Tennessee Valley Authority Watts Bar Nuclear Plant Unit No. 2; Order Approving Extension of Construction Permit, 72120-72122 [2013-28813]
Download as PDF
emcdonald on DSK67QTVN1PROD with NOTICES
72120
Federal Register / Vol. 78, No. 231 / Monday, December 2, 2013 / Notices
on important emerging areas in a timely
manner. EFRI awards receive support of
up to a total of $2,000,000 spread over
four years. The EFRI program has
awarded 215 research proposals since
2007.
The EFRI program is a relatively new
and substantial funding initiative.
Therefore, it is of great value to
determine the effectiveness and
outcomes of the program. This request
for OMB approval is in reference to a
pilot project to test the design and
implementation of a questionnaire
developed by the EFRI/ENG and OAD/
ENG team. The EFRI/ENG team is
seeking the assistance of an objective,
independent, third party to evaluate that
the questionnaire has a format and
scope that minimizes the burden on the
respondents. The questionnaire shall be
evaluated for its effectiveness in
capturing the data detailed in the EFRI
logic model while streamlining the
collection process and minimizing the
burden to the PI, including eliminating
any redundancies and overlap with
indicators already collected in the NSF’s
standard reporting mechanism, the
Research Performance Progress Report
(RPPR). The purpose of the
questionnaire being tested is to obtain,
on a voluntary basis, the best data
available on the outcomes of the funded
research. Because of the very unique
and innovative nature of the EFRI
grants, we are seeking to collect
additional longitudinal information
from the grantees about their research
that allows us to capture the unique
goals and purpose of the program. This
is very important to enable appropriate
and accurate evaluation of the program
and to determine whether or not the
specific goals of the program are being
met.
The questionnaire, built to reflect
upon the EFRI logic model, address the
following categories of activities: (1)
Knowledge transfer across disciplines,
(2) innovation of ideas in areas of
greater opportunity, (3) potential for
translational research, (4) project results
advance the frontier/creation of new
fields of study, (5) innovative research
methods or discoveries are introduced
to the classroom, and (6) fostering
participation of underrepresented
groups in science. For each of the
categories the questionnaire collects
information from the grantees on
specific project outputs and outcomes.
Grantees will be asked to provide
responses to the questions asked in the
questionnaire on their progress, on a
voluntary basis. To track the activity of
EFRI grants, the questionnaire collects
information on impact indicators. These
indicators are both quantitative and
VerDate Mar<15>2010
20:41 Nov 29, 2013
Jkt 232001
descriptive and may include, for
example, the achievements of EFRI
investigators and students;
characteristics of industrial and/or other
sector participation; research,
educational, and knowledge transfer
impacts; patents, licenses; publications;
new methods, significant advances,
achievements and other outcomes of the
EFRI effort.
Use of the Information: The data
collected will be used for NSF internal
reports, historical data, program level
studies and evaluations, and for
securing future funding for continued
EFRI program maintenance and growth.
Estimate of Burden: No more than 8.5
hours per grant for no greater than 20
grants (including the time to collect the
data and information).
Respondents: Principle Investigators
that lead the EFRI grants, students and
post-docs.
Estimated Number of Responses per
Report: There are 14 questions in the
questionnaire and an additional 7
questions in a student satisfaction
survey.
Dated: November 26, 2013.
Suzanne H. Plimpton,
Reports Clearance Officer, National Science
Foundation.
[FR Doc. 2013–28738 Filed 11–29–13; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
Tennessee Valley Authority Watts Bar
Nuclear Plant Unit No. 2; Order
Approving Extension of Construction
Permit
I
Tennessee Valley Authority (TVA, the
permittee) is the current holder of
Construction Permit (CP) No. CPPR–92,
issued by the Atomic Energy
Commission (now the U.S. Nuclear
Regulatory Commission (NRC or the
Commission)) on January 23, 1973
(NRC’s Agencywide Documents Access
and Management System (ADAMS)
Accession No. ML020780293), for
construction of the Watts Bar Nuclear
Plant (WBN), Unit 2. The NRC also
issued CP No. CPPR–91 for construction
of WBN Unit 1 on January 23, 1973
(ADAMS Accession No. ML020780293),
and Facility Operating License NPF–90
was issued for operation of Unit 1 on
February 7, 1996 (ADAMS Accession
No. ML073460320). The WBN Unit 2 is
currently partially completed. These
facilities are at the permittee’s site on
Frm 00061
Fmt 4703
Sfmt 4703
In March 2012, TVA completed a detailed
review of the status of WBN Unit 2
construction and developed a revised
estimate of the time and resources necessary
to complete the unit. This revised estimate
was formed after months of analyses and
consideration of numerous lessons learned as
well as detailed analyses of remaining work
associated with the Project. The estimate was
then subjected to rigorous internal and
independent external review which provided
additional assurance and high confidence in
a most likely WBN Unit 2 completion
estimate of December 2015.
