Download as PDF Federal Register / Vol. 78, No. 236 / Monday, December 9, 2013 / Notices conference facility to conduct a public vote on the results of the Fiscal Year 2013 ‘‘Creating an Innovation Culture’’ Study. The ASB board members will cast a vote to accept the results of this study and record that vote for the record according to the Army Science Board Bylaws, Article VII, Section 2 and Sunshine in the Government Act of 1976. Committee’s Designated Federal Officer (DFO)/Point of Contact: COL William McLagan at (703) 545–8651 or email: william.m.mclagan.mil@mail.mil or Ms. Carolyn German at (703) 545– 8654 or email: carolyn.t.german.civ@mail.mil. SUPPLEMENTARY INFORMATION (Filing Written Statement): Pursuant to 41 CFR 102–3.140d, the Committee is not obligated to allow the public to speak; however, interested persons may submit a written statement for consideration by the Subcommittees. Individuals submitting a written statement must submit their statement to the Designated Federal Officer (DFO) at the address listed below. Written statements not received at least 10 calendar days prior to the meeting may not be considered by the Board prior to its scheduled meeting. The DFO will review all timely submissions with the Board’s executive committee and ensure they are provided to the specific study members as necessary before, during, or after the meeting. After reviewing written comments, the study chairs and the DFO may choose to invite the submitter of the comments to orally present their issue during a future open meeting. The DFO, in consultation with the executive committee, may allot a specific amount of time for members of the public to present their issues for discussion. FOR FURTHER INFORMATION CONTACT: Army Science Board, Designated Federal Officer, 2530 Crystal Drive, Suite 7098, Arlington,VA 22202. Brenda S. Bowen, Army Federal Register Liaison Officer. maindgalligan on DSK5TPTVN1PROD with NOTICES [FR Doc. 2013–29250 Filed 12–6–13; 8:45 am] BILLING CODE 3710–08–P VerDate Mar<15>2010 17:03 Dec 06, 2013 Jkt 232001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13005–003] Oliver Hydro LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original Major License. b. Project No.: 13005–003. c. Date filed: December 14, 2011. d. Applicant: Oliver Hydro LLC. e. Name of Project: William Bacon Oliver Lock and Dam Hydroelectric Project. f. Location: At the U.S. Army Corps of Engineers’ (Corps) William Bacon Oliver Lock and Dam on the Black Warrior River, in Tuscaloosa County, Alabama. The project would occupy 8.7 acres of United States lands administered by the Corps’ Mobile District. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Vincent A. Lamarra, Symbiotics LLC, 975 South State Highway, Logan, UT 84321; (435) 752–2580; or email at vincent.lamarra@symbioticsenergy.com. i. FERC Contact: Michael Spencer at (202) 502–8365, or via email at michael.spencer@ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13005–003. PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 73853 The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is now ready for environmental analysis. l. The proposed project would utilize the Corps’ existing William Bacon Oliver Lock and Dam, and would consist of the following new facilities: (1) A forebay; (2) an intake structure; (3) a powerhouse containing two generating units with a total capacity of 11.72 megawatts (MW); (4) a 150-foot-long, 68foot-wide tailrace; (5) a proposed 1.7mile-long, 25 kilovolt (kV) transmission line; (6) a switchyard; and (7) appurtenant facilities. The proposed project would have an average annual generation of 42.6 GWh, and operate in a run-of-river mode utilizing surplus water from the William Bacon Oliver Lock and Dam, as directed by the Corps. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. All filings must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’, ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in E:\FR\FM\09DEN1.SGM 09DEN1 73854 Federal Register / Vol. 78, No. 236 / Monday, December 9, 2013 / Notices accordance with 18 CFR 4.34(b), and 385.2010. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Public notice of the filing of the initial development application, which has already been given, established the due date for filing competing applications or notices of intent. Under the Commission’s regulations, any competing development application must be filed in response to and in compliance with public notice of the initial development application. No competing applications or notices of intent may be filed in response to this notice. o. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Dated: December 2, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–29328 Filed 12–6–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission maindgalligan on DSK5TPTVN1PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2253–009. Applicants: Astoria Energy LLC. Description: Notice of Non-material Change in Status of Astoria Energy LLC. Filed Date: 11/27/13. Accession Number: 20131127–5056. Comments Due: 5 p.m. ET 12/18/13. Docket Numbers: ER11–2447–001. Applicants: Pacific Northwest Generating Cooperative, Inc. Description: Notice of change in status of Pacific Northwest Generating Cooperative, Inc. Filed Date: 11/26/13. Accession Number: 20131126–5189. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–97–000. Applicants: Midcontinent Independent System Operator, Inc. VerDate Mar<15>2010 17:03 Dec 06, 2013 Jkt 232001 Description: Supplement to October 15, 2013 Midcontinent Independent System Operator, Inc. tariff filing. Filed Date: 11/25/13. Accession Number: 20131125–5128. Comments Due: 5 p.m. ET 12/9/13. Docket Numbers: ER14–116–001. Applicants: American Electric Power Service Corporation, Ohio Power Company, AEP Ohio Transmission Company, Inc., PJM Interconnection, L.L.C. Description: AEP submits an amendment to the 39th Revised Service Agmt No. 1336 in ER14–116 to be effective 9/19/2013. Filed Date: 11/26/13. Accession Number: 20131126–5163. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–161–001. Applicants: American Electric Power Service Corporation, AEP Indiana Michigan Transmission Company, Indiana Michigan Power Company, Wabash Valley Power Association, Inc., PJM Interconnection, L.L.C. Description: AEP submits an Amendment to the 10th Revised ILDSA–PJM SA No. 1262 in ER14–161 to be effective 4/11/2013. Filed Date: 11/26/13. Accession Number: 20131126–5176. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–172–000. Applicants: ISO New England Inc. Description: ISO New England Inc. submits Supplement to Conforming Filing to be effective N/A. Filed Date: 11/27/13. Accession Number: 20131127–5083. Comments Due: 5 p.m. ET 12/18/13. Docket Numbers: ER14–463–000. Applicants: ISO New England Inc. Description: Exigent Circumstances Filing of Revisions to FCM Rules to be effective 1/24/2014. Filed Date: 11/25/13. Accession Number: 20131125–5196. Comments Due: 5 p.m. ET 12/16/13. Docket Numbers: ER14–474–000. Applicants: Sempra Generation. Description: Sempra Generation LLC Notice of Succession and MBR Tariff to be effective 11/27/2013. Filed Date: 11/26/13. Accession Number: 20131126–5115. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–475–000. Applicants: New York Independent System Operator, Inc., Rochester Gas and Electric Corporation Description: LGIA between RG&E and Allegany Generator, SA No. 2036 to be effective 11/1/2013. Filed Date: 11/26/13. Accession Number: 20131126–5125. Comments Due: 5 p.m. ET 12/17/13. PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 Docket Numbers: ER14–476–000. Applicants: Portsmouth Genco, LLC. Description: 2nd Rev MBR to be effective 11/27/2013. Filed Date: 11/26/13. Accession Number: 20131126–5131. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–477–000. Applicants: Red Oak Power, LLC. Description: 2nd Rev MBR to be effective 11/27/2013. Filed Date: 11/26/13. Accession Number: 20131126–5132. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–478–000. Applicants: James River Genco, LLC. Description: 2nd Revised MBR to be effective 11/27/2013. Filed Date: 11/26/13. Accession Number: 20131126–5148. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–479–000. Applicants: Great Bay Energy V, LLC. Description: Baseline new to be effective 12/1/2013. Filed Date: 11/26/13. Accession Number: 20131126–5150. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–480–000. Applicants: California Independent System Operator Corporation. Description: 2013–11–26_ Order764MarketChanges to be effective 4/1/2014. Filed Date: 11/26/13. Accession Number: 20131126–5175. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–481–000. Applicants: Duke Energy Carolinas, LLC. Description: Smoky Mountain IA Filing to be effective 11/1/2013. Filed Date: 11/27/13. Accession Number: 20131127–5002. Comments Due: 5 p.m. ET 12/18/13. Docket Numbers: ER14–482–000. Applicants: DTE Electric Company. Description: DTE Electric Company submits Revised Wholesale Distribution Agreements to be effective 1/1/2014. Filed Date: 11/27/13. Accession Number: 20131127–5040. Comments Due: 5 p.m. ET 12/18/13. Docket Numbers: ER14–483–000. Applicants: Niagara Mohawk Power Corporation. Description: Notice of Cancellation of Grandfathered Network Integration Transmission Service Agreement No. 118 of Niagara Mohawk Power Corporation. Filed Date: 11/26/13. Accession Number: 20131126–5187. Comments Due: 5 p.m. ET 12/17/13. Docket Numbers: ER14–484–000. Applicants: Niagara Mohawk Power Corporation. E:\FR\FM\09DEN1.SGM 09DEN1

