemption is
authorized by law, will not present an
undue risk to the public health and
safety, and is consistent with the
common defense and security. Also
special circumstances are present.
Therefore, the Commission hereby
grants EOI a one-time exemption from
the requirements of 10 CFR 50,
Appendix E, Section I.5 pertaining to
the Grand Gulf Unit 3 COL application
to allow submittal of the revised COL
application that complies with the new
EP rules prior to, or coincident with,
any request to the NRC to resume the
review, and in any event, no later than
December 31, 2014.
Pursuant to 10 CFR 51.22, the
Commission has determined that the
exemption request meets the applicable
categorical exclusion criteria set forth in
10 CFR 51.22(c)(25), and the granting of
this exemption will not have a
significant effect on the quality of the
human environment.
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 4th day
of December 2013.
PO 00000
Frm 00055
Fmt 4703
Sfmt 4703
75383
For the Nuclear Regulatory Commission.
Ronaldo Jenkins,
Branch Chief, Licensing Branch 3, Division
of New Reactor Licensing, Office of New
Reactors.
[FR Doc. 2013–29560 Filed 12–10–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 52–022 and 52–023; NRC–
2013–0261]
Duke Energy Progress; Shearon Harris
Units 2 and 3; Exemption From
Requirements To Revise Combined
License Applications To Address
Enhancements to Emergency
Preparedness Rules
Nuclear Regulatory
Commission.
ACTION: Exemption.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to a July 29,
2013, request from Duke Energy
Progress (DEP). On May 2, 2013, DEP
requested that the NRC suspend review
of its combined license (COL)
application until further notice. On July
29, 2013, DEP requested an exemption
from certain regulatory requirements
which, if granted, would allow them to
revise their COL application in order to
address enhancements to the Emergency
Preparedness (EP) rules within six
months of requesting the NRC to resume
the review of their COL application,
rather than by December 31, 2013, as the
regulations currently require. The NRC
staff reviewed this request and
determined that it is appropriate to
grant the exemption, but stipulated that
the revised application must be
submitted prior to requesting the NRC
resume its review of the COL
application or by December 31, 2014,
whichever comes first.
ADDRESSES: Please refer to Docket ID
NRC–2013–0261 when contacting the
NRC about the availability of
information regarding this document.
You may access publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0261. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individuals listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
SUMMARY:
E:\FR\FM\11DEN1.SGM
11DEN1
Agencies
[Federal Register Volume 78, Number 238 (Wednesday, December 11, 2013)]
[Notices]
[Pages 75381-75383]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-29560]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 52-024; NRC-2008-0233]
Entergy Operations, Inc.; Combined License Application for Grand
Gulf Unit 3; Exemption From the Requirements To Revise a Combined
License Application To Comply With Enhancements to Emergency
Preparedness Rule
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
exemption in response to a September 30, 2013 request from Entergy
Operations, Inc. (EOI) which requested an exemption from addressing
enhancements to the Emergency Preparedness (EP) rules in their Combined
License (COL) application. The NRC staff reviewed this request and
determined that it is appropriate to grant the exemption but stipulated
that the revised application must be submitted prior to, or coincident
with, requesting the NRC to resume its review of the COL application,
or by December 31, 2014, whichever comes first.
ADDRESSES: Please refer to Docket ID NRC-2008-0233 when contacting the
NRC about the availability of information regarding this document. You
may access publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0233. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individuals listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number
for each document referenced in this document (if that document is
available in ADAMS) is provided the first time that the document is
referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: John Klos, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;
telephone: 301-415-5136; email: John.Klos@nrc.gov.
SUPPLEMENTARY INFORMATION: The following sections include the text of
the exemption in its entirety as issued to EOI.
1.0 Background
On February 27, 2008, EOI submitted to the NRC a COL application
for one Economic Simplified Boiling-Water Reactor to be constructed and
operated at the Grand Gulf Nuclear Station (GGNS) site in Claiborne
County, Mississippi. The NRC accepted for docketing the Grand Gulf
Nuclear Station Unit 3 (GGNS3) COL application on April 17, 2008,
(Agencywide Documents Access and Management System (ADAMS) Accession
No. ML081050460, Docket No. 52-024). On January 9, 2009, EOI requested
that the NRC temporarily suspend review of the application and the NRC
granted EOI's request (ADAMS Accession No. ML090080523) while the
application remained docketed. On September 30, 2013 (ADAMS Accession
No. ML13275A065), EOI requested an exemption from the requirements of
10 CFR Part 50, Appendix E, Section I.5, as referenced by 10 CFR
52.79(a)(21), to submit an update by December 31, 2013,
[[Page 75382]]
to the COL application, addressing the enhancements to Emergency
Preparedness (EP) rules by December 31, 2013.