The letter also states:
The only modification requested to
Construction Permit CPPR–92 is the
extension of the latest completion date. The
extension would only allow TVA more time
to complete the construction and testing of
WBN Unit 2 that is already authorized under
the existing construction permit. The
extension would not allow any work of a
type not previously authorized by the
existing construction permit to be performed.
II
[Docket No. 50–391; Permit No. CPPR–92;
NRC–2008–0369]
PO 00000
the west branch of the Tennessee River,
approximately 50 miles northeast of
Chattanooga, Tennessee.
On May 17, 2012 (ADAMS Accession
No. ML12143A346), TVA filed a request
pursuant to Section 50.55(b) of Title 10
of the Code of Federal Regulations (10
CFR) for an extension of the CP
completion date for WBN Unit 2 to
September 30, 2016. The TVA requested
this extension to the WBN Unit 2
construction permit for the following
reasons, as stated in its application:
The NRC reviewed the request dated
May 17, 2012. As discussed more fully
in the staff’s related safety evaluation,
good cause has been shown for the
delay, and the requested extension
involves no significant hazards
consideration.
The NRC staff has prepared an
environmental assessment and made a
final finding of no significant impact,
which was published in the Federal
Register on October 22, 2013 (78 FR
62,709). The NRC staff determined that
extending the construction completion
date will not have significant effect on
the quality of the human environment
and therefore, an environmental impact
statement for the proposed action would
not be prepared.
For further details regarding this
action, see TVA’s letter dated May 17,
2012, and the NRC staff’s letter and
safety evaluation of the requested
extension dated November 21, 2013
(ADAMS Accession No. ML13175A308).
III
In accordance with 10 CFR 2.202, the
Licensee, and any other person
adversely affected by this Order, may
E:\FR\FM\02DEN1.SGM
02DEN1
Federal Register / Vol. 78, No. 231 / Monday, December 2, 2013 / Notices
emcdonald on DSK67QTVN1PROD with NOTICES
submit an answer to this Order within
twenty (20) days of its publication in the
Federal Register. In addition, the
Licensee and any other person adversely
affected by this Order may request a
hearing of this Order within twenty (20)
days of its publication in the Federal
Register. Where good cause is shown,
consideration will be given to extending
the time to request a hearing. A request
for extension of time must be made, in
writing, to the Director, Office of
Nuclear Reactor Regulation, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001, and
include a statement of good cause for
the extension.
The answer may consent to this
Order. If an answer includes a request
for a hearing, it shall, under oath or
affirmation, specifically set forth the
matters of fact and law on which the
Licensee, or other adversely affected
person, relies and the reasons as to why
the Order should not have been issued.
If a person other than the Licensee
requests a hearing, that person shall set
forth with particularity the manner in
which his interest is adversely affected
by this Order and shall address the
criteria set forth in 10 CFR 2.309(d). The
scope of a construction permit extension
proceeding is limited to direct
challenges to the permit holder’s
asserted reasons that show ‘‘good cause’’
justification for the delay.
If a hearing is requested by a licensee
or a person whose interest is adversely
affected, the Commission will issue an
Order designating the time and place of
any hearings. If a hearing is held, the
issue to be considered at such hearing
shall be whether this Order should be
sustained. In the absence of any request
for hearing, or any written approval of
an extension of time in which to request
a hearing, the provisions of this Order
shall be final 20 days from the date this
Order is published in the Federal
Register without further order or
proceedings. If an extension of time for
requesting a hearing has been approved,
the provisions specified in this Order
shall be final when the extension
expires if a hearing request has not been
received.
IV
Described in 10 CFR 2.302 are the
requirements for filing of documents.
All documents filed in NRC
adjudicatory proceedings, including a
request for hearing, a petition for leave
to intervene, any motion or other
document filed in the proceeding prior
to the submission of a request for
hearing or petition to intervene, and
documents filed by interested
governmental entities participating
VerDate Mar<15>2010
20:41 Nov 29, 2013
Jkt 232001
under 10 CFR 2.315(c), must be filed in
accordance with the NRC E-Filing rule
(72 FR 49139, August 28, 2007). The EFiling process requires participants to
submit and serve all adjudicatory
documents over the internet, or in some
cases to mail copies on electronic
storage media. Participants may not
submit paper copies of their filings
unless they seek an exemption in
accordance with the procedures
described below.