Agencies

[Federal Register Volume 78, Number 236 (Monday, December 9, 2013)]
[Notices]
[Pages 73853-73854]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-29328]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13005-003]


Oliver Hydro LLC; Notice of Application Ready for Environmental 
Analysis and Soliciting Comments, Recommendations, Terms and 
Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: 13005-003.
    c. Date filed: December 14, 2011.
    d. Applicant: Oliver Hydro LLC.
    e. Name of Project: William Bacon Oliver Lock and Dam Hydroelectric 
Project.
    f. Location: At the U.S. Army Corps of Engineers' (Corps) William 
Bacon Oliver Lock and Dam on the Black Warrior River, in Tuscaloosa 
County, Alabama. The project would occupy 8.7 acres of United States 
lands administered by the Corps' Mobile District.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Vincent A. Lamarra, Symbiotics LLC, 975 South 
State Highway, Logan, UT 84321; (435) 752-2580; or email at 
vincent.lamarra@symbioticsenergy.com.
    i. FERC Contact: Michael Spencer at (202) 502-8365, or via email at 
michael.spencer@ferc.gov.
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-13005-003.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    l. The proposed project would utilize the Corps' existing William 
Bacon Oliver Lock and Dam, and would consist of the following new 
facilities: (1) A forebay; (2) an intake structure; (3) a powerhouse 
containing two generating units with a total capacity of 11.72 
megawatts (MW); (4) a 150-foot-long, 68-foot-wide tailrace; (5) a 
proposed 1.7-mile-long, 25 kilovolt (kV) transmission line; (6) a 
switchyard; and (7) appurtenant facilities. The proposed project would 
have an average annual generation of 42.6 GWh, and operate in a run-of-
river mode utilizing surplus water from the William Bacon Oliver Lock 
and Dam, as directed by the Corps.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must (1) bear in all capital letters the title 
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in

[[Page 73854]]

accordance with 18 CFR 4.34(b), and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Public notice of the filing of the initial development 
application, which has already been given, established the due date for 
filing competing applications or notices of intent. Under the 
Commission's regulations, any competing development application must be 
filed in response to and in compliance with public notice of the 
initial development application. No competing applications or notices 
of intent may be filed in response to this notice.
    o. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

    Dated: December 2, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-29328 Filed 12-6-13; 8:45 am]