2.0 Request/Action
Title 10 of the Code of Federal Regulations (10 CFR) Part 50,
Appendix E, Section I.5 requires that an applicant for a COL under
Subpart C of 10 CFR Part 52 whose application was docketed prior to
December 23, 2011, must revise their COL application to comply with the
EP rules published in the Federal Register (76 FR 72560) on November
23, 2011. 10 CFR Part 50, Appendix E, Section I.5 gives those COL
applicants close to receiving their COL the option to defer addressing
the changes to the EP rules, however a license amendment request must
be submitted no later than December 31, 2013. An applicant that does
not receive a COL before December 31, 2013, shall revise its COL
application to comply with these changes no later than December 31,
2013.
Because EOI will not hold a COL prior to December 31, 2013, it is
therefore, required to revise its application to be compliant with the
new EP rules by December 31, 2013. By letter dated January 9, 2009, EOI
requested that the NRC suspend review of the GGNS3 COL application. The
NRC granted EOI's request for suspension of all review activities while
the application remained docketed (ADAMS Accession No. ML090080523). In
a letter dated, September 30, 2013 (ADAMS Accession No. ML13275A065),
EOI requested an exemption from the requirements of 10 CFR Part 50,
Appendix E, Section I.5 until the time that EOI requests reactivation
of the GGNS3 COL application review. Prior to, or coincident with this
reactivation request, EOI commits to submit an upgrade of the GGNS3 COL
application addressing the enhancements to Emergency Preparedness
Regulations.
EOI's requested exemption is seen as an open-ended, one-time
schedule change from the requirements of 10 CFR Part 50, Appendix E,
Section I.5. Therefore the NRC included an imposed December 31, 2014
deadline as part of its review of the exemption request. The exemption
would allow EOI to comply with the new EP rule at a later date, but
still in advance of NRC's reinstating its review of the application and
in any event, by December 31, 2014. The current schedule to comply with
the new EP rule by December 31, 2013, could not be changed, absent the
exemption.
3.0 Discussion
Pursuant to 10 CFR 50.12, the Commission may, upon application by
any interested person or upon its own initiative, grant exemptions from
the requirements of 10 CFR Part 50, including 10 CFR Part 50, Appendix
E, Section I.5, when: (1) The exemption(s) are authorized by law, will
not present an undue risk to public health or safety, and are
consistent with the common defense and security; and (2) special
circumstances are present. As relevant to the requested exemption,
special circumstances exist if: ``application of the regulation in the
particular circumstances would not serve the underlying purpose of the
rule or is not necessary to achieve the underlying purpose of the
rule'' (10 CFR 50.12(a)(2)(ii)).
The purpose of 10 CFR Part 50 Appendix E, Section I.5 was to ensure
that applicants and new COL holders updated their COL application or
Combined License to allow the NRC to review them efficiently and
effectively, and to bring the applicants or licensees into compliance
prior to COL approval and receipt of license, or operate the facility.
The target of Section I.5 of the rule were those applications that were
in the process of being actively reviewed by the NRC staff when the
rule came into effect on November 23, 2011. Because EOI requested the
NRC to suspend its review of the GGNS3 COL application, compelling EOI
to revise its COL application in order to meet the December 31, 2013
compliance deadline would only bring on unnecessary burden and hardship
for the applicant to meet the compliance date. So long as it is
recognized that the COL application must be updated to comply with the
enhancements to the EP rules, prior to the NRC approving EOI's COL
application, it makes no difference if they revise the COL application
now, when they request the review be restarted, or December 31, 2014.
For this reason the application of Appendix E, Section I.5 can be
deemed unnecessary, and therefore special circumstances are present.
Authorized by Law
The exemption is a one-time schedule exemption from the
requirements of 10 CFR Part 50, Appendix E, Section I.5. The exemption
would allow EOI to revise its COL application and comply with the new
EP rules on or before December 31, 2014, in lieu of December 31, 2013,
the date required by 10 CFR Part 50, Appendix E, Section I.5. As stated
above, 10 CFR 50.12 allows the NRC to grant exemptions from the
requirements of 10 CFR Part 50. The NRC staff has determined that
granting EOI the requested one-time exemption from the requirements of
10 CFR Part 50, Appendix E, Section I.5 will be only temporary, and
will not result in a violation of the Atomic Energy Act of 1954, as
amended, or the NRC's regulations. Therefore, the exemption is
authorized by law.
No Undue Risk to Public Health and Safety
The underlying purpose of the enhancements to Emergency
Preparedness found in 10 CFR Part 50, Appendix E is to amend certain EP
requirements which are aimed at enhancing protective measures in the
event of a radiological emergency; address, in part, enhancements
identified after the terrorist events of September 11, 2001; clarify
regulations to effect consistent Emergency Plan implementation among
licensees; and modify certain requirements to be more effective and
efficient. Since plant construction cannot proceed until the NRC review
of the application is completed, a mandatory hearing is completed, and
a license is issued, the exemption does not increase the probability of
postulated accidents. Additionally, based on the nature of the
requested exemption as described above, no new accident precursors are
created by the exemption; thus neither the probability, nor the
consequences of postulated accidents are increased. Therefore, there is
no undue risk to public health and safety.