To comply with the procedural
requirements of E-Filing, at least ten 10
days prior to the filing deadline, the
participant should contact the Office of
the Secretary by email at
hearing.docket@nrc.gov, or by telephone
at 301–415–1677, to request (1) a digital
identification (ID) certificate, which
allows the participant (or its counsel or
representative) to digitally sign
documents and access the E-Submittal
server for any proceeding in which it is
participating; and (2) advise the
Secretary that the participant will be
submitting a request or petition for
hearing (even in instances in which the
participant, or its counsel or
representative, already holds an NRCissued digital ID certificate). Based upon
this information, the Secretary will
establish an electronic docket for the
hearing in this proceeding if the
Secretary has not already established an
electronic docket.
Information about applying for a
digital ID certificate is available on the
NRC’s public Web site at https://
www.nrc.gov/site-help/e-submittals/
apply-certificates.html. System
requirements for accessing the ESubmittal server are detailed in the
NRC’s ‘‘Guidance for Electronic
Submission,’’ which is available on the
agency’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html. Participants may
attempt to use other software not listed
on the Web site, but should note that the
NRC’s E-Filing system does not support
unlisted software, and the NRC Meta
System Help Desk will not be able to
offer assistance in using unlisted
software.
If a participant is electronically
submitting a document to the NRC in
accordance with the E-Filing rule, the
participant must file the document
using the NRC’s online, Web-based
submission form. In order to serve
documents through the Electronic
Information Exchange System, users
will be required to install a Web
browser plug-in from the NRC’s Web
site. Further information on the Webbased submission form, including the
installation of the Web browser plug-in,
is available on the NRC’s public Web
PO 00000
Frm 00062
Fmt 4703
Sfmt 4703
72121
site at https://www.nrc.gov/site-help/esubmittals.html.
Once a participant has obtained a
digital ID certificate and a docket has
been created, the participant can then
submit a request for hearing or petition
for leave to intervene. Submissions
should be in Portable Document Format
(PDF) in accordance with NRC guidance
available on the NRC’s public Web site
at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered
complete at the time the documents are
submitted through the NRC’s E-Filing
system. To be timely, an electronic
filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern
Time on the due date. Upon receipt of
a transmission, the E-Filing system
time-stamps the document and sends
the submitter an email notice
confirming receipt of the document. The
E-Filing system also distributes an email
notice that provides access to the
document to the NRC’s Office of the
General Counsel and any others who
have advised the Office of the Secretary
that they wish to participate in the
proceeding, so that the filer need not
serve the documents on those
participants separately. Therefore,
applicants and other participants (or
their counsel or representative) must
apply for and receive a digital ID
certificate before a hearing request/
petition to intervene is filed so that they
can obtain access to the document via
the E-Filing system.
A person filing electronically using
the NRC’s adjudicatory E-Filing system
may seek assistance by contacting the
NRC Meta System Help Desk through
the ‘‘Contact Us’’ link located on the
NRC’s public Web site at https://
www.nrc.gov/site-help/esubmittals.html, by email to
MSHD.Resource@nrc.gov, or by a tollfree call at 866–672–7640. The NRC
Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have a good cause for not submitting
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial filing
requesting authorization to continue to
use alternate format and transmission of
documents. Such filings must be
submitted by: (1) First class mail
addressed to the Office of the Secretary
of the Commission, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001, Attention: Rulemakings
and Adjudications Staff, or (2) courier,
express mail, or expedited delivery
service to the Office of the Secretary,
16th Floor, One White Flint North,
E:\FR\FM\02DEN1.SGM
02DEN1
72122
Federal Register / Vol. 78, No. 231 / Monday, December 2, 2013 / Notices
11555 Rockville Pike, Rockville, MD
20852, Attention: Rulemakings and
Adjudications Staff. Participants filing a
document in this manner are
responsible for serving the document on
all other participants. Filing is
considered complete by first-class mail
as of the time of deposit in the mail, or
by courier, express mail, or expedited
delivery service upon depositing the
document with the provider of the
service. A presiding officer, having
granted an exemption request from
using E-Filing, may require a participant
or party to use E-Filing if the presiding
officer subsequently determines that the
reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory
proceedings will appear in the NRC’s
electronic hearing docket which is
available to the public at https://
ehd1.nrc.gov/ehd/, unless excluded
pursuant to an order of the Commission,
or the presiding officer. Participants are
requested not to include personal
privacy information, such as social
security numbers, home addresses, or
home phone numbers in their filings,
unless an NRC regulation or other law
requires submission of such
information. With respect to
copyrighted works, except for limited
excerpts that serve the purpose of the
adjudicatory filings and would
constitute a Fair Use application,
participants are requested not to include
copyrighted materials in their
submission.
emcdonald on DSK67QTVN1PROD with NOTICES
V
Copies of the application to extend
the completion date in the CP for WBN
Unit 2 are available for public
inspection at the NRC’s PDR, located at
One White Flint North, Room O1–F21,
11555 Rockville Pike (first floor),
Rockville, MD 20852. The application
may be accessed in ADAMS through the
NRC Library at https://www.nrc.gov/
reading-rm/adams.html under ADAMS
Accession No. ML12143A346. Persons
who do not have access to ADAMS or
who encounter problems in accessing
the documents located in ADAMS,
should contact the NRC’s PDR reference
staff by telephone at 1–800–397–4209,
or 301–415–4737, or by email to
PDR.Resource@nrc.gov.
Attorney for the permit holder: Ralph
Rodgers, Executive Vice President and
General Counsel, Tennessee Valley
Authority, 400 West Summit Hill Drive,
Knoxville, TN 37902.
VI
It is hereby ordered that the latest
completion date for CP No. CPPR–92 is
VerDate Mar<15>2010
20:41 Nov 29, 2013
Jkt 232001
extended from March 31, 2013, to
September 30, 2016.
Dated at Rockville, Maryland, this 21st day
of November 2013.
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor
Regulation.
[FR Doc. 2013–28813 Filed 11–29–13; 8:45 am]
BILLING CODE 7590–01–P
I. Accessing Information and
Submitting Comments
NUCLEAR REGULATORY
COMMISSION
[NRC–2013–0262]
Draft Emergency Preparedness
Frequently Asked Questions
Nuclear Regulatory
Commission.
ACTION: Notice of availability and
opportunity for public comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is making available
for comment Emergency Preparedness
Frequently Asked Question (EPFAQ)
No. 2013–008. This EPFAQ will be used
to provide clarification of guidance
documents related to the development
and maintenance of emergency
preparedness program elements. The
NRC is publishing these preliminary
results to inform the public and solicit
comments.
DATES: Submit comments by January 2,
2014. Comments submitted after this
date will be considered if it is practical
to do so, but assurance of consideration
cannot be given except for comments
received on or before this date.
ADDRESSES: You may submit comments
by any of the following methods (unless
this document describes a different
method for submitting comments on a
specific subject):
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0262. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual(s) listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• Mail comments to: Cindy Bladey,
Chief, Rules, Announcements, and
Directives Branch (RADB), Office of
Administration, Mail Stop: 3WFN–06–
44M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
For additional direction on accessing
information and submitting comments,
see ‘‘Accessing Information and
Submitting Comments’’ in the
SUMMARY:
PO 00000
Frm 00063
Fmt 4703
Sfmt 4703
SUPPLEMENTARY INFORMATION
section of this document.
FOR FURTHER INFORMATION CONTACT:
Carolyn Kahler, Office of Nuclear
Security and Incident Response,
telephone: 301–287–3722 or by email at:
carolyn.kahler@nrc.gov; U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
SUPPLEMENTARY INFORMATION:
A. Accessing Information
Please refer to Docket ID NRC–2013–
0262 when contacting the NRC about
the availability of information regarding
this document. You may access
publicly-available information related to
this document by any of the following
methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0262.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced in this document
(if that document is available in
ADAMS) is provided the first time that
a document is referenced. The draft
EPFAQ is available electronically under
ADAMS Accession Number
ML13323B458, and is available on the
NRC’s Web site at https://www.nrc.gov/
about-nrc/emerg-preparedness/faq/faqcontactus.html.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2013–
0262 in the subject line of your
comment submission, in order to ensure
that the NRC is able to make your
comment submission available to the
public in this docket.
The NRC cautions you not to include
identifying or contact information that
you do not want to be publicly
disclosed in you comment submission.