Consistent With Common Defense and Security
The requested exemption would allow EOI to submit the revised COL
application prior to, or coincident, with a request of the NRC to
resume the review, and in any event, on or before December 31, 2014.
This schedule change has no relation to security issues. Therefore, the
common defense and security is not impacted.
Special Circumstances
Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii),
are present whenever ``application of the regulation in the particular
circumstances would not serve the underlying purpose of the rule or is
not necessary to achieve the underlying purpose of the rule'' (10 CFR
50.12(a)(2)(ii)). The underlying purpose of 10 CFR Part 50, Appendix E,
Section I.5 is to ensure that applicants are in compliance with the new
EP rules in a time that allows the NRC to effectively review their
revised COL application prior to issuance of the license. Because
[[Page 75383]]
the requirement to comply with the new EP rules was intended for active
reviews and the GGNS3 COL application review is now suspended, the
application of this regulation in this particular circumstance is
unnecessary in order to achieve its underlying purpose. If the NRC were
to grant this exemption, and EOI were then required to comply by
December 31, 2014 or prior to any request to restart their review, the
purpose of the rule would still be achieved. Therefore, the special
circumstances required by 10 CFR 50.12(a)(2)(ii) for the granting of an
exemption from 10 CFR Part 50, Appendix E, Section I.5 exist.
Eligibility for Categorical Exclusion From Environmental Review:
With respect to the exemption's impact on the quality of the human
environment, the NRC has determined that this specific exemption
request is eligible for categorical exclusion as identified in 10 CFR
51.22(c)(25) and justified by the NRC staff as follows:
(c) The following categories of actions are categorical exclusions:
(25) Granting of an exemption from the requirements of any
regulation of this chapter, provided that--
(i) There is no significant hazards consideration;
The criteria for determining whether there is no significant
hazards consideration are found in 10 CFR 50.92. The proposed action
involves only a schedule change regarding the submission of an update
to the application for which the licensing review has been suspended.
Therefore, there is no significant hazards considerations because
granting the proposed exemption would not:
(1) Involve a significant increase in the probability or
consequences of an accident previously evaluated; or
(2) Create the possibility of a new or different kind of accident
from any accident previously evaluated; or
(3) Involve a significant reduction in a margin of safety.
(ii) There is no significant change in the types or significant
increase in the amounts of any effluents that may be released offsite;
The proposed action involves only a schedule change which is
administrative in nature, and does not involve any changes to be made
in the types or significant increase in the amounts of effluents that
may be released offsite.
(iii) There is no significant increase in individual or cumulative
public or occupational radiation exposure;
Since the proposed action involves only a schedule change which is
administrative in nature, it does not contribute to any significant
increase in occupational or public radiation exposure.
(iv) There is no significant construction impact;
The proposed action involves only a schedule change which is
administrative in nature; the application review is suspended until
further notice, and there is no consideration of any construction at
this time, and hence the proposed action does not involve any
construction impact.
(v) There is no significant increase in the potential for or
consequences from radiological accidents; and
The proposed action involves only a schedule change which is
administrative in nature, and does not impact the probability or
consequences of accidents.
(vi) The requirements from which an exemption is sought involve:
(B) Reporting requirements;
The exemption request involves submitting an updated COL
application by EOI and
(G) Scheduling requirements;
The proposed exemption relates to the schedule for submitting a COL
application update to the NRC.
4.0 Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
50.12(a)(1) and (2), the exemption is authorized by law, will not
present an undue risk to the public health and safety, and is
consistent with the common defense and security. Also special
circumstances are present. Therefore, the Commission hereby grants EOI
a one-time exemption from the requirements of 10 CFR 50, Appendix E,
Section I.5 pertaining to the Grand Gulf Unit 3 COL application to
allow submittal of the revised COL application that complies with the
new EP rules prior to, or coincident with, any request to the NRC to
resume the review, and in any event, no later than December 31, 2014.
Pursuant to 10 CFR 51.22, the Commission has determined that the
exemption request meets the applicable categorical exclusion criteria
set forth in 10 CFR 51.22(c)(25), and the granting of this exemption
will not have a significant effect on the quality of the human
environment.
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 4th day of December 2013.
For the Nuclear Regulatory Commission.
Ronaldo Jenkins,
Branch Chief, Licensing Branch 3, Division of New Reactor Licensing,
Office of New Reactors.
[FR Doc. 2013-29560 Filed 12-10-13; 8:45 am]
BILLING CODE 7590-01-P