The NRC will post all comment
submissions at https://
www.regulations.gov as well as enter the
E:\FR\FM\02DEN1.SGM
02DEN1
Agencies
[Federal Register Volume 78, Number 231 (Monday, December 2, 2013)]
[Notices]
[Pages 72120-72122]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-28813]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-391; Permit No. CPPR-92; NRC-2008-0369]
Tennessee Valley Authority Watts Bar Nuclear Plant Unit No. 2;
Order Approving Extension of Construction Permit
I
Tennessee Valley Authority (TVA, the permittee) is the current
holder of Construction Permit (CP) No. CPPR-92, issued by the Atomic
Energy Commission (now the U.S. Nuclear Regulatory Commission (NRC or
the Commission)) on January 23, 1973 (NRC's Agencywide Documents Access
and Management System (ADAMS) Accession No. ML020780293), for
construction of the Watts Bar Nuclear Plant (WBN), Unit 2. The NRC also
issued CP No. CPPR-91 for construction of WBN Unit 1 on January 23,
1973 (ADAMS Accession No. ML020780293), and Facility Operating License
NPF-90 was issued for operation of Unit 1 on February 7, 1996 (ADAMS
Accession No. ML073460320). The WBN Unit 2 is currently partially
completed. These facilities are at the permittee's site on the west
branch of the Tennessee River, approximately 50 miles northeast of
Chattanooga, Tennessee.
On May 17, 2012 (ADAMS Accession No. ML12143A346), TVA filed a
request pursuant to Section 50.55(b) of Title 10 of the Code of Federal
Regulations (10 CFR) for an extension of the CP completion date for WBN
Unit 2 to September 30, 2016. The TVA requested this extension to the
WBN Unit 2 construction permit for the following reasons, as stated in
its application:
In March 2012, TVA completed a detailed review of the status of
WBN Unit 2 construction and developed a revised estimate of the time
and resources necessary to complete the unit. This revised estimate
was formed after months of analyses and consideration of numerous
lessons learned as well as detailed analyses of remaining work
associated with the Project. The estimate was then subjected to
rigorous internal and independent external review which provided
additional assurance and high confidence in a most likely WBN Unit 2
completion estimate of December 2015.
The letter also states:
The only modification requested to Construction Permit CPPR-92
is the extension of the latest completion date. The extension would
only allow TVA more time to complete the construction and testing of
WBN Unit 2 that is already authorized under the existing
construction permit. The extension would not allow any work of a
type not previously authorized by the existing construction permit
to be performed.
II
The NRC reviewed the request dated May 17, 2012. As discussed more
fully in the staff's related safety evaluation, good cause has been
shown for the delay, and the requested extension involves no
significant hazards consideration.
The NRC staff has prepared an environmental assessment and made a
final finding of no significant impact, which was published in the
Federal Register on October 22, 2013 (78 FR 62,709). The NRC staff
determined that extending the construction completion date will not
have significant effect on the quality of the human environment and
therefore, an environmental impact statement for the proposed action
would not be prepared.
For further details regarding this action, see TVA's letter dated
May 17, 2012, and the NRC staff's letter and safety evaluation of the
requested extension dated November 21, 2013 (ADAMS Accession No.
ML13175A308).
III
In accordance with 10 CFR 2.202, the Licensee, and any other person
adversely affected by this Order, may
[[Page 72121]]
submit an answer to this Order within twenty (20) days of its
publication in the Federal Register. In addition, the Licensee and any
other person adversely affected by this Order may request a hearing of
this Order within twenty (20) days of its publication in the Federal
Register. Where good cause is shown, consideration will be given to
extending the time to request a hearing. A request for extension of
time must be made, in writing, to the Director, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001, and include a statement of good cause for the extension.
The answer may consent to this Order. If an answer includes a
request for a hearing, it shall, under oath or affirmation,
specifically set forth the matters of fact and law on which the
Licensee, or other adversely affected person, relies and the reasons as
to why the Order should not have been issued. If a person other than
the Licensee requests a hearing, that person shall set forth with
particularity the manner in which his interest is adversely affected by
this Order and shall address the criteria set forth in 10 CFR 2.309(d).
The scope of a construction permit extension proceeding is limited to
direct challenges to the permit holder's asserted reasons that show
``good cause'' justification for the delay.
If a hearing is requested by a licensee or a person whose interest
is adversely affected, the Commission will issue an Order designating
the time and place of any hearings. If a hearing is held, the issue to
be considered at such hearing shall be whether this Order should be
sustained. In the absence of any request for hearing, or any written
approval of an extension of time in which to request a hearing, the
provisions of this Order shall be final 20 days from the date this
Order is published in the Federal Register without further order or
proceedings. If an extension of time for requesting a hearing has been
approved, the provisions specified in this Order shall be final when
the extension expires if a hearing request has not been received.
IV
Described in 10 CFR 2.302 are the requirements for filing of
documents. All documents filed in NRC adjudicatory proceedings,
including a request for hearing, a petition for leave to intervene, any
motion or other document filed in the proceeding prior to the
submission of a request for hearing or petition to intervene, and
documents filed by interested governmental entities participating under
10 CFR 2.315(c), must be filed in accordance with the NRC E-Filing rule
(72 FR 49139, August 28, 2007). The E-Filing process requires
participants to submit and serve all adjudicatory documents over the
internet, or in some cases to mail copies on electronic storage media.
Participants may not submit paper copies of their filings unless they
seek an exemption in accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least
ten 10 days prior to the filing deadline, the participant should
contact the Office of the Secretary by email at hearing.docket@nrc.gov,
or by telephone at 301-415-1677, to request (1) a digital
identification (ID) certificate, which allows the participant (or its
counsel or representative) to digitally sign documents and access the
E-Submittal server for any proceeding in which it is participating; and
(2) advise the Secretary that the participant will be submitting a
request or petition for hearing (even in instances in which the
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the
Secretary will establish an electronic docket for the hearing in this
proceeding if the Secretary has not already established an electronic
docket.
Information about applying for a digital ID certificate is
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing
the E-Submittal server are detailed in the NRC's ``Guidance for
Electronic Submission,'' which is available on the agency's public Web
site at https://www.nrc.gov/site-help/e-submittals.html. Participants
may attempt to use other software not listed on the Web site, but
should note that the NRC's E-Filing system does not support unlisted
software, and the NRC Meta System Help Desk will not be able to offer
assistance in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through the Electronic Information Exchange System,
users will be required to install a Web browser plug-in from the NRC's
Web site. Further information on the Web-based submission form,
including the installation of the Web browser plug-in, is available on
the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an email notice confirming receipt of the document. The
E-Filing system also distributes an email notice that provides access
to the document to the NRC's Office of the General Counsel and any
others who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC's public
Web site at https://www.nrc.gov/site-help/e-submittals.html, by email to
MSHD.Resource@nrc.gov, or by a toll-free call at 866-672-7640. The NRC
Meta System Help Desk is available between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial filing requesting
authorization to continue to use alternate format and transmission of
documents. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemakings and Adjudications Staff, or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, 16th Floor,
One White Flint North,
[[Page 72122]]
11555 Rockville Pike, Rockville, MD 20852, Attention: Rulemakings and
Adjudications Staff. Participants filing a document in this manner are
responsible for serving the document on all other participants. Filing
is considered complete by first-class mail as of the time of deposit in
the mail, or by courier, express mail, or expedited delivery service
upon depositing the document with the provider of the service. A
presiding officer, having granted an exemption request from using E-
Filing, may require a participant or party to use E-Filing if the
presiding officer subsequently determines that the reason for granting
the exemption from use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in the
NRC's electronic hearing docket which is available to the public at
https://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as social security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information. With
respect to copyrighted works, except for limited excerpts that serve
the purpose of the adjudicatory filings and would constitute a Fair Use
application, participants are requested not to include copyrighted
materials in their submission.
V
Copies of the application to extend the completion date in the CP
for WBN Unit 2 are available for public inspection at the NRC's PDR,
located at One White Flint North, Room O1-F21, 11555 Rockville Pike
(first floor), Rockville, MD 20852. The application may be accessed in
ADAMS through the NRC Library at https://www.nrc.gov/reading-rm/adams.html under ADAMS Accession No. ML12143A346. Persons who do not
have access to ADAMS or who encounter problems in accessing the
documents located in ADAMS, should contact the NRC's PDR reference
staff by telephone at 1-800-397-4209, or 301-415-4737, or by email to
PDR.Resource@nrc.gov.
Attorney for the permit holder: Ralph Rodgers, Executive Vice
President and General Counsel, Tennessee Valley Authority, 400 West
Summit Hill Drive, Knoxville, TN 37902.
VI
It is hereby ordered that the latest completion date for CP No.
CPPR-92 is extended from March 31, 2013, to September 30, 2016.
Dated at Rockville, Maryland, this 21st day of November 2013.
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor Regulation.
[FR Doc. 2013-28813 Filed 11-29-13; 8:45 